Permit NumberBLD09-00980
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 4610 W HILLCREST DR
Project NameHillcrest Country Club
Customer Number08-007
ePlanReviewNo
Description
Hillcrest Country Club - Phase I Addition and Remodel - Phase I includes remodel of the entire building on the west side of the fire wall, plus 750 square feet on the east side of the fire wall (everything west of grid line S). To demo and remove the structure at the Garden Court areas. To demo and removed most of the interior partitions, ceilings and finishes, except at Mech/Elect Room #124 and the stairways. Demo and remove a large portion of the west exterior wall, planters and exterior stairways. To construct a new 4,150 sq. ft. basement and 3,875 sq. ft., wood framed first floor addition on the west end of the existing club house building. To construct new covered patio and entry areas. To refinish the interior to include new men's and women's lounges, showers, locker rooms and restrooms, new golf shop, fitness area, kitchen and bar/dining area. There is a two-hour, masonry fire wall constructed at grid line Q. The area of the Phase I project is 18,900 square feet with a 11,900 square foot basement. This building is fully fire sprinkled. The sprinklers are used for area increase. The area on the west side of the fire wall is 18,150 sq. ft. with an 11,900 sq. ft. basement; the area on the east side of the fire wall is 21,710 sq. ft. with a 1,535 sq. ft. basement. This permit is for Phase I of the project only. A separate tenant improvement permit will be required to finish Phase II. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 10/21/201010/12/2010 DONE
This permit finaled on the web by Brandon Byington
First Notice 9/30/201010/11/2010 DONE
Permanent Occupancy  9/20/2010 DONE
DetailsTisha Gallop
BLD-Final7/29/20107/30/20107/30/2010APASS
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by Mike Shain
FIRE-Final Inspection7/26/20107/27/20107/27/2010APASS
DetailsTroy Cobbley
Life safety for phase 1 passed.
FIRE-Final Inspection7/9/20107/12/20107/12/2010AFAIL
DetailsTroy Cobbley
The project related fire sprinkler permit needs addressed and "indicators" and "stickers" shall be provided per IFC 1008.1.8.3 (2.1) and (2.2) at doors 126A, 130A and 132B.
FIRE-Final Inspection7/8/20107/9/20107/9/2010ACANC
DetailsTroy Cobbley
To be rescheduled for monday
FIRE-Final Inspection6/8/20106/9/20106/9/2010APART
DetailsTroy Cobbley
A temporary was given with Marks permission until the remaining life safety items previously listed are addressed.
BLD-Final6/8/20106/9/20106/9/2010APART
DetailsTom Arcoraci
Inspection requested from web by: Mike Shain Phone #: ###-#### ok for temp, ok for final when hardware is complete
FIRE-Final Inspection6/2/20106/2/20106/2/2010AFAIL
DetailsTroy Cobbley
This inspection entry is for phone conversations between Mike and I and discussions with Jason and John. Item #1: Per Jason and John the exit doors from the covered patio into the main corridor will be allowed to have key locking hardware as long as all requirements are met such as the indicator, sticker also an exit sign is required above the door as well as emergency lighting in the covered patio area. Item #2: Per John and I's discussion the pocket/half door at the bar will not be required to have accessible hardware as long as the pocket door is in the open position during business hours. Item #3: Per Jason and I's discussion the three sets of double doors from the Pro Shop, Fitness Area and Dining Area will not be allowed to have manual flush bolts in the inactive leaf or keyed locking hardware on the egress side of the active leaf. These doors must comply with IFC 1008.1.8.3 and 1008.1.8.4.
FIRE-Final Inspection5/26/20106/1/20106/1/2010AFAIL
DetailsTroy Cobbley
See correction notice for deficiencies.
PubWorks Occupancy Approval5/27/20105/27/20105/27/2010 DONE
DetailsTiffany Lowery
BLD-Conference5/20/20105/21/20105/21/2010ACANC
DetailsJim Sly
Mike phone
Zoning Approval5/21/20105/21/20105/21/2010 DONE
DetailsCody Riddle
Final site improvements will be required upon complete of phase two.
BLD-Other5/20/20105/20/20105/20/2010PCANC
DetailsJim Sly
need zoning/ landscape occupancy card sign off Inspection requested from web by: Mike Shain Phone #: ###-####
Mike to call Zoning Dept.
BLD-Other4/19/20104/20/20104/20/2010APASS
DetailsTom Arcoraci
ceiling cover Inspection requested from web by: Mike Shain Phone #: ###-####
BLD-Wall cover4/1/20104/2/20104/2/2010APASS
DetailsTom Arcoraci
Vern ###-#### Inspection requested from web by: Mike Shain fire retardent ply wood on deck
BLD-Conference2/9/20102/9/20102/9/2010PPASS
DetailsTom Arcoraci
Fire wall reinspection I need Tom per Dave Hannah Inspection requested from web by: Mike Shain arch has corrected the plan
BLD-Conference2/1/20102/1/20102/1/2010PPART
DetailsDave Hannah
Fire wall inspection Phone #: ###-#### Internet Inspection Request from: Mike Shain talked with contractor about details for eves on each side of fire wall it looks like the arct got the cut in the wrong spot contractor will call aect and also get tom envoled
BLD-Framing/Rough-in12/23/200912/24/200912/24/2009APART
DetailsTom Arcoraci
Framing rough in exsisting athletic building Phone #: ###-#### Internet Inspection Request from: Mike Shain wip ok
BLD-Energy code compliance12/15/200912/15/200912/15/2009PPASS
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Framing/Rough-in12/11/200912/14/200912/14/2009PPART
DetailsTom Arcoraci
Framing west end addition Phone #: ###-#### Internet Inspection Request from: Mike Shain wip ok
Issue PAID IN FULL permit  11/19/2009 DONE
DetailsTisha Gallop
Routing - PLAN CHECK11/3/2009 11/10/2009 PASS
DetailsJohn Menard
Print Occupancy Form  11/10/2009 DONE
DetailsTisha Gallop
Received Certificate of Value  11/10/2009 DONE
DetailsTisha Gallop
Received revised cert of value for phase 1 only; new project value is $3,850,000; ele $300,000; plm $155,000; mech $315,000; fire spr $120,000; fire alarm $10,000//11/10/09 LEG
Telephone call  11/10/2009 DONE
DetailsTisha Gallop
called Patrick Hazard and told him permit is ready, fees and need ACHD receipt
Permit Ready to Issue  11/10/2009 DONE
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  11/9/2009 DONE
DetailsJohn Menard
Plan assigned to (JCM)6/22/2009 11/9/2009 PASS
DetailsJohn Menard
11/9/2009 14:28:54 JCM - activity updated through activity BLDA022 from case BLD09-00980.
Plan resubmittals received  11/6/2009 DONE
DetailsJohn Menard
Received additional plan revisions and alternate request letter. JCM
Plan resubmittals requested  11/3/2009 DONE
DetailsJohn Menard
E-mailed the architect a letter requesting additional revisions. JCM
Routing - FIRE11/3/2009 11/3/2009 PASS
DetailsScott Arellano
Attached updated IFC comments to plans.
Routing - PLAN CHECK8/18/2009 11/3/2009  
DetailsJohn Menard
Routing Off Site - STRUCTURAL10/28/2009 11/2/2009 PASS
DetailsJohn Menard
Received letter from consulting structural engineer approving final structural revisions. JCM
Telephone call  10/28/2009 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Plan resubmittals received  10/26/2009  
DetailsTisha Gallop
received three copies of the following: response to comments for John Menard, response to fire comments for Scott Arellano, response to structural comments, structural calculations, plan sheets A0.00, A2.02, A2.05, A2.015, A3.01, A4.03, A4.04, A5.03, A5.04, A5.05, A5.12, A6.04, A7.12, P2.03, P3.01, E3.02, S1.01, S1.02, S1.03, S2.00, S2.01, S2.02, S2.03, S2.04, S3.01, S3.02, S3.03, S4.01, S4.02, S4.03, S4.04; inserted by arch. rep. and taken back to John Menard.
Routing Off Site - STRUCTURAL10/5/2009 10/14/2009 FAIL
DetailsJohn Menard
resubs
Plan resubmittals requested  10/14/2009 DONE
DetailsJohn Menard
E-mailed the architect a copy of the 4th structural review requesting revisions. JCM
Plan resubmittals received  10/8/2009 DONE
received 3 copies of sheets S2.00,S2.01,S2.02,S2.04,S4.04 sent to John M
Plan resubmittals received  10/2/2009  
DetailsJohn Menard
Rec;d 3 copies of calcs and 3 copies of sheets; S2.1; S2.2; S1.01; S1.02; S1.03; S2.00; S2.01; S2.02; S2.03; S2.04; S3.01; S3.02; S3.03; S4.01; S4.02; S4.03; S4.04
Plan resubmittals requested  9/16/2009 DONE
DetailsJohn Menard
E-mailed the architect a copy of the third structural review requesting additioinal revisions. JCM
Routing Off Site - STRUCTURAL9/8/2009 9/15/2009 FAIL
DetailsJohn Menard
Received comment list from consulting engineer requesting additional revisions. JCM
Plan resubmittals received  9/9/2009  
DetailsTisha Gallop
received three copies of response comments and plan sheets M4.02, A0.01, A0.02, A2.02, A2.03, A2.04, A2.07, A2.08, A2.09, A2.15, A4.03, A4.04, A5.03, A5.04, A6.01, A6.04, A6.08, A6.09, A7.01, A7.02, A7.10, A7.11, A7.12, A7.13, A8.03; inserted by arch. rep. and taken back to John Menard
Plan resubmittals received  9/4/2009  
DetailsTisha Gallop
received three copies of structural calculation comments, plan sheets S1.01, S1.02, S1.03, S2.00, S2.01, S2.02, S2.03, S2.04, S3.01, S3.02, S3.03, S4.01, S4.02 S4.03, S4.04; inserted into plans by arch. rep. and taken back to John Menard
Route to Impact Fee Review8/12/20098/17/20098/20/2009 PASS
DetailsCindy M. Gould
Routing - FIRE8/12/20098/12/20098/18/2009 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Plan resubmittals requested  8/12/2009 DONE
DetailsJohn Menard
Emailed the architect a copy of the plan review requestng revisions. JCM
Routing - PLAN CHECK7/20/2009 8/12/2009 FAIL
DetailsJohn Menard
Routing Off Site - STRUCTURAL8/3/2009 8/6/2009 FAIL
DetailsJohn Menard
received comment list from consulting structural engineer requesting additional revisions. JCM
Plan Reviewer's activity  8/6/2009 DONE
DetailsJohn Menard
E-mailed the architect a copy of the second structural review requesting revisions. JCM
Plan resubmittals received  7/30/2009  
received 3 comment lists,3 structural review comments, 3 structural calcs and 3 copies of sheets S1.01,S1.02,S1.03,S2.0,S2.01,S2.02,S2.03,S2.04,S3.01,S3.02,S3.03,S4.01,S4.02,S4.03,S4.04 inserted by Dave Maloney from BRS Arch and taken back to John M.
Plan resubmittals requested  7/21/2009 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing - PLAN CHECK7/9/2009 7/20/2009  
DetailsJohn Menard
Routing - PUBLIC WORKS7/20/2009 7/20/2009 PASS
DetailsBeverly Hall
Routing PW Drainage7/20/2009 7/20/2009 PASS
DetailsBrian Murphy
Routing - PLUMBING7/7/2009 7/9/2009 PASS
DetailsBill VanDegrift
per plans and 2003 upc
1st review completed  7/9/2009 FAIL
DetailsJohn Menard
Failed Public Works, Structural, Plumbing, Planning, Plan Check, Will need to route to Fire when resubs. received.
Routing Off Site - STRUCTURAL6/22/2009 7/7/2009 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requestng revisions. JCM
Routing - PLAN CHECK6/29/2009 7/7/2009  
DetailsJohn Menard
John Menard
Plan resubmittals received  7/2/2009  
DetailsTisha Gallop
Received three copies of response and plan sheets P2.05, P2.06, P2.07, P2.08; inserted by arch. rep. and taken back to John Menard
Routing - PLANNING6/26/2009 6/29/2009 PASS
DetailsSusan Riggs
cup08-00120 Susan Riggs
Routing - PLUMBING6/26/2009 6/26/2009 FAIL
DetailsBill VanDegrift
120 deg. max hot water to public lavs. max horizontal 1 1/2" vent is 20'. combination waste and vent systems are prohibited in kitchens. bench sewer dist. may have pretreatment requirements. address items 1 and 3 and resubmit.
Routing - Erosion and Sediment6/25/2009 6/26/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC09-00365
Routing - PUBLIC WORKS6/24/2009 6/25/2009 FAIL
DetailsConnie Baumgartner
Routing PW Solid Waste6/25/2009 6/25/2009 PASS
DetailsPeter J. McCullough
No changes to solid waste collection area.
Routing PW Grading-Hillside6/24/2009 6/25/2009 PASS
DetailsTerry Records
Not hillside. The area where the project is being done does not have grades steeper than 15% and is therefore not considered a hillside.
Routing - Addressing6/24/2009 6/24/2009 PASS
DetailsApril Wing
Routing - PLANNING Land Div6/23/2009 6/24/2009 PASS
DetailsDave Abo
The existing clubhouse has a "tax parcel" line through the building. This was done by the Ada County Assessor.
Routing PW Drainage6/24/2009 6/24/2009 FAIL
DetailsBrian Murphy
needs to show existing system can handle 50 year storm. BRIAN MURPHY ###-####
Pending Assignment by JCM6/22/2009 6/22/2009 BLDA
DetailsJohn Menard
6/22/2009 15:44:49 JCM - activity updated through activity BLDA166 from case BLD09-00980.
Telephone call  6/22/2009 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Plan routing begun/NEW & ADDTN  6/22/2009 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  6/22/2009 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  6/22/2009 DONE
DetailsTisha Gallop
Application received 6/22/2009