BLD-Final | 9/8/2009 | 9/8/2009 | 9/8/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/8/2009 at 7:57:42 AM. Contact: ###-####.
|
DOC - Permit Finaled | 9/8/2009 | 9/8/2009 | 9/8/2009 | P | PASS |
Mike Jordan
|
|
|
Cert. of occ was isued.
|
BLD-Energy code compliance | 8/11/2009 | 8/12/2009 | 8/12/2009 | A | PASS |
Mike Jordan
|
|
|
Rustin Phone #: ###-####
|
BLD-Framing/Rough-in | 8/12/2009 | 8/12/2009 | 8/12/2009 | A | PASS |
Mike Jordan
|
|
|
Rustin Phone #: ###-####. All issues were resolved.
|
BLD-Framing/Rough-in | 8/11/2009 | 8/11/2009 | 8/11/2009 | P | FAIL |
Mike Jordan
|
|
|
Rustin ###-####. Complete lateral bracing on A5 and A5a trusses. Complete airseal under both tub/shower at drains. Provide double layer 5/8type x rock at east soffitt. c/n posted. ok to insul.
|
BLD-Framing/Rough-in | 8/10/2009 | 8/10/2009 | 8/10/2009 | P | NR |
Mike Jordan
|
|
|
rustin Phone #: ###-####. ESC issues were not resolved at time of arrival.
|
BLD-Framing/Rough-in | 8/7/2009 | 8/10/2009 | 8/10/2009 | A | FAIL |
Mike Jordan
|
|
|
Rustin Phone #: ###-####. Still needs mech rough in inspection and needs to resolved ESC issues prior to framing inspection.
|
BLD-Foundation | 7/10/2009 | 7/10/2009 | 7/10/2009 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/10/2009 at 7:15:37 AM. Contact: ###-####.
|
BLD-Footing | 7/9/2009 | 7/10/2009 | 7/10/2009 | A | PASS |
Jim Sly
|
|
|
Shelly Phone #: ###-####
|
Plan assigned to (CDM) | 7/9/2009 | 7/9/2009 | 7/9/2009 | | DONE |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 6/26/2009 | 7/1/2009 | 7/9/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 7/6/2009 | | 7/9/2009 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/9/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/9/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2009 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/9/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/9/2009 | | DONE |
|
|
|
t/c w shelly strate at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/9/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/9/2009 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 7/6/2009 | | 7/6/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLANNING | 7/6/2009 | | 7/6/2009 | | PASS |
Cody Riddle
|
|
|
Revised plans indicate compliance with 15' setback along western property line.
|
Routing - PLANNING | 6/26/2009 | | 6/29/2009 | | FAIL |
Cody Riddle
|
|
|
Fail: A 15' setback is required along the western property line. Called applicant and informed them of the required changes.
Routed to Cody 6/29 CUP06-73
|
Routing - Addressing | 6/26/2009 | | 6/26/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 6/26/2009 | | | |
|
|
|
|