Third Notice | | 1/27/2010 | 1/20/2010 | | DONE |
|
|
|
|
Third Notice | | 12/30/2009 | 1/13/2010 | | DONE |
Tisha Gallop
|
|
|
2nd third notice for tenant. Called, faxed and mailed.
|
Telephone call | | | 1/13/2010 | | DONE |
Tisha Gallop
|
|
|
called and left vm for Danae/AMS Co. need FV. Received phone call back from Nicole/AMS Co. she will get it to me today.
|
Telephone call | | | 12/18/2009 | | DONE |
Tisha Gallop
|
|
|
received message from John Lodman (GC) we need to contact the tenant, who is the applicant, Amalgamated Sugar Co. for final values, contact is Danae at ###-####.
|
Third Notice | | 12/9/2009 | 12/16/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/16/2009 | | DONE |
Tisha Gallop
|
|
|
called and left vm for John Lodman need FV
|
Third Notice | | 11/14/2009 | 11/25/2009 | | DONE |
|
|
|
faxed
|
Second Notice | | 10/31/2009 | 11/4/2009 | | DONE |
|
|
|
|
First Notice | | 10/3/2009 | 10/21/2009 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 9/23/2009 | 9/23/2009 | 9/23/2009 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. ok for perm occ. Could not find card while on site. Ok for Troy to sign my name on card.
|
FIRE-Final Inspection | 9/23/2009 | 9/23/2009 | 9/23/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
Permanent Occupancy | | | 9/23/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/23/2009 | | |
|
|
|
|
FIRE-Final Inspection | 9/18/2009 | 9/18/2009 | 9/18/2009 | A | DONE |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 9/18/2009 at 7:29:56 AM. Contact: ###-####.--Contractor Called and Cancelled///9-18-09 @ 9:25am BAS
|
BLD-Final | 8/27/2009 | 8/27/2009 | 8/27/2009 | A | PART |
Mike Jordan
|
|
|
requesting temp final pending completion of fire corrections issued yesterday. temp approval from fire is complete. Phone #: ###-#### Internet Inspection Request from: John Lodman. ok for temp occ. only.
|
Temporary Occupancy UNPAID FEE | | | 8/27/2009 | | DONE |
|
|
|
|
BLD-Final | 8/26/2009 | 8/26/2009 | 8/26/2009 | P | CANC |
Mike Jordan
|
|
|
|
FIRE-Alarm Testing | 8/26/2009 | 8/26/2009 | 8/26/2009 | A | DONE |
Troy Cobbley
|
|
|
See previous entry.
|
FIRE-Final Inspection | 8/26/2009 | 8/26/2009 | 8/26/2009 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with scott and marks approval. The remaining items are provide additional emergency lighting as marked on the electrical sheet, provide missing hardware and exit signs in the board room, provide occupant load signs for the conference rooms, provide correct smoke detector coverage in room 176, provide verification that the velocity listing for the underfloor detectors has not been exceeded, provide maps at both fire panels as discussed and test the server room liebert units for shutdown.
|
BLD-Final | 8/26/2009 | 8/26/2009 | 8/26/2009 | A | NR |
Mike Jordan
|
|
|
requesting temp occupancy with balance of interior doors as only exception. door install in progress. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
FIRE-Final Inspection | 8/25/2009 | 8/25/2009 | 8/25/2009 | P | CANC |
Troy Cobbley
|
|
|
The life safety could not be completed due to time constraints and the project related fire alarm and fire sprinkler permits not being completed. I also noted that several doors/hardware had not been installed.
|
FIRE-Alarm Testing | 8/25/2009 | 8/25/2009 | 8/25/2009 | P | CANC |
Troy Cobbley
|
|
|
The life safety could not be completed due to time constraints and the project related fire alarm and fire sprinkler permits not being completed. I also noted that several doors/hardware had not been installed.
|
BLD-Other | 8/20/2009 | 8/21/2009 | 8/21/2009 | P | PART |
Mike Jordan
|
|
|
ceiling cover north of grid 3.5 please. Phone #: ###-#### Internet Inspection Request from: John Lodman. Pend. elec. ri.
|
BLD-Other | 8/18/2009 | 8/19/2009 | 8/19/2009 | A | PART |
Mike Jordan
|
|
|
ceiling cover south of grid 3.5. pending trade inspection should be complete this morning. Phone #: ###-#### Internet Inspection Request from: John Lodman. Grid ok, south half. Noted to general contractor that their is no occupancy allowed at this time. Noted employees with offices set up and working.
|
BLD-Other | 8/18/2009 | 8/18/2009 | 8/18/2009 | P | NR |
Mike Jordan
|
|
|
ceiling cover south of gridline 3.5 please Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Other | 8/6/2009 | 8/7/2009 | 8/7/2009 | A | PART |
Jim Sly
|
|
|
Ceiling cover in room 176-data only. elec and fire sprink pending this a.m. thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman Data room OK. After Fire and Ele OK'd
|
BLD-Wall cover | 7/28/2009 | 7/28/2009 | 7/28/2009 | P | PASS |
Mike Jordan
|
|
|
John center of building Phone #: ###-####. INterior steel stud framed walls at center portion. no grid.
|
BLD-Framing/Rough-in | 7/22/2009 | 7/23/2009 | 7/23/2009 | A | PART |
Mike Jordan
|
|
|
AM electrical inspection pending. Requesting approval to cover walls south of approx gridline 3.5 and north of approx gridline 5.3. no plumbing inspection required in these areas to be covered as plumbing is all existing. Phone #: ###-#### Internet Inspection Request from: John Lodman. INterior steel stud framed walls only at north and south ends od bldg. wip on center portion.
|
Print Occupancy Form | | | 7/22/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/22/2009 | | DONE |
|
|
|
t/c w damon beard at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/22/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/22/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 6/30/2009 | | 7/21/2009 | | PASS |
Sam Zahorka
|
|
|
7/21/2009 15:07:09 SRZ - activity updated through activity BLDA022 from case BLD09-01062.
|
Routing - PLAN CHECK | 7/16/2009 | | 7/21/2009 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - FIRE | 7/10/2009 | 7/10/2009 | 7/16/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 7/16/2009 | | FAIL |
Scott Arellano
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 7/10/2009 | 7/15/2009 | 7/13/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenet improvement no impact fees
|
Plan resubmittals received | | | 7/13/2009 | | |
Tisha Gallop
|
|
|
Received transmittal, response from architect, two copies of sheets A-0, A-1, A-2, A-3, A-4, A-6, A-7, A-8, E2.1; taken to Sam Z.
|
Case Summary (BLD) | | | 7/10/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 7/6/2009 | | 7/10/2009 | | FAIL |
Sam Zahorka
|
|
|
Emailed corrections to the Architect. Routed plans to Fire Review.
|
Routing - PLANNING | 7/3/2009 | | 7/6/2009 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - CZC09-00127
|
Routing - PUBLIC WORKS | 6/30/2009 | | 7/2/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - Erosion and Sediment | 7/2/2009 | | 7/2/2009 | | PASS |
Steven Webb
|
|
|
ESC09-00364 plan waiver approved with attached conditions.
|
Routing - Addressing | 7/1/2009 | | 7/1/2009 | | PASS |
April Wing
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/30/2009 | | DONE |
|
|
|
|
Pending Assignment by JCB | 6/30/2009 | | 6/30/2009 | | DONE |
Jason Blais
|
|
|
|
Application received | | 6/29/2009 | | | |
|
|
|
|