Third Notice | | 11/20/2009 | 11/13/2009 | | DONE |
|
|
|
|
Third Notice | | 10/25/2009 | 11/6/2009 | | DONE |
|
|
|
faxed
|
Second Notice | | 9/27/2009 | 10/15/2009 | | DONE |
|
|
|
|
First Notice | | 8/28/2009 | 9/17/2009 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/28/2009 | 8/28/2009 | 8/28/2009 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled, fire dept. access and remote manual standpipe arrangement approved per M. Sentenno.
|
BLD-Final | 8/27/2009 | 8/28/2009 | 8/28/2009 | P | PASS |
Dave Hannah
|
|
|
Joe Phone #: ###-#### ok for perm occ
|
Zoning Approval | 8/28/2009 | 8/28/2009 | 8/28/2009 | | PASS |
David Moser
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 8/28/2009 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 8/5/2009 | 8/6/2009 | 8/6/2009 | A | PASS |
Dave Hannah
|
|
|
joe Phone #: ###-#### ok to skirt
|
Issue PAID IN FULL permit | | | 7/10/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Print Occupancy Form | | | 7/9/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/9/2009 | | DONE |
|
|
|
left message w margie for don hutchinson at ###-#### - permit ready and fees given - also need ACHD receipt, GC name and rce# and rp name
|
Permit Ready to Issue | | | 7/9/2009 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 6/5/2009 | 6/12/2009 | 7/8/2009 | | PASS |
Sam Zahorka
|
|
|
7/8/2009 10:55:44 SRZ - activity updated through activity BLDA022 from case BLD09-00873.
|
Routing - PLAN CHECK | 7/7/2009 | | 7/8/2009 | | PASS |
Sam Zahorka
|
|
|
Taken to Front Desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/8/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - FIRE | 7/2/2009 | | 7/7/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan resubmittals received | | | 7/2/2009 | | |
Tisha Gallop
|
|
|
Received two copies of sheet A1.2 and response letter; inserted into plans by arch. rep. and taken back to Sam Zahorka.
|
Routing - PLAN CHECK | 6/22/2009 | | 7/2/2009 | | PASS |
Sam Zahorka
|
|
|
Passed on 6/19/2009. Routed to Fire w/ resubmittals.
|
Route to Impact Fee Review | 6/19/2009 | 6/24/2009 | 6/23/2009 | | PASS |
Donna Wolf
|
|
|
Change in use.
|
Routing - FIRE | 6/19/2009 | 6/19/2009 | 6/22/2009 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 6/22/2009 | | FAIL |
|
|
|
Failed Fire
|
Telephone call | | | 6/22/2009 | | DONE |
Scott Arellano
|
|
|
Spoke with Don Hutchinson regarding fire code plan review resubmittal item. Explained to Don that the fire code requires the furthest exterior portion of a new building or structure to be within 150 feet of an approved fire department access roadway. Submitted plans do not meet this requirement. Alternate access is available from 29th street, however the width of this access road is less than the minimum required 20 feet. Referred Don to the fire marshal, Mark Senteno, for consideration of this alternate FD access roadway.
|
Routing - PLAN CHECK | 6/12/2009 | | 6/19/2009 | | PASS |
Sam Zahorka
|
|
|
Routed to Fire.
|
Case Summary (BLD) | | | 6/18/2009 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 6/18/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLANNING | 6/12/2009 | | 6/12/2009 | | PASS |
Susan Riggs
|
|
|
CUP09-00035 Susan R.
|
Routing - PLUMBING | 6/11/2009 | | 6/12/2009 | | PASS |
Bill VanDegrift
|
|
|
provide a drain valve by the shutoff valve below frost depth. thermol expansion protection required.
|
Routing PW Drainage | | | 6/11/2009 | | PASS |
Brian Murphy
|
|
|
|
Routing - Erosion and Sediment | 6/11/2009 | | 6/11/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00317
|
Routing - PUBLIC WORKS | 6/8/2009 | | 6/11/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Design | 6/9/2009 | | 6/10/2009 | | PASS |
Jon R. Gunnerson
|
|
|
Connect to private sewer south of SMH372A
|
Routing PW Sewer Rating | 6/10/2009 | | 6/10/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 6/8/2009 | | 6/8/2009 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 6/5/2009 | | 6/8/2009 | | PASS |
Todd Tucker
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/5/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/5/2009 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCM | 6/5/2009 | | 6/5/2009 | | BLDA |
John Menard
|
|
|
6/5/2009 15:17:32 JCM - activity updated through activity BLDA160 from case BLD09-00873.
|
Intake Approval | | | 5/29/2009 | | FAIL |
Carl D Madsen
|
|
|
Grading and drainage with geotech report required, Esc permit, and othe misc items required
|
Application received | | 6/5/2009 | | | |
|
|
|
|
Application received | | 5/29/2009 | | | |
|
|
|
|