First Notice | | 9/20/2010 | 9/20/2010 | | DONE |
|
|
|
Per Ken Fisher/owner rep. send FV bill to him.
|
Permanent Occupancy | | | 9/10/2010 | | DONE |
|
|
|
|
BLD-Final | 9/8/2010 | 9/8/2010 | 9/8/2010 | P | PASS |
Jim Sly
|
|
|
Please call 1/2 hour prior, thanks. Phone #: ###-#### >> Inspection requested via web by Darren Gossett OK for Perm Occ.
|
FIRE-Final Inspection | 9/8/2010 | 9/8/2010 | 9/8/2010 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 9/7/2010 | 9/8/2010 | 9/8/2010 | A | CANC |
Jim Sly
|
|
|
Please call 1/2 hour prior, thanks. Phone #: ###-#### >> Inspection requested via web by Darren Gossett Inspection cancelled from web by: Darren Gossett
|
BLD-Final | 9/2/2010 | 9/7/2010 | 9/7/2010 | A | CANC |
Jim Sly
|
|
|
Please call 1/2 hour prior, thanks. Phone #: ###-#### >> Inspection requested via web by Darren Gossett Inspection cancelled from web by: Darren Gossett
|
FIRE-Final Inspection | 9/2/2010 | 9/3/2010 | 9/3/2010 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm permit signed off.
|
BLD-Final | 9/1/2010 | 9/2/2010 | 9/2/2010 | P | CANC |
Jim Sly
|
|
|
Darren Phone #: ###-#### Inspection cancelled from web by: Darren Gossett
|
FIRE-Final Inspection | 9/1/2010 | 9/2/2010 | 9/2/2010 | A | CANC |
Troy Cobbley
|
|
|
Darren Phone #: ###-####
|
BLD-Other | 11/19/2009 | 11/20/2009 | 11/20/2009 | A | PASS |
Jim Sly
|
|
|
Please call 1/2 upon arrival,thanks. Phone #: ###-#### Internet Inspection Request from: Darren Gossett Grid OK
|
BLD-Wall cover | 11/17/2009 | 11/18/2009 | 11/18/2009 | A | PASS |
Jim Sly
|
|
|
please call 1/2 hour upon arrival, thanks. Phone #: ###-#### Internet Inspection Request from: Darren Gossett
|
BLD-Final | 10/22/2009 | 10/22/2009 | 10/22/2009 | A | PART |
Jim Sly
|
|
|
Please call 1/2 hour upon arrival, thanks.
Darren Phone #: ###-#### Internet Phased project. Phase 1 ....OK.......signed off on approved plan. Inspection Request from: Darren Gossett
|
BLD-Final | 10/21/2009 | 10/23/2009 | 10/22/2009 | A | CANC |
Jim Sly
|
|
|
Please call 1/2 upon arrival, thanks.
Darren Phone #: ###-#### Internet Inspection Request from: Darren Gossett Inspection cancelled from web by: Darren Gossett
|
FIRE-Final Inspection | 10/21/2009 | 10/21/2009 | 10/21/2009 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in Phase I of this project.
|
FIRE-Final Inspection | 10/20/2009 | 10/20/2009 | 10/20/2009 | A | CANC |
Troy Cobbley
|
|
|
Cancelled per Darren Gossett. To be rescheduled.
|
BLD-Other | 10/8/2009 | 10/8/2009 | 10/8/2009 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/8/2009 at 7:04:40 AM. Contact: ###-####. Grid OK
|
FIRE-Conference | 10/1/2009 | 10/2/2009 | 10/2/2009 | A | DONE |
Troy Cobbley
|
|
|
Per conversation between Darren with HC Company, Mark Sentenno and myself areas of this project will be phased. The tenant will be able to occupy the remodeled areas as long as all fire alarm, fire sprinkler and fire life safety items are complete in the occupied remodeled areas. A final will be given when the entire project is complete.
|
BLD-Framing/Rough-in | 9/25/2009 | 9/28/2009 | 9/28/2009 | A | PART |
Jim Sly
|
|
|
Please call one 1/2 hour upon arrival, thanks. Darren Phone #: ###-#### Internet Inspection Request from: Darren Gossett
Phase 1 ....OK
|
Issue PAID IN FULL permit | | | 9/24/2009 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 6/18/2009 | 6/22/2009 | 9/2/2009 | | PASS |
Carl Westfall
|
|
|
9/2/2009 11:37:31 CJW - activity updated through activity BLDA022 from case BLD09-00946.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/2009 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/2/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/2/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/2/2009 | | DONE |
|
|
|
|
Telephone call | | | 9/2/2009 | | DONE |
|
|
|
Called Margie permit ready and fee given Also need GC #
|
Routing - PLAN CHECK | 8/24/2009 | | 9/2/2009 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review.
|
Plan resubmittals received | | | 9/1/2009 | | |
Carl Westfall
|
|
|
Rec'd 2 copies of sheet A2.02- taken to Carl W
|
Routing - PLAN CHECK | 7/20/2009 | | 8/24/2009 | | FAIL |
Carl Westfall
|
|
|
Completed the 2nd plan review. Two items not resolved. Waiting for resubmittals.
|
Plan resubmittals received | | | 8/20/2009 | | |
Tisha Gallop
|
|
|
received transmittal, response comments, HVAC report, and two copies of structural calcs, plan cover sheet and sheets A0.01, A0.02, A0.05, A1.01, A2.01, A2.02, A7.01, A8.01, M0.0, M1.1, M1.2, M2.1, M2.2, E1.01; taken to Carl Westfall
|
Routing - FIRE | 7/14/2009 | 7/14/2009 | 7/20/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 7/20/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 7/14/2009 | 7/17/2009 | 7/14/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 6/22/2009 | | 7/14/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on July 13, 2009 and was finished the next day. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 6/18/2009 | | 6/22/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - Addressing | 6/19/2009 | | 6/19/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 6/18/2009 | | 6/18/2009 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/17/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/17/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 6/17/2009 | | | |
|
|
|
|