Third Follow up | | | 5/17/2010 | | |
|
|
|
|
Third Notice | | 4/30/2010 | 5/4/2010 | | DONE |
|
|
|
faxed, called and e-mailed
|
Telephone call | | | 5/4/2010 | | DONE |
Tisha Gallop
|
|
|
called and left vm on Greg Anderson's cell# still need FV, if not received within 2 weeks will put Westwood Contractors on hold for no new permits or inspections in Boise until FV received.
|
Third Notice | | 3/29/2010 | 4/16/2010 | | DONE |
|
|
|
faxed and called
|
Third Notice | | 3/7/2010 | 3/15/2010 | | DONE |
|
|
|
faxed
|
Telephone call | | | 12/10/2009 | | DONE |
|
|
|
Talked to Greg Anderson- value is large difference and he was going to look into it...permit started out with a different GC and he was going to see if he could get their value also
|
Second Notice | | 11/15/2009 | 11/24/2009 | | DONE |
|
|
|
|
First Notice | 10/23/2009 | 10/23/2009 | 11/5/2009 | | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 10/22/2009 | 10/23/2009 | 10/23/2009 | A | PASS |
Mike Jordan
|
|
|
Fred store does not open until 10 am Phone #: ###-####
|
DOC - Permit Finaled | 10/23/2009 | 10/23/2009 | 10/23/2009 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 10/22/2009 | 10/23/2009 | 10/23/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
OVERRIDE | | | 10/20/2009 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/20/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/20/2009 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/20/2009 | | |
|
|
|
|
Telephone call | | | 10/20/2009 | | DONE |
Barbara Stitt
|
|
|
Called Greg Anderson and told him that plan mod was ready for pick up and the fees due///10-20-09 @ 11:00am BAS
|
Permit Ready to Issue | | | 10/20/2009 | | |
|
|
|
|
Plan assigned to (TLW) | 10/14/2009 | | 10/19/2009 | | PASS |
Tim L. Woodard
|
|
|
10/19/2009 15:57:35 TLW - activity updated through activity BLDA022 from case BLD09-01272.
|
Routing - PLAN CHECK | 10/19/2009 | | 10/19/2009 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod approved per new plans and attached engineering. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 10/19/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Plan Modification Accepted | | | 10/14/2009 | | DONE |
|
|
|
plan modification excepted to provide and install support steel for the installation ot two bike lifts,and extend electrical power to lifts pages A0.0,A2.0,S1.1,E1.0
|
FIRE-Final Inspection | 9/3/2009 | 9/4/2009 | 9/4/2009 | A | FAIL |
Troy Cobbley
|
|
|
Life safety not performed since the project related fire alarm permit was failed.
|
BLD-Final | 9/3/2009 | 9/4/2009 | 9/4/2009 | A | NR |
Mike Jordan
|
|
|
fred Phone #: ###-####. Fire failed.
|
BLD-Conference | 9/3/2009 | 9/3/2009 | 9/3/2009 | P | PASS |
Mike Jordan
|
|
|
Needs fire alarm and life safety final. All other trades final. Also reviewed special insp. report for welding done on job. ok.
|
(F) Reprint permit | | | 9/2/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/4/2009 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 7/30/2009 | | 8/3/2009 | | PASS |
Tim L. Woodard
|
|
|
8/3/2009 11:01:58 TLW - activity updated through activity BLDA022 from case BLD09-01272.
|
Routing - PLAN CHECK | 8/3/2009 | | 8/3/2009 | | PASS |
Tim L. Woodard
|
|
|
Approved as submitted. TLW
|
Routing - FIRE | | | 8/3/2009 | | PASS |
Tim L. Woodard
|
|
|
Field Verify
|
1st review completed | | | 8/3/2009 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 8/3/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 8/3/2009 | | DONE |
|
|
|
|
Telephone call | | | 8/3/2009 | | DONE |
|
|
|
t/c w robert lewis at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/3/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/30/2009 | | DONE |
|
|
|
|
Application received | | 7/28/2009 | | | |
|
|
|
|