First Notice | | 7/23/2009 | 7/27/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/23/2009 | | DONE |
|
|
|
|
BLD-Final | 7/20/2009 | 7/21/2009 | 7/21/2009 | P | PASS |
Tom Arcoraci
|
|
|
James Phone #: ###-####
|
FIRE-Final Inspection | 7/20/2009 | 7/21/2009 | 7/21/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 7/13/2009 | 7/14/2009 | 7/14/2009 | P | PART |
Jim Sly
|
|
|
James Phone #: ###-#### OK for temp occ, OK for Perm Occ. when Fire Corr notice completed, and Fire finals for Perm Occ.
|
FIRE-Final Inspection | 7/13/2009 | 7/14/2009 | 7/14/2009 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the thumbturn is removed and lever hardware is provided on north warehouse exit door. Also I could not reach the sales area exit sign and emergency light test switches to see if they worked. They will need to be tested when I come back for the door hardware as per discussion with contractor.
|
Issue PAID IN FULL permit | | | 6/12/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 6/9/2009 | | 6/11/2009 | | PASS |
Tim L. Woodard
|
|
|
6/11/2009 14:13:17 TLW - activity updated through activity BLDA022 from case BLD09-00899.
|
Routing - PLAN CHECK | 6/9/2009 | | 6/11/2009 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 6/11/2009 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 6/11/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 6/11/2009 | | DONE |
|
|
|
|
Telephone call | | | 6/11/2009 | | DONE |
Barbara Stitt
|
|
|
Called James and told him that permit is ready & fees due///6-11-09 @ 3:23pm BAS
|
Permit Ready to Issue | | | 6/11/2009 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Erosion and Sediment | 6/9/2009 | | 6/9/2009 | | PASS |
Steven Webb
|
|
|
ESC plan waiver approved with attached conditions. ESC09-00328
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 6/9/2009 | | | |
|
|
|
|