Plan Reviewer's activity | | | 6/21/2010 | | DONE |
|
|
|
Took office copy to Records.
|
Third Notice | | 3/9/2010 | 2/23/2010 | | DONE |
|
|
|
This permit finaled on the web by Matthew Evans
|
Third Notice | | 2/2/2010 | 2/23/2010 | | DONE |
|
|
|
faxed
|
Second Notice | | 1/22/2010 | 1/28/2010 | | DONE |
|
|
|
|
First Notice | | 1/8/2010 | 1/12/2010 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 12/28/2009 | 12/29/2009 | 12/29/2009 | A | PASS |
Dave Hannah
|
|
|
michael Phone #: ###-####
|
Permanent Occupancy | | | 12/29/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/29/2009 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 7/6/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/6/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/6/2009 | | DONE |
Barbara Stitt
|
|
|
Called Matt Rhees and told him that permit is ready, fees due and need GC and rce number for GC///7-6-09 @ 10:30 BAS
|
Plan assigned to (CJW) | 6/1/2009 | 6/4/2009 | 7/2/2009 | | PASS |
Carl Westfall
|
|
|
7/2/2009 15:45:08 CJW - activity updated through activity BLDA022 from case BLD09-00823.
|
Routing - PLANNING | 7/2/2009 | | 7/2/2009 | | PASS |
Sarah Schafer
|
|
|
Approved per CZC09-00112.
|
Routing - PLAN CHECK | 6/26/2009 | | 7/2/2009 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
Routing - PLAN CHECK | 7/2/2009 | | 7/2/2009 | | DONE |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/1/2009 | | |
Carl Westfall
|
|
|
Rec'd transmittal letter, and two copies of sheets A1.0 & A2.0- taken to Carl W
|
1st review completed | | | 6/26/2009 | | FAIL |
|
|
|
Failed Design Review, Plan Check
|
Routing - PLAN CHECK | 6/25/2009 | | 6/26/2009 | | |
|
|
|
Took to Land Division.
|
Routing - PLANNING Land Div | 6/26/2009 | | 6/26/2009 | | PASS |
Todd Tucker
|
|
|
|
Routing - FIRE | 6/22/2009 | 6/22/2009 | 6/25/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Route to Impact Fee Review | 6/22/2009 | 6/25/2009 | 6/22/2009 | | PASS |
Donna Wolf
|
|
|
Tenant improvements - existing.
|
Routing - PLAN CHECK | 6/4/2009 | | 6/22/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on June 15, 2009 and was finished on June 22, 2009 (6 work days). Revised drawings were required. See the plan review report. E-mailed a copy of the report to the architect, the property manager, and the tenant.
|
Routing - Design Review | 6/3/2009 | | 6/4/2009 | | FAIL |
Sarah Schafer
|
|
|
Sarah Schafer
Because there is a change in use of the space a zoning certificate needs to be processed to address parking for the site. I spoke with Matt Rhees on 6/2/09 and then spoke with the user of the space on 6/3/09 explaining the need to verify parking. They should be submitting the zoning certificate soon.
|
Routing - PUBLIC WORKS | 6/1/2009 | | 6/3/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 6/3/2009 | | 6/3/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 6/2/2009 | | 6/2/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 5/29/2009 | | 6/1/2009 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/28/2009 | | PASS |
Sam Zahorka
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/28/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/28/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 5/28/2009 | | | |
|
|
|
|