BLD-Final | 10/15/2009 | 10/15/2009 | 10/15/2009 | P | PASS |
Tony Young
|
|
|
Craig Phone #: ###-#### new wood hand rails meet code
|
DOC - Permit Finaled | 10/15/2009 | 10/15/2009 | 10/15/2009 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 9/17/2009 | 9/17/2009 | 9/17/2009 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/17/2009 at 9:31:49 AM. Contact: ###-####. Contr removed top cap of handrail to see if profile of pc remaining above metal guards would meet code. Did not meet Section R-311.5.6. Reviewed this section with contractor.
|
BLD-Conference | 7/28/2009 | 7/28/2009 | 7/29/2009 | P | FAIL |
Tony Young
|
|
|
amy Phone #: ###-#### sample of hand rail does not meet code
|
BLD-Footing | 7/16/2009 | 7/16/2009 | 7/16/2009 | P | PASS |
Tony Young
|
|
|
david Phone #: ###-####
|
PubWorks Subgrade Approval | 7/16/2009 | 7/16/2009 | 7/16/2009 | | DONE |
Brian Murphy
|
|
|
Engineer letter on sub-grade approved per Brian Murphy///7/16/09
|
Routing Walk-In (BLD) | 7/14/2009 | 7/14/2009 | 7/14/2009 | A | PASS |
Carl D Madsen
|
|
|
7/14/2009 09:29:05 CDM - activity updated through activity BLDA022 from case BLD09-01155.
|
Routing Walk-In (BLD) | 7/13/2009 | 7/13/2009 | 7/14/2009 | P | DONE |
Darla L Downs
|
|
|
7/14/2009 08:20:36 DLD - activity updated through activity BLDI252 from case BLD09-01155.
|
Case Summary (BLD) | | | 7/14/2009 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/14/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2009 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/14/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing Walk-In (PW Hillside) | 7/13/2009 | 7/13/2009 | 7/13/2009 | A | PASS |
Terry Records
|
|
|
A letter from the applicants geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling footing inspection.
|
Routing Walk-In (Zoning) | 7/13/2009 | 7/13/2009 | 7/13/2009 | A | DONE |
Tisha Gallop
|
|
|
7/13/2009 09:22:35 LEG - activity updated through activity BLDI252 from case BLD09-01155.
|
Routing Walk-In (BLD) | 7/13/2009 | 7/13/2009 | 7/13/2009 | A | FAIL |
Perry Paine
|
|
|
|
Routing Walk-In (Zoning) | 7/13/2009 | 7/13/2009 | 7/13/2009 | P | PASS |
Colleen T Carroll
|
|
|
|
Application/Plans DENIED | | | 7/13/2009 | | FAIL |
|
|
|
need foundation and framing engineering
|
Application received | | 7/13/2009 | | | |
|
|
|
|