| Plan Reviewer's activity | | | 3/8/2011 | | DONE |
Sam Zahorka
|
|
|
The contractor Curt Barber requested all activities concerning this permit. I printed them out and suggested he request a public records request to obtain all records. SRZ
|
| BLD-Final | 2/17/2011 | 2/22/2011 | 2/22/2011 | A | PASS |
Mike Jordan
|
|
|
curt - please call 1/2 hr prior so he can meet you there Phone #: ###-####. Ok for perm occ.
|
| Zoning Approval | 2/22/2011 | 2/22/2011 | 2/22/2011 | | PASS |
Josh Wilson
|
|
|
Ok per DRH09-00190
|
| Permanent Occupancy | | | 2/22/2011 | | DONE |
|
|
|
|
| FIRE-Final Inspection | 2/16/2011 | 2/17/2011 | 2/17/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
| PubWorks Occupancy Approval | 2/10/2011 | 2/10/2011 | 2/10/2011 | | DONE |
Tiffany Lowery
|
|
|
|
| Telephone call | | | 1/7/2011 | | DONE |
Sam Zahorka
|
|
|
Telephone call with the contractor Curt Barber to discuss options for an assumed property line between buildings. The contractor Curt Barber is trying to modify his permits and get rid of a Fire Flow issue. SRZ
|
| Plan Reviewer's activity | | | 11/24/2010 | | DONE |
Sam Zahorka
|
|
|
Curt Barber picked up the updated permit and a new occupancy card. I let him know Fire, Building, and Public works still need to sign-off.
|
| Telephone call | | | 11/22/2010 | | DONE |
Sam Zahorka
|
|
|
I spoke with the owner Mr. Tom Bolens on the telephone. I explained to him the mezzanine and bathroom have been removed from this permit upon his request with no refund of any fees. I let him know future permits will be required to construct the mezzanine, bathroom, and any racking for storage. I requested the approved plans be brought to my office. I would then change the scope of his permit removing the mezzanine, bathroom, and shell language. I also let him know a new occupancy card would be issued and all signatures are needed prior to final. SRZ
|
| Routing - PLAN CHECK | 11/22/2010 | | 11/22/2010 | | PASS |
Sam Zahorka
|
|
|
Received the approved plans from the contractor Curt Barber. Red-lined plans removing the mezzanine, shell language, and reprinted the permit summary and attached to the plans, and produced a new occupancy card for signatutres.
|
| Print Occupancy Form | | | 11/22/2010 | | DONE |
|
|
|
|
| CHANGE STATUS TO (ISS) | | | 11/22/2010 | | DONE |
Sam Zahorka
|
|
|
|
| FIRE-Conference | 11/12/2010 | 11/15/2010 | 11/15/2010 | A | DONE |
Troy Cobbley
|
|
|
I left address and permit information on both Mark Sentenno's and Scott Arellano's voice mails.
|
| FIRE-Conference | 11/12/2010 | 11/12/2010 | 11/12/2010 | P | DONE |
Troy Cobbley
|
|
|
Kurt; phone ###-####. Kurt and I spoke about the missing fire hydrant. I deferred him to Scott Arellano. I also afterward spoke to Mark Senteno. A conference has been set up for monday to bring scott and mark up to speed on project status.
|
| FIRE-Conference | 11/10/2010 | 11/10/2010 | 11/10/2010 | P | DONE |
Troy Cobbley
|
|
|
I met with Tom Bolens and discussed the missing fire hydrant shown on resubmittal sheet A1.0. I deferred him to Scott Arellano for requirement information.
|
| Telephone call | | | 11/10/2010 | | DONE |
Sam Zahorka
|
|
|
I spoke with the owner Tom Bolens and verified no mezzanine or restroom will be built at this time. Mr. Bolens gave permission to remove the mezzanine and restroom from the scope of his permit and off of his approved plans. I explained to Mr. Bolens he will not be re-funded any fees paid. I also informed Mr. Bolens he would be required to obtain new permits in the future to construct the mezzanine and/or restroom. This permit was originally submitted as a Shell/Core permit by the registered design professional. The owner wants to occupy this building therefore the shell language was removed from the scope and a occupancy card was created.
|
| FIRE-Final Inspection | 11/9/2010 | 11/9/2010 | 11/9/2010 | P | FAIL |
Troy Cobbley
|
|
|
Provide two Fire Lane - No Parking signs and post them as discussed and provide verification with plan review about possible resubmittals due to the mezzanine not being built.
|
| Inspection Record Card- Bld | | | 11/9/2010 | | DONE |
Tisha Gallop
|
|
|
|
| Plan Reviewer's activity | | | 11/9/2010 | | DONE |
Sam Zahorka
|
|
|
This was never suppose to be a shell permit. The registered design proffessional (Ward Schwider) submitted this as a shell building initially though. The owners intention was to occupy this building as a storage building for the existing building located on the same site. The mezzanine located on the approved plans has been removed. The scope of work has been updated to remove the mezzanine, remove the shell language, and a new occupancy card will be issued. Future permits for the mezzanine, bethroom, and racking are required. SRZ
|
| BLD-Other | 9/22/2010 | 9/22/2010 | 9/22/2010 | P | PASS |
Mike Jordan
|
|
|
shear inspection//Curt Phone #: ###-####. interior shear walls ok.
|
| Telephone call | | | 7/6/2010 | | DONE |
Sam Zahorka
|
|
|
Recieved a telephone call from Curt Barber with Custom Steel. He asked questions about a note on the plans concerning occupancy. I let him know what Section 110 of the 2006 IBC, Certificate of Occupancy says.
|
| BLD-Framing/Rough-in | 6/14/2010 | 6/15/2010 | 6/15/2010 | A | PART |
Mike Jordan
|
|
|
Curt please call 30 min before going out Phone #: ###-####. Ok to install osb roof deck and exterior metal siding. Verified holdowns and all straps.
|
| BLD-Footing | 4/19/2010 | 4/20/2010 | 4/20/2010 | A | PASS |
Mike Jordan
|
|
|
john - rebar Phone #: ###-####. Welded wire mesh and #4 rebar @ 4ft. on center for interior slab on grade ok. Constructed as per approved plans.
|
| BLD-Footing | 4/6/2010 | 4/7/2010 | 4/7/2010 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####.. Reviewed special inspection report on epox dowels for misplaced vertical reinforcement at piers. Also reviewed clarification and reinspected reinforcement for piers. ok for concrete.
|
| BLD-Foundation | 4/6/2010 | 4/6/2010 | 4/6/2010 | P | PART |
Mike Jordan
|
|
|
ben Phone #: ###-####. Noted that contractor incorrectly placed verts in several loactions at piers. This will require an rfi from engineer of record for repair and special inspection if required. Contractor to also get clarification on pier detail regarding the #3 rebar at 6 inches on center.
|
| BLD-Footing | 4/1/2010 | 4/1/2010 | 4/1/2010 | P | PASS |
Jim Storey
|
|
|
jay - late afternoon please Phone #: ###-####
|
| Routing PW Drainage | 3/29/2010 | | 3/30/2010 | | PASS |
Brian Murphy
|
|
|
|
| Routing - PUBLIC WORKS | 3/30/2010 | | 3/30/2010 | | PASS |
Connie Baumgartner
|
|
|
|
| Routing - PLAN CHECK | 3/30/2010 | | 3/30/2010 | | PASS |
Sam Zahorka
|
|
|
Plan modification is to simply move the new building location closer to the existing building. Sarah Schafer with Planning and Zoning, Brian Murphy with public works, and Building Plan Review have reviewed this modification and have passed.
|
| CHANGE STATUS TO (ISS) | | | 3/30/2010 | | DONE |
Sam Zahorka
|
|
|
|
| BLD-Footing | 3/26/2010 | 3/29/2010 | 3/29/2010 | A | NR |
Mike Jordan
|
|
|
curt - late morning please Phone #: ###-####. Spoke with curt this morning, he noted some set back issues with bldg. Noted that bldg. is going to have to be moved 3ft. closer to exisiting bldg. to meet the rear setback. Noted to curt to contact plan review and zoning. Plans may have to be resubmitted to city for approval.
|
| Telephone call | | | 3/29/2010 | | DONE |
Sam Zahorka
|
|
|
I received a telephone call from the contractor Curt Barber. He stated they need to move the building closer to the existing building in order to meet their rear setbacks. I told him to resubmit plans showing the changes as a plan modification. SRZ
|
| Plan Modification Accepted | | | 3/29/2010 | | DONE |
Sam Zahorka
|
|
|
Plan modification received. Routed plans to Public Works and Planning for approvals.
|
| Routing - PLANNING | 3/29/2010 | | 3/29/2010 | | PASS |
Josh Wilson
|
|
|
Site plan change OK'd per Sarah Schafer.
|
| Issue PAID IN FULL permit | | | 3/18/2010 | | DONE |
Tisha Gallop
|
|
|
|
| Routing - Erosion and Sediment | 2/22/2010 | | 2/23/2010 | | PASS |
Steven Webb
|
|
|
ESC plan approved according to the permit's attached conditions. ESC09-00356
|
| Routing - PLAN CHECK | 2/23/2010 | | 2/23/2010 | | PASS |
Sam Zahorka
|
|
|
Sam Z.
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2010 | | DONE |
Sam Zahorka
|
|
|
|
| Inspection Record Card- Bld | | | 2/23/2010 | | DONE |
Tisha Gallop
|
|
|
|
| Permit Ready to Issue | | | 2/23/2010 | | DONE |
Tisha Gallop
|
|
|
|
| Telephone call | | | 2/23/2010 | | DONE |
Tisha Gallop
|
|
|
called Curt Barber/Custon Steel Sturctures and told him permit is ready, fees and need ACHD.
|
| Plan assigned to (SRZ) | 6/19/2009 | | 2/23/2010 | | PASS |
Sam Zahorka
|
|
|
2/23/2010 14:47:12 SRZ - activity updated through activity BLDA022 from case BLD09-00962.
|
| Routing - PLAN CHECK | 1/22/2010 | | 2/22/2010 | | PEND |
Sam Zahorka
|
|
|
Pending ESC to pass. 2/22/2010 - Recieved resubmittals and routed to ESC. SRZ
|
| Plan resubmittals received | | | 2/22/2010 | | DONE |
|
|
|
received 3 esc narratives,& 2 copies of site plan sent to Sam Z.
|
| Routing - PLANNING Land Div | 2/5/2010 | | 2/5/2010 | | PASS |
Dave Abo
|
|
|
Three platted lots have been combined into a single parcel.
|
| Case Summary (BLD) | | | 2/5/2010 | | DONE |
|
|
|
|
| Routing - PUBLIC WORKS | 1/20/2010 | | 1/22/2010 | | PASS |
Beverly Hall
|
|
|
|
| Routing PW Drainage | 1/20/2010 | | 1/22/2010 | | PASS |
Brian Murphy
|
|
|
|
| Routing - PLAN CHECK | 1/12/2010 | | 1/20/2010 | | PEND |
Sam Zahorka
|
|
|
Pending others to pass.
|
| Plan resubmittals received | | | 1/20/2010 | | |
Tisha Gallop
|
|
|
received five copies of drainage report and plan sheets A1.0, 1 of 1 (drainage plan); inserted by Ward Schwider and taken back to Sam Zahorka
|
| Routing - PUBLIC WORKS | 12/24/2009 | | 1/12/2010 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Brian Murphy - Drainage Coordinator - ###-####
|
| Routing PW Drainage | 12/29/2009 | | 1/12/2010 | | FAIL |
Brian Murphy
|
|
|
Need to ID irrigation line or move swales, dimension swales, elevation for front valley gutter to swale ect Brian Murphy ###-####.
|
| Routing - Erosion and Sediment | 1/12/2010 | | 1/12/2010 | | FAIL |
Steven Webb
|
|
|
ESC plan still does not comply with BMC 8-17. I did not see any re-submittal since the Plan Review Checklist was prepared and sent to applicant, September 22, 2009. Narrative and plan does not agree with each other. ESC09-00356
|
| Plan resubmittals received | | | 1/6/2010 | | |
Tisha Gallop
|
|
|
received six copies of sheet A1.0 and five copies of sheet 1 of 1 (grading/drainage); inserted by Ward Schwider and plans taken back to Brian Murphy.
|
| Routing - Addressing | 12/29/2009 | | 12/29/2009 | | PASS |
April Wing
|
|
|
|
| Routing - PLUMBING | 12/21/2009 | | 12/23/2009 | | PASS |
Bill VanDegrift
|
|
|
united water will require the warehouse to have it's own meter and service. dcva and thermol expansion protection.
|
| Plan resubmittals received | | | 12/23/2009 | | DONE |
|
|
|
Rec'd 5 copies of sheet A1.0 for Brian Murphy- inserted by Ward and taken back to Sam
|
| Telephone call | | | 12/17/2009 | | DONE |
Sam Zahorka
|
|
|
Called Curt Barber and let him know the status of the plans. The plans are still needing resubmittals for other reviewing departments. SRZ
|
| Routing - PUBLIC WORKS | 12/11/2009 | | 12/15/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
| Routing PW Drainage | 12/11/2009 | | 12/15/2009 | | FAIL |
Brian Murphy
|
|
|
O AND M PLAN STAMP PROPERTY LINE SCALED DRAWING LENGHT AND WIDTH SAND FILTERS
|
| Telephone call | | | 12/15/2009 | | DONE |
Sam Zahorka
|
|
|
Called the architect and the owner. I requested a permit extension letter by tomorrow 12/16/09 in order to have request for permit application extension granted. SRZ
|
| Extend Review Timeline | | | 12/15/2009 | | DONE |
Jenifer Gilliland
|
|
|
|
| Routing Off Site - STRUCTURAL | 12/10/2009 | | 12/15/2009 | | PASS |
Tisha Gallop
|
|
|
Recieved structural corrections.
Received Final comments from the Structural Reviewer.
|
| Plan Reviewer's activity | | | 12/11/2009 | | DONE |
Sam Zahorka
|
|
|
Emailed the City of Boise plan review expiration letter to the Architect and owner. Waiting for resubmittals to be able to issue permit.
|
| Plan resubmittals received | | | 12/11/2009 | | |
Tisha Gallop
|
|
|
received five copies of sheet 1 of 1 (Drainage Plan); inserted into plans by Ward Schwider and taken back to Sam Zahorka
|
| Routing - PLAN CHECK | 12/4/2009 | | 12/10/2009 | | PEND |
Sam Zahorka
|
|
|
Passed Plan Review. Pending others to Pass.
|
| Telephone call | | | 12/10/2009 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
| Case Summary (BLD) | | | 12/10/2009 | | DONE |
Sam Zahorka
|
|
|
|
| Telephone call | | | 12/10/2009 | | DONE |
Sam Zahorka
|
|
|
Contacted the Architect by telephone. I let him know I red-lined a few missed items. I asked for new Comcheck compliance certificates for envelope, exterior lighting, interior lighting, and mechanical. I requested he email these certificates and I would attach them to the plans for him. I then asked if there were any corrections for other departments made in the resubmittals so I could route them to the next department. He then asked who still needed corrections. I explained the plans are still in Fail status in Public Works, Planning Land division, Plumbing, Structural review, and Erosion Sediment Control. He asked for ESC departments number and I gave it to him. Permit issuance is pending all revieiwing agencies approvals. I stated to Mr. Schwider I would wait until I get resubmittals before I route them again. SRZ
|
| Plan resubmittals received | | | 12/8/2009 | | |
Tisha Gallop
|
|
|
received one copy of exterior lighting compliance cert., response to comment from architect, three coipies of plan review response from engineer, structural calculations, plan sheets A2.0, A2.1; inserted by Ward Schweider and taken back to Sam Z.
|
| Routing - FIRE | 11/30/2009 | | 12/4/2009 | | PASS |
Scott Arellano
|
|
|
Plan sheet A-1, dated 11/17/09, indicates the installation of one new fire hydrant along West Woodlark Street. The design and installation of the new fire hydrant shall be under the direction of United Water. Contact John Lee of U.W. (###-####) for further information. Attached updated IFC comments to plans. Emailed updated fire code comments to building owner, architect, and general contractor. Final approval will be subject to satisfactory field inspection by the PDS Fire inspector.
|
| Telephone call | | | 12/3/2009 | | DONE |
Sam Zahorka
|
|
|
I telephoned the owner Mr. Bolen and offered my assistance in understanding what is still needed to complete plan reviews from all reviewing agencies to achieve building permit issuance for his project. I offered the PDS online tools for him to be able to track his permit and activities. He stated he was vey appreciative and felt he would be able to stay on top of progress now with his permitting processes.
|
| Plan Reviewer's activity | | | 12/3/2009 | | DONE |
Sam Zahorka
|
|
|
I emailed a response letter to the owner, architect, and the contractor explaining what is still needed for permit issuance. THe letter is attached under documents.
|
| Routing Off Site - STRUCTURAL | 11/19/2009 | | 12/3/2009 | | FAIL |
Tisha Gallop
|
|
|
Recieved Structural Reviewers 3rd correction report. Emailed to the Architect.
|
| Routing - PLAN CHECK | 11/17/2009 | | 12/1/2009 | | FAIL |
Sam Zahorka
|
|
|
Waiting for letter from the owner to complete third IBC plan Review. Routed to Planning.
12/1/09 Recieved letter as requested. Plans failed due to other corrections. Emailed the Plan Review correction report to the Architect, Contractor, and the Owner.
|
| Routing - PLANNING | 11/24/2009 | | 11/25/2009 | | PASS |
Josh Wilson
|
|
|
Exterior Beezeway added to connect existing building and the proposed new building.
|
| Telephone call | | | 11/25/2009 | | DONE |
Sam Zahorka
|
|
|
Spoke with the Architect this morning and requested the letter again from the owner describing storage materials and defining the area of retail/mercantile so I can complete a third review. Let the architect know I routed the plans to Planning and Zoning due to the exterior changes. He stated some Fire review corrections were made and I let him know ounce I recieved the plans back from Planning I would route them to Fire for another review. SRZ
|
| Telephone call | | | 11/19/2009 | | DONE |
Tisha Gallop
|
|
|
called action couriers for pick up
|
| Meeting | | | 11/17/2009 | | DONE |
Sam Zahorka
|
|
|
Attended an unscheduled meeting with the Contractor and the Architect. Requested re-submittals and answered questions concerning what exactly is needed to keep this project moving. I requested the Architect to submit an appeal letter to the Building Official explaining why he feels the occupancy classification as an M has been incorrectly interpreted. Waiting on a third set to be submitted along with a submittal transmittal letter detailing exactly what has been addressed/corrected and what department needs to complete a new review based on comments/corrections given. SRZ
|
| Plan resubmittals received | | | 11/17/2009 | | |
Sam Zahorka
|
|
|
Received 3 copies of sheet A0.0, A1.0, A2.0, A2.1, A3.0, building permit data from Ada County, zoning certificate from Ada County and taken to Sam Zahorka///11-17-09 BAS
|
| Telephone call | | | 11/13/2009 | | DONE |
Sam Zahorka
|
|
|
Recieved an email from the Architect Ward Schwider stating "What's the word on this project? Owner is getting pretty upset." I then called Mr. schwider back and explained that we were still waiting for his resubmittals and third set to send to Structural review. He then stated he had brought the resubmittals in along with the third set. I found the plans at the front counter, there still is only two sets, and the plans look like they have been pulled apart. I asked Alex the permit technician and she stated Ward had never finished inserting the re-submittal sheets or delivering the third set of plans. SRZ
|
| Meeting | | | 11/3/2009 | | DONE |
Scott Arellano
|
|
|
Meeting with Mark Senteno and Scott Arellano. The fire marshal has agreed to approve the FD access roadway with the following conditions: 1) no parking designation within 25 feet of the 16' x 14' roll up door of the proposed new building to the north of the property and, 2) no parking designation in front of the northeast exterior door located in the existing warehouse.
Emailed architect updated fire code review comments indicating approval of FD access road with conditions.
|
| Plan resubmittals received | | | 11/3/2009 | | |
Sam Zahorka
|
|
|
Rec'd two copies A1.0; taken to Sam Z
|
| Telephone call | | | 11/2/2009 | | DONE |
Scott Arellano
|
|
|
Ward Schweider emailed requesting a meeting with the fire division to further explain the fire code resubmittal items.
|
| Telephone call | | | 10/29/2009 | | DONE |
Sam Zahorka
|
|
|
Called architect to check status of re-submittals. Still waiting for third set drawings in order to route to structural reviewer. could not leave message due to telephone mailbox being full.
|
| Telephone call | | | 10/28/2009 | | DONE |
Scott Arellano
|
|
|
Ward Schweider telephoned inquiring into what the resubmittal requirements were for fire code plan review because he had not received fire plan review comments. Fire plan review comments we're posted online and emailed to the permit applicant on July 24th, 2009. However, at this time no comments we're faxed to the applicant because the permit application did not include a fax number.
Informed Architect of the following fire code resubmittal items: 1) The furthest exterior portion of the proposed building addition is not within 150 feet of the approved FD access roadway and does not meet the requirements of IFC 503.1.1; and 2) The proposed building addition increases the minimum required fire flow to 3,000 gpm, per IFC appendix "B". A minimum of 3 fire hydrants are now required to meet IFC table C105.1. Only one fire hydrant was shown on plans along Woodlark Street. City records indicate the next available fire hydrant to be 744 lineal feet from the hydrant shown on plans which exceeds the 400 ft average spacing requirement of IFC C105.1.
We discussed the addition of a new fire hydrant along West Woodlark street to address item number 2. Resent fire code review comments to architects via email.
|
| Plan resubmittals received | | | 10/23/2009 | | |
Tisha Gallop
|
|
|
Received response to comments, 8 1/2" x 11" copy of sheet A1.0 (ESC & Site plan), O & M report (1 page), two copies of structural calculations and plan sheets A3.0, A2.0, A2.1; taken to Sam Zahorka.
|
| Telephone call | | | 10/23/2009 | | DONE |
Sam Zahorka
|
|
|
Called architect and requested another set of plans with re-submittals. He stated he would deliver another set of plans to the city. I let him know I would wait to route the plans until I recieved the third set.
|
| Routing - PLUMBING | 9/29/2009 | | 9/29/2009 | | FAIL |
Bill VanDegrift
|
|
|
no resubmitals
|
| Routing - PLANNING | 9/24/2009 | | 9/25/2009 | | PASS |
Josh Wilson
|
|
|
Routed to Josh Wilson, per DRH09-00190
|
| Routing - PLANNING Land Div | 9/23/2009 | | 9/23/2009 | | FAIL |
Dave Abo
|
|
|
Still need to combine three platted lots into one parcel. Same comment as 6/19/09.
|
| Routing - Erosion and Sediment | 9/21/2009 | | 9/22/2009 | | FAIL |
Steven Webb
|
|
|
Narrative and ESC blueprint does not meet requirements of BMC 8-17. Plan and narrative must agree with one another and prepared by Boise City certified plan preparer. Checklist faxed to Chad Jones. Re-submittal required.
|
| Routing - PUBLIC WORKS | 9/17/2009 | | 9/21/2009 | | FAIL |
Beverly Hall
|
|
|
|
| Routing PW Drainage | 9/18/2009 | | 9/21/2009 | | FAIL |
Brian Murphy
|
|
|
NEED REVISED PLAN. BRIAN MURPHY ###-####
|
| Telephone call | | | 9/18/2009 | | DONE |
Sam Zahorka
|
|
|
Recieved telephone call from Ward Schwider the Architect stating this project does not have a Mercantile Occupancy. The permit application says the building is used for office/storage and Sales. The information on the internet says this buisiness is a Wholesale Electronics distribution store. The Architect also stated there is a customer counter at the front of the building accessible to the public to pick up their electronic parts and pay for them.
|
| Meeting | | | 9/17/2009 | | DONE |
Sam Zahorka
|
|
|
Attended unscheduled meeting with Ward Schwider the Architect and the Contractor for this project. Went over 2nd Plan Review corrections item by item to insure understanding of what is needed to achieve code compliance on the plans to be able to pass plan review. I gave the permit activities to the contractor so he could identify all departments that still need resubmittals in order to pass his project through the system. I then routed the plans to the Public Works department.
|
| Routing - PLAN CHECK | 7/24/2009 | | 9/16/2009 | | FAIL |
Sam Zahorka
|
|
|
2nd IBC review completed. Emailed corrections to the Architect. Routed on to Planning.
|
| Meeting | | | 9/15/2009 | | DONE |
Sam Zahorka
|
|
|
Held meeting with Mr. Curt Barber the contractor and explained the status of this permit and what is needed to complete the permitting process. All reviewing departments must pass before issuance. Let him know I'm currently reviewing re-submittals. I requested he speak with his architect to expedite the plan review process. SRZ
|
| Routing Off Site - STRUCTURAL | 8/28/2009 | | 9/8/2009 | | FAIL |
Sam Zahorka
|
|
|
Recieved Structural Reviewers 2nd correction report. Emailed to the Architect.
|
| Plan resubmittals received | | | 8/28/2009 | | |
Tisha Gallop
|
|
|
received three copies structural calculations and plan sheets A2.0, A2.1; inserted by LEG and taken back to Sam Zahorka
|
| Telephone call | | | 8/28/2009 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
| Routing - FIRE | 7/20/2009 | 7/20/2009 | 7/24/2009 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal items to architect. Fax number not provided by RDP.
|
| 1st review completed | | | 7/24/2009 | | FAIL |
|
|
|
Failed Public Works, Erosion & Soil Control, Structural, Plumbing, Planning, Plan Check, Fire
|
| Route to Impact Fee Review | 7/20/2009 | 7/23/2009 | 7/21/2009 | | PASS |
Cindy M. Gould
|
|
|
|
| Routing - PLAN CHECK | 7/8/2009 | | 7/20/2009 | | FAIL |
Sam Zahorka
|
|
|
Plan Corrections sent to the Architect. Routed to Fire Review.
|
| Case Summary (BLD) | | | 7/17/2009 | | DONE |
|
|
|
|
| Routing Off Site - STRUCTURAL | 6/19/2009 | | 7/10/2009 | | FAIL |
Sam Zahorka
|
|
|
Called Action Couriers for pick up
7/10/09 Emailed to the Architect.
|
| Routing - PLANNING | 7/7/2009 | | 7/8/2009 | | FAIL |
Cody Riddle
|
|
|
Staff level design review approval required. Called architect and left voicemail regarding requirement at 10:30. CER
|
| Routing - PLUMBING | 7/1/2009 | | 7/7/2009 | | FAIL |
Bill VanDegrift
|
|
|
existing sewer service under proposed office addition will need to be schedule 40. united water will require the proposed warehouse to have its own meter and service. resubmit addressing these two items.
|
| Plan resubmittals received | | | 7/2/2009 | | |
Sam Zahorka
|
|
|
Rec'd 2 copies of A1.0 and ESc narrative/plan- inserted by architect and taken back to plumbing
|
| Routing - Erosion and Sediment | 6/30/2009 | | 7/1/2009 | | FAIL |
Steven Webb
|
|
|
ESC plan does not meet requirements according to BMC 8-17. No narrative was included in the submittal and a Boise City Certified plan designer is required to prepare the plan.
|
| Routing - PUBLIC WORKS | 6/19/2009 | | 6/30/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
| Routing PW Street Lights | 6/30/2009 | | 6/30/2009 | | PASS |
Hank Alarcon
|
|
|
|
| Routing PW Sewer Design | 6/23/2009 | | 6/30/2009 | | PASS |
Jon R. Gunnerson
|
|
|
Connect onto existing sanitary sewer service line.
|
| Routing PW Solid Waste | | | 6/30/2009 | | PASS |
Peter J. McCullough
|
|
|
|
| Routing PW Sewer Rating | 6/23/2009 | | 6/23/2009 | | PASS |
Connie Baumgartner
|
|
|
|
| Routing PW Drainage | 6/23/2009 | | 6/23/2009 | | FAIL |
Brian Murphy
|
|
|
need revision to o and m, stamp, strucural letter and grading plans ect
|
| Routing - PLANNING Land Div | 6/19/2009 | | 6/19/2009 | | FAIL |
Dave Abo
|
|
|
Do not issue building permit until all three lots are combined into one buildable parcel.
|
| Plans ACCEPTED BY PLAN TECH | | | 6/19/2009 | | DONE |
|
|
|
Ok per Dan S for New Commercial intake meeting
|
| Plan routing begun/NEW & ADDTN | | | 6/19/2009 | | DONE |
|
|
|
|
| Pending Assignment by JCM | 6/19/2009 | | 6/19/2009 | | BLDA |
John Menard
|
|
|
6/19/2009 08:50:27 JCM - activity updated through activity BLDA160 from case BLD09-00962.
|
| Application received | | 6/18/2009 | 6/18/2009 | | DONE |
Darla L Downs
|
|
|
|
| Routing - PUBLIC WORKS | 3/29/2010 | | | | |
Connie Baumgartner
|
|
|
Building location has changed. There is no longer 10 ft. between buildings. See plans. This is a plan modification. Brian Murphy for grading and drainage?
|
| Routing - PUBLIC WORKS | 3/29/2010 | | | | |
Barbara Moore
|
|
|
|