Third Notice | | 10/16/2010 | 10/19/2010 | | DONE |
|
|
|
|
Second Notice | | 10/4/2010 | 10/11/2010 | | DONE |
|
|
|
|
First Notice | | 9/18/2010 | 9/24/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/8/2010 | | DONE |
|
|
|
|
BLD-Final | 8/12/2010 | 8/12/2010 | 8/12/2010 | P | PASS |
Tony Young
|
|
|
Jim Phone #: ###-####
|
BLD-Final | 8/11/2010 | 8/12/2010 | 8/12/2010 | A | PASS |
Tony Young
|
|
|
Jim Phone #: ###-####
|
BLD-Final | 7/30/2010 | 8/2/2010 | 8/10/2010 | A | PART |
Tony Young
|
|
|
Jim Phone #: ###-####,, need final architect reports... etc. need exterior stair issues resolved
|
Zoning Approval | 8/9/2010 | 8/9/2010 | 8/9/2010 | | DONE |
Joshua Johnson
|
|
|
|
Telephone call | | | 8/5/2010 | | DONE |
|
|
|
Bud from CDHD called and said everything is ok for them.
|
BLD-Final | 7/29/2010 | 7/30/2010 | 7/30/2010 | P | PART |
Tony Young
|
|
|
Jim Phone #: ###-####,, temp ok pending others
|
FIRE-Final Inspection | 7/23/2010 | 7/26/2010 | 7/26/2010 | P | PASS |
Forrest France
|
|
|
Corrections field verified for completion. Fire life safety passed.
|
FIRE-Final Inspection | 7/22/2010 | 7/23/2010 | 7/23/2010 | A | FAIL |
Forrest France
|
|
|
Missing one EM light at the counselors room 1st floor per plan, install one exit sign with directional arrow per plan at the 1st floor north corridor, add one EM light at the basement level band room, provide one missing PFE at the 2nd floor, post max occupant signs at the cafeteria and gym as discussed. Remainder of fire life safety items okayed.
|
FIRE-Conference | 7/20/2010 | 7/20/2010 | 7/20/2010 | A | DONE |
Forrest France
|
|
|
Discussion with contractor regarding project completion and trade permit work.
|
PubWorks Occupancy Approval | 7/15/2010 | 7/15/2010 | 7/15/2010 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Other | 6/7/2010 | 6/8/2010 | 6/8/2010 | P | PASS |
Tony Young
|
|
|
jim - overhead ceiling tile cover Phone #: ###-####,, basment ok
|
BLD-Conference | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | PART |
Tony Young
|
|
|
Jim Stubbs Phone #: ###-#### stair ?s,, ceilings ok pending others
|
BLD-Other | 5/24/2010 | 5/25/2010 | 5/26/2010 | P | PASS |
Tony Young
|
|
|
ceiling cover Phone #: ###-####,, main halls ok
|
BLD-Framing/Rough-in | 5/24/2010 | 5/24/2010 | 5/24/2010 | P | PART |
Tony Young
|
|
|
ceiling cover Phone #: ###-####,, main hallway needs more firecaulking,, tie all wires,, conf on basement ceiling
|
BLD-Framing/Rough-in | 4/26/2010 | 4/26/2010 | 4/27/2010 | P | CANC |
Tony Young
|
|
|
rob Phone #: ###-####
|
BLD-Framing/Rough-in | 4/27/2010 | 4/27/2010 | 4/27/2010 | A | PART |
Tony Young
|
|
|
rob Phone #: ###-####,, grid work in progress,, also conf on north/ east landing and stair,, need to rebuild to meet code
|
BLD-Other | 4/26/2010 | 4/27/2010 | 4/27/2010 | A | PART |
Tony Young
|
|
|
rob Phone #: ###-####,, ceiling grid,, north of main level grid ok,, upper level ok
|
FIRE-Conference | 2/24/2010 | 2/24/2010 | 2/26/2010 | P | DONE |
Forrest France
|
|
|
On site meeting with project architect regarding IFC sec. 906 and IDAPA amendments.
|
FIRE-Final Inspection | 2/24/2010 | 2/24/2010 | 2/24/2010 | P | CANC |
Forrest France
|
|
|
Incorrect inspection type, not intended for final.
|
BLD-Framing/Rough-in | 2/16/2010 | 2/17/2010 | 2/17/2010 | P | PART |
Tony Young
|
|
|
Ceiling cover inspection please-Rob Phone #: ###-#### north stairs ok x 2
|
BLD-Other | 1/29/2010 | 1/29/2010 | 1/29/2010 | P | PART |
Tony Young
|
|
|
Rob this is foe the fire lid in elevator shaft Phone #: ###-####elevator room and elevator lid 1st layers ok
|
BLD-Framing/Rough-in | 1/20/2010 | 1/20/2010 | 1/20/2010 | P | PART |
Tony Young
|
|
|
Rob Phone #: ###-#### main level main lav ceiling ok
|
FIRE-Conference | 1/15/2010 | 1/15/2010 | 1/15/2010 | A | DONE |
Forrest France
|
|
|
Conference with general contractor regarding NFPA 13 2007 sec. 8.15.1.2.-8.15.2.2.
|
BLD-Framing/Rough-in | 1/14/2010 | 1/14/2010 | 1/14/2010 | P | PART |
Jim Sly
|
|
|
rob Phone #: ###-#### OK to cover chase walls located between main restrooms....1st floor....and lids at 3 small restrooms at South end bldg (Kindergarten area).
|
BLD-Framing/Rough-in | 1/7/2010 | 1/7/2010 | 1/7/2010 | P | PART |
Tom Arcoraci
|
|
|
Rob Phone #: ###-#### two hard lids south side,studs in hall for new support, non bearing walls 2 west side 1 east ok
|
BLD-Framing/Rough-in | 12/23/2009 | 12/23/2009 | 12/24/2009 | P | PART |
Tony Young
|
|
|
Rob Phone #: ###-#### hard lids in rest rooms
|
BLD-Framing/Rough-in | 12/11/2009 | 12/14/2009 | 12/14/2009 | A | PART |
Tony Young
|
|
|
Rob Phone #: ###-#### interior walls as noted on plans
|
BLD-Framing/Rough-in | 12/3/2009 | 12/4/2009 | 12/4/2009 | A | PART |
Tony Young
|
|
|
Rob Phone #: ###-#### upper floor hall way bearing walls,, pending trades ok to insulate and cover
|
BLD-Framing/Rough-in | 12/3/2009 | 12/3/2009 | 12/3/2009 | P | DEFR |
Tony Young
|
|
|
Rob Phone #: ###-#### out of time, told him he could insulate,, re scheduled for 12/4
|
BLD-Framing/Rough-in | 11/12/2009 | 11/16/2009 | 11/16/2009 | A | PART |
Tony Young
|
|
|
rob Phone #: ###-#### some interior walls,, ok pending trades r/in,,, siesmic ties in roof on So. end,, other ties ok pend engineer letter of ok
|
BLD-Framing/Rough-in | 10/27/2009 | 10/28/2009 | 10/28/2009 | A | PART |
Tony Young
|
|
|
Rob Phone #: ###-#### 2nd floor floor ties ok on north wing pending special inspection report,, also 2 ties at entry
|
BLD-Framing/Rough-in | 10/26/2009 | 10/27/2009 | 10/27/2009 | A | NR |
Tony Young
|
|
|
Rob Phone #: ###-####
|
BLD-Framing/Rough-in | 9/18/2009 | 9/21/2009 | 9/21/2009 | A | PART |
Tom Arcoraci
|
|
|
Rob Phone #: ###-#### wip ok
|
Case Summary (BLD) | | | 9/18/2009 | | |
|
|
|
|
BLD-Framing/Rough-in | 9/17/2009 | 9/17/2009 | 9/17/2009 | P | PART |
Jim Storey
|
|
|
rob Phone #: ###-#### roof straping and nailling ok marked plan as to location.
|
BLD-Framing/Rough-in | 9/4/2009 | 9/8/2009 | 9/8/2009 | P | PART |
Tony Young
|
|
|
rob Phone #: ###-#### seismic ties roof area 1 and 5
|
Print Occupancy Form | | | 7/30/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/30/2009 | | DONE |
|
|
|
left message w peggy for gregg at ###-#### - permit ready and fees given - also need gc name, rce# and rp name
|
Permit Ready to Issue | | | 7/30/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/30/2009 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 6/9/2009 | | 7/29/2009 | | PASS |
Dan Stuart
|
|
|
7/29/2009 14:06:38 DRS - activity updated through activity BLDA022 from case BLD09-00887.
|
Routing - PLAN CHECK | 7/24/2009 | | 7/29/2009 | | FAIL |
Dan Stuart
|
|
|
Routed back to PW with copy of easement from Independant School district of Boise to City of Boise City.
|
Plan resubmittals received | | | 7/29/2009 | | |
|
|
|
received 1 grant of easement taken to Dan S.
|
Routing PW Flood Plain | 7/29/2009 | | 7/29/2009 | | PASS |
Jim Wyllie
|
|
|
|
Routing - PUBLIC WORKS | 7/29/2009 | | 7/29/2009 | | PASS |
Beverly Hall
|
|
|
Plans and copy of easement grant for crane creek to BAH.
|
Routing - PLAN CHECK | 7/29/2009 | | 7/29/2009 | | PASS |
Dan Stuart
|
|
|
Plans approved by all reviewing agencies. Routing to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2009 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/29/2009 | | |
|
|
|
|
Routing PW Drainage | 7/24/2009 | | 7/24/2009 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Flood Plain | 7/24/2009 | | 7/24/2009 | | FAIL |
Jim Wyllie
|
|
|
Signed Grant of Easement Document for the Crane Creek Flume not submitted. Jim Wyllie / ###-####.
|
Plan resubmittals received | | | 7/24/2009 | | |
Dan Stuart
|
|
|
Rec'd response letter and 1 copy of SK20
|
Routing - PUBLIC WORKS | 7/24/2009 | | 7/24/2009 | | FAIL |
Beverly Hall
|
|
|
Floodplain still not approved.
|
Routing - PLAN CHECK | 7/23/2009 | | 7/24/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals for PW Drainage recieved. Routed back to PW, Brian Murphy
|
Plan resubmittals received | | | 7/23/2009 | | |
Tisha Gallop
|
|
|
Received five copies of SD1.3, SD2.0; inserted by arch. rep. and taken back to Dan Stuart
|
Routing - PUBLIC WORKS | 7/22/2009 | | 7/23/2009 | | FAIL |
Beverly Hall
|
|
|
|
Routing PW Drainage | 7/22/2009 | | 7/23/2009 | | FAIL |
Brian Murphy
|
|
|
NEEDS REVISED INVERTS LINER FOR BED. BRIAN MURPHY ###-####
|
Routing PW Flood Plain | 7/22/2009 | | 7/23/2009 | | FAIL |
Jim Wyllie
|
|
|
Signed Grant of Easement Document for the Crane Creek Flume not submitted. Jim Wyllie / ###-####
|
Routing - PLAN CHECK | 7/6/2009 | | 7/22/2009 | | FAIL |
Dan Stuart
|
|
|
Routed back to PW at request of Brian Murphy.
|
Telephone call | | | 7/22/2009 | | DONE |
|
|
|
Don Hutchison & Greg Bush confernce call to review what they had discovered. There are limits on classroom size based on the age of the students based on school district information. The district follows the suggested guidlines published by the State board of Education. A copy of this information will be provided with resubmittals. The Gym is occasionally used for special events / programs so an occupant load of 200 was being assigned the Gym. This occupant load plus the classroom size occupant loads will reduce the original 27 lavs to approximately 15 lavs. The three lav common units at the main kids restroom will be changed to provide 4 lav units. Plans are also failed in PW Drainage & PW Flood Plain.
|
Telephone call | | | 7/21/2009 | | DONE |
|
|
|
Call from Otto Gabiola, Ticker Engineers concerning the number of Lavs. I reviewed the occupant load provided by Greg Bush in e-mail and the computed number of lavs per Chapter 29 and explained that the common sinks in the classrooms could not be counted as meeting lav requirements. Lavs are in conjunction with toilets to provide sufficient hand washing stations at the restrooms based on the occupant load. Suggested Otto talk with Greg to see if there are State of Idaho classroom size standards, that perhaps the occupant load is not as great as presented based on the State regulations.
|
Telephone call | | | 7/21/2009 | | DONE |
|
|
|
Call from Greg Bush and I reviewed with him what I had reviewed with Otto Gabiola, Engineer. Based on provide occupant load, 27 lavs will be required. Thirteen lavs are available so 14 additional stations are required unless under State of Idaho / Boise School District regulations / policy the classroom size is limited and this would reduce the occupant load based on the regulations. If a lower occupant load results then less fixtures would be required.
|
Telephone call | | | 7/20/2009 | | DONE |
|
|
|
Discussion on number of Lavs and the difference of having Lavs at the restrooms and not calling the sinks in the classroom Lavs to meet Ch 29, IBC requirements. Persons using the restrooms need to wash their hands before leavinf restrooms to prevent spread of germs to door handles & other common use items. Greg Bush will check with mechanical design engineer.
|
Route to Impact Fee Review | 7/2/2009 | 7/8/2009 | 7/6/2009 | | PASS |
Cindy M. Gould
|
|
|
Remodel only no new sq footage on this permit
|
Routing - FIRE | 7/2/2009 | 7/2/2009 | 7/6/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 7/6/2009 | | FAIL |
|
|
|
Failed Public Works, Plan Check
|
Routing - PLAN CHECK | 6/24/2009 | | 7/2/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Plans routing to Fire and then Planning.
|
Routing - PLUMBING | 6/18/2009 | | 6/24/2009 | | PASS |
Bill VanDegrift
|
|
|
cleanouts required at the base of stacks and waste lines over 5'. r.p. required on water line serving hose bib in shop. additional cross connection protection may be required.
|
Plan resubmittals received | | | 6/19/2009 | | |
Dan Stuart
|
|
|
Received 5 copies of sheets SD1.1, SD1.3, SD2.0, 2 copies of O & M Reports and 2 copies of Storm Drainage reports and inserted into plans by engineers office then taken back to Plumbing inbox///6-19-09 @ 2:05pm BAS
|
Routing - Erosion and Sediment | 6/17/2009 | | 6/18/2009 | | PASS |
Steven Webb
|
|
|
ESC09-00325 plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 6/9/2009 | | 6/17/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 6/16/2009 | | 6/17/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Flood Plain | 6/15/2009 | | 6/16/2009 | | FAIL |
Jim Wyllie
|
|
|
City requires a 20 foot wide drainage easement for the operation and maintenance of the Crane Creek Flume which runs along the northwesterly boundary of the school site. City will prepare documents which need to be executed by the School District prior to issuance of a building permit. Jim Wyllie / ###-####
|
Routing PW Solid Waste | 6/16/2009 | | 6/16/2009 | | PASS |
Peter J. McCullough
|
|
|
Gates must open minimum 120 degrees; bollards will be moved per Architect.
Peter McCullough, ###-####.
|
Routing PW Drainage | 6/10/2009 | | 6/15/2009 | | FAIL |
Brian Murphy
|
|
|
NEEDS REVISIONS BRIAN MURPHY ###-####
|
Routing - Addressing | 6/10/2009 | | 6/10/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 6/8/2009 | | 6/9/2009 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/8/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/8/2009 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 6/8/2009 | | PASS |
Carl D Madsen
|
|
|
|
FIRE-Conference | 2/16/2010 | 2/16/2010 | | P | |
Forrest France
|
|
|
Don H. Phone #: ###-####
|
Application received | | 6/8/2009 | | | |
|
|
|
|
Routing - PLANNING | 6/24/2009 | | | | |
Joshua Johnson
|
|
|
Josh Johnson CUP09-00019
|