Letter of compliance/Occupancy | | | 8/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
DOC - L/C Approved | | | 8/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 4/5/2011 | 4/5/2011 | 4/5/2011 | A | PASS |
Forrest France
|
|
|
Final okay. Inspection passed- Ref. activity notes.
|
BLD-Aging Inspection | 2/14/2011 | 2/14/2011 | 2/14/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 12/15/2010 | 12/15/2010 | 12/15/2010 | P | PASS |
Dave Hannah
|
|
|
Kelly Phone #: ###-####
|
BLD-Final | 12/13/2010 | 12/13/2010 | 12/14/2010 | P | NR |
Dave Hannah
|
|
|
kelly Phone #: ###-####
|
FIRE-Final Inspection | 12/13/2010 | 12/13/2010 | 12/13/2010 | A | PASS |
Forrest France
|
|
|
Correction items finished. Fire life safety finaled.
|
FIRE-Final Inspection | 12/7/2010 | 12/8/2010 | 12/8/2010 | A | PART |
Forrest France
|
|
|
Final pending door hardware at two locations.
|
BLD-Framing/Rough-in | 10/20/2010 | 10/21/2010 | 10/21/2010 | A | PART |
Dave Hannah
|
|
|
Kelly Phone #: ###-#### ok to cover 2hr wall
|
BLD-Framing/Rough-in | 10/19/2010 | 10/20/2010 | 10/20/2010 | A | NR |
Dave Hannah
|
|
|
Kelly Phone #: ###-####
|
BLD-Conference | 8/25/2010 | 8/25/2010 | 9/1/2010 | A | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 8/25/2010 | 8/25/2010 | 8/25/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 4/28/2010 | 4/29/2010 | 4/29/2010 | A | PART |
Dave Hannah
|
|
|
zack - cover insp Phone #: ###-#### ok to cover ceiling in pn 3
|
BLD-Framing/Rough-in | 4/6/2010 | 4/7/2010 | 4/7/2010 | A | PASS |
Dave Hannah
|
|
|
zack Phone #: ###-#### ok to cover ph3 after all other trades ok for cover
|
BLD-Aging Inspection | 10/1/2009 | 10/1/2009 | 10/6/2009 | | PART |
Dave Hannah
|
|
|
wip
|
Issue & PRINT to be Invoiced | | | 7/2/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (DRS) | 6/4/2009 | | 6/29/2009 | | PASS |
Dan Stuart
|
|
|
6/29/2009 06:07:47 DRS - activity updated through activity BLDA022 from case BLD09-00860.
|
Routing - PLAN CHECK | 6/25/2009 | | 6/29/2009 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2009 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2009 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2009 | | DONE |
|
|
|
left vm for curtis at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/29/2009 | | DONE |
|
|
|
|
Routing - FIRE | 6/24/2009 | 6/24/2009 | 6/25/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/25/2009 | | PASS |
|
|
|
|
Route to Impact Fee Review | 6/24/2009 | 6/29/2009 | 6/24/2009 | | PASS |
Donna Wolf
|
|
|
Tenant improvements - Existing.
|
Routing - PLAN CHECK | 6/9/2009 | | 6/24/2009 | | PASS |
Dan Stuart
|
|
|
No resubmittals required. Routing to fire code analyst for review.
|
Routing - PLUMBING | 6/8/2009 | | 6/9/2009 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc.
|
Routing - PUBLIC WORKS | 6/4/2009 | | 6/8/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 6/5/2009 | | 6/5/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 6/4/2009 | | 6/4/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 6/3/2009 | | 6/4/2009 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 6/3/2009 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/3/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | 6/3/2009 | | | |
|
|
|
|