Second Notice | | 10/21/2010 | 10/12/2010 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
First Notice | | 9/30/2010 | 10/11/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/20/2010 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 7/29/2010 | 7/30/2010 | 7/30/2010 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike Shain
|
FIRE-Final Inspection | 7/26/2010 | 7/27/2010 | 7/27/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety for phase 1 passed.
|
FIRE-Final Inspection | 7/9/2010 | 7/12/2010 | 7/12/2010 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire sprinkler permit needs addressed and "indicators" and "stickers" shall be provided per IFC 1008.1.8.3 (2.1) and (2.2) at doors 126A, 130A and 132B.
|
FIRE-Final Inspection | 7/8/2010 | 7/9/2010 | 7/9/2010 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled for monday
|
FIRE-Final Inspection | 6/8/2010 | 6/9/2010 | 6/9/2010 | A | PART |
Troy Cobbley
|
|
|
A temporary was given with Marks permission until the remaining life safety items previously listed are addressed.
|
BLD-Final | 6/8/2010 | 6/9/2010 | 6/9/2010 | A | PART |
Tom Arcoraci
|
|
|
Inspection requested from web by: Mike Shain Phone #: ###-#### ok for temp, ok for final when hardware is complete
|
FIRE-Final Inspection | 6/2/2010 | 6/2/2010 | 6/2/2010 | A | FAIL |
Troy Cobbley
|
|
|
This inspection entry is for phone conversations between Mike and I and discussions with Jason and John. Item #1: Per Jason and John the exit doors from the covered patio into the main corridor will be allowed to have key locking hardware as long as all requirements are met such as the indicator, sticker also an exit sign is required above the door as well as emergency lighting in the covered patio area. Item #2: Per John and I's discussion the pocket/half door at the bar will not be required to have accessible hardware as long as the pocket door is in the open position during business hours. Item #3: Per Jason and I's discussion the three sets of double doors from the Pro Shop, Fitness Area and Dining Area will not be allowed to have manual flush bolts in the inactive leaf or keyed locking hardware on the egress side of the active leaf. These doors must comply with IFC 1008.1.8.3 and 1008.1.8.4.
|
FIRE-Final Inspection | 5/26/2010 | 6/1/2010 | 6/1/2010 | A | FAIL |
Troy Cobbley
|
|
|
See correction notice for deficiencies.
|
PubWorks Occupancy Approval | 5/27/2010 | 5/27/2010 | 5/27/2010 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Conference | 5/20/2010 | 5/21/2010 | 5/21/2010 | A | CANC |
Jim Sly
|
|
|
Mike phone
|
Zoning Approval | 5/21/2010 | 5/21/2010 | 5/21/2010 | | DONE |
Cody Riddle
|
|
|
Final site improvements will be required upon complete of phase two.
|
BLD-Other | 5/20/2010 | 5/20/2010 | 5/20/2010 | P | CANC |
Jim Sly
|
|
|
need zoning/ landscape occupancy card sign off Inspection requested from web by: Mike Shain Phone #: ###-#### Mike to call Zoning Dept.
|
BLD-Other | 4/19/2010 | 4/20/2010 | 4/20/2010 | A | PASS |
Tom Arcoraci
|
|
|
ceiling cover Inspection requested from web by: Mike Shain Phone #: ###-####
|
BLD-Wall cover | 4/1/2010 | 4/2/2010 | 4/2/2010 | A | PASS |
Tom Arcoraci
|
|
|
Vern ###-#### Inspection requested from web by: Mike Shain fire retardent ply wood on deck
|
BLD-Conference | 2/9/2010 | 2/9/2010 | 2/9/2010 | P | PASS |
Tom Arcoraci
|
|
|
Fire wall reinspection I need Tom per Dave Hannah Inspection requested from web by: Mike Shain arch has corrected the plan
|
BLD-Conference | 2/1/2010 | 2/1/2010 | 2/1/2010 | P | PART |
Dave Hannah
|
|
|
Fire wall inspection Phone #: ###-#### Internet Inspection Request from: Mike Shain talked with contractor about details for eves on each side of fire wall it looks like the arct got the cut in the wrong spot contractor will call aect and also get tom envoled
|
BLD-Framing/Rough-in | 12/23/2009 | 12/24/2009 | 12/24/2009 | A | PART |
Tom Arcoraci
|
|
|
Framing rough in exsisting athletic building Phone #: ###-#### Internet Inspection Request from: Mike Shain wip ok
|
BLD-Energy code compliance | 12/15/2009 | 12/15/2009 | 12/15/2009 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### Internet Inspection Request from: Mike Shain
|
BLD-Framing/Rough-in | 12/11/2009 | 12/14/2009 | 12/14/2009 | P | PART |
Tom Arcoraci
|
|
|
Framing west end addition Phone #: ###-#### Internet Inspection Request from: Mike Shain wip ok
|
Issue PAID IN FULL permit | | | 11/19/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 11/3/2009 | | 11/10/2009 | | PASS |
John Menard
|
|
|
|
Print Occupancy Form | | | 11/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
Received Certificate of Value | | | 11/10/2009 | | DONE |
Tisha Gallop
|
|
|
Received revised cert of value for phase 1 only; new project value is $3,850,000; ele $300,000; plm $155,000; mech $315,000; fire spr $120,000; fire alarm $10,000//11/10/09 LEG
|
Telephone call | | | 11/10/2009 | | DONE |
Tisha Gallop
|
|
|
called Patrick Hazard and told him permit is ready, fees and need ACHD receipt
|
Permit Ready to Issue | | | 11/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2009 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 6/22/2009 | | 11/9/2009 | | PASS |
John Menard
|
|
|
11/9/2009 14:28:54 JCM - activity updated through activity BLDA022 from case BLD09-00980.
|
Plan resubmittals received | | | 11/6/2009 | | DONE |
John Menard
|
|
|
Received additional plan revisions and alternate request letter. JCM
|
Plan resubmittals requested | | | 11/3/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a letter requesting additional revisions. JCM
|
Routing - FIRE | 11/3/2009 | | 11/3/2009 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans.
|
Routing - PLAN CHECK | 8/18/2009 | | 11/3/2009 | | |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 10/28/2009 | | 11/2/2009 | | PASS |
John Menard
|
|
|
Received letter from consulting structural engineer approving final structural revisions. JCM
|
Telephone call | | | 10/28/2009 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Plan resubmittals received | | | 10/26/2009 | | |
Tisha Gallop
|
|
|
received three copies of the following: response to comments for John Menard, response to fire comments for Scott Arellano, response to structural comments, structural calculations, plan sheets A0.00, A2.02, A2.05, A2.015, A3.01, A4.03, A4.04, A5.03, A5.04, A5.05, A5.12, A6.04, A7.12, P2.03, P3.01, E3.02, S1.01, S1.02, S1.03, S2.00, S2.01, S2.02, S2.03, S2.04, S3.01, S3.02, S3.03, S4.01, S4.02, S4.03, S4.04; inserted by arch. rep. and taken back to John Menard.
|
Routing Off Site - STRUCTURAL | 10/5/2009 | | 10/14/2009 | | FAIL |
John Menard
|
|
|
resubs
|
Plan resubmittals requested | | | 10/14/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the 4th structural review requesting revisions. JCM
|
Plan resubmittals received | | | 10/8/2009 | | DONE |
|
|
|
received 3 copies of sheets S2.00,S2.01,S2.02,S2.04,S4.04 sent to John M
|
Plan resubmittals received | | | 10/2/2009 | | |
John Menard
|
|
|
Rec;d 3 copies of calcs and 3 copies of sheets; S2.1; S2.2; S1.01; S1.02; S1.03; S2.00; S2.01; S2.02; S2.03; S2.04; S3.01; S3.02; S3.03; S4.01; S4.02; S4.03; S4.04
|
Plan resubmittals requested | | | 9/16/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the third structural review requesting additioinal revisions. JCM
|
Routing Off Site - STRUCTURAL | 9/8/2009 | | 9/15/2009 | | FAIL |
John Menard
|
|
|
Received comment list from consulting engineer requesting additional revisions. JCM
|
Plan resubmittals received | | | 9/9/2009 | | |
Tisha Gallop
|
|
|
received three copies of response comments and plan sheets M4.02, A0.01, A0.02, A2.02, A2.03, A2.04, A2.07, A2.08, A2.09, A2.15, A4.03, A4.04, A5.03, A5.04, A6.01, A6.04, A6.08, A6.09, A7.01, A7.02, A7.10, A7.11, A7.12, A7.13, A8.03; inserted by arch. rep. and taken back to John Menard
|
Plan resubmittals received | | | 9/4/2009 | | |
Tisha Gallop
|
|
|
received three copies of structural calculation comments, plan sheets S1.01, S1.02, S1.03, S2.00, S2.01, S2.02, S2.03, S2.04, S3.01, S3.02, S3.03, S4.01, S4.02 S4.03, S4.04; inserted into plans by arch. rep. and taken back to John Menard
|
Route to Impact Fee Review | 8/12/2009 | 8/17/2009 | 8/20/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 8/12/2009 | 8/12/2009 | 8/18/2009 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Plan resubmittals requested | | | 8/12/2009 | | DONE |
John Menard
|
|
|
Emailed the architect a copy of the plan review requestng revisions. JCM
|
Routing - PLAN CHECK | 7/20/2009 | | 8/12/2009 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 8/3/2009 | | 8/6/2009 | | FAIL |
John Menard
|
|
|
received comment list from consulting structural engineer requesting additional revisions. JCM
|
Plan Reviewer's activity | | | 8/6/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the second structural review requesting revisions. JCM
|
Plan resubmittals received | | | 7/30/2009 | | |
|
|
|
received 3 comment lists,3 structural review comments, 3 structural calcs and 3 copies of sheets S1.01,S1.02,S1.03,S2.0,S2.01,S2.02,S2.03,S2.04,S3.01,S3.02,S3.03,S4.01,S4.02,S4.03,S4.04 inserted by Dave Maloney from BRS Arch and taken back to John M.
|
Plan resubmittals requested | | | 7/21/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Routing - PLAN CHECK | 7/9/2009 | | 7/20/2009 | | |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 7/20/2009 | | 7/20/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Drainage | 7/20/2009 | | 7/20/2009 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 7/7/2009 | | 7/9/2009 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
1st review completed | | | 7/9/2009 | | FAIL |
John Menard
|
|
|
Failed Public Works, Structural, Plumbing, Planning, Plan Check, Will need to route to Fire when resubs. received.
|
Routing Off Site - STRUCTURAL | 6/22/2009 | | 7/7/2009 | | FAIL |
John Menard
|
|
|
Received comment list from consulting structural engineer requestng revisions. JCM
|
Routing - PLAN CHECK | 6/29/2009 | | 7/7/2009 | | |
John Menard
|
|
|
John Menard
|
Plan resubmittals received | | | 7/2/2009 | | |
Tisha Gallop
|
|
|
Received three copies of response and plan sheets P2.05, P2.06, P2.07, P2.08; inserted by arch. rep. and taken back to John Menard
|
Routing - PLANNING | 6/26/2009 | | 6/29/2009 | | PASS |
Susan Riggs
|
|
|
cup08-00120 Susan Riggs
|
Routing - PLUMBING | 6/26/2009 | | 6/26/2009 | | FAIL |
Bill VanDegrift
|
|
|
120 deg. max hot water to public lavs. max horizontal 1 1/2" vent is 20'. combination waste and vent systems are prohibited in kitchens. bench sewer dist. may have pretreatment requirements. address items 1 and 3 and resubmit.
|
Routing - Erosion and Sediment | 6/25/2009 | | 6/26/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00365
|
Routing - PUBLIC WORKS | 6/24/2009 | | 6/25/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 6/25/2009 | | 6/25/2009 | | PASS |
Peter J. McCullough
|
|
|
No changes to solid waste collection area.
|
Routing PW Grading-Hillside | 6/24/2009 | | 6/25/2009 | | PASS |
Terry Records
|
|
|
Not hillside. The area where the project is being done does not have grades steeper than 15% and is therefore not considered a hillside.
|
Routing - Addressing | 6/24/2009 | | 6/24/2009 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 6/23/2009 | | 6/24/2009 | | PASS |
Dave Abo
|
|
|
The existing clubhouse has a "tax parcel" line through the building. This was done by the Ada County Assessor.
|
Routing PW Drainage | 6/24/2009 | | 6/24/2009 | | FAIL |
Brian Murphy
|
|
|
needs to show existing system can handle 50 year storm. BRIAN MURPHY ###-####
|
Pending Assignment by JCM | 6/22/2009 | | 6/22/2009 | | BLDA |
John Menard
|
|
|
6/22/2009 15:44:49 JCM - activity updated through activity BLDA166 from case BLD09-00980.
|
Telephone call | | | 6/22/2009 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Plan routing begun/NEW & ADDTN | | | 6/22/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/22/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/22/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 6/22/2009 | | | |
|
|
|
|