Second Notice | | 11/14/2009 | 11/5/2009 | | DONE |
|
|
|
|
First Notice | 10/29/2009 | 10/29/2009 | 11/4/2009 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 10/28/2009 | 10/29/2009 | 10/29/2009 | A | PASS |
Dave Hannah
|
|
|
tim - please call 1/2 hr prior Phone #: ###-####
|
DOC - Permit Finaled | 10/29/2009 | 10/29/2009 | 10/29/2009 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 10/28/2009 | 10/28/2009 | 10/28/2009 | P | PASS |
Forrest France
|
|
|
Fire life safety completed satisfactory.
|
BLD-Final | 9/21/2009 | 9/22/2009 | 9/22/2009 | A | PART |
Dave Hannah
|
|
|
tim - please call 1/2 prior Phone #: ###-#### ok to occ to upstairs area
|
FIRE-Final Inspection | 9/21/2009 | 9/21/2009 | 9/22/2009 | P | PART |
Forrest France
|
|
|
Fire life safety for the second floor remodel is acceptable, final pending completion of the scope of work for the project attatched fire sprinkler permit which includes heads at a new freezer in the warehouse area not yet installed.
|
BLD-Other | 9/15/2009 | 9/16/2009 | 9/17/2009 | P | PART |
Dave Hannah
|
|
|
tim - ceiling cover - please call 1/2 hr prior Phone #: ###-#### ok to cover ceiling
|
BLD-Framing/Rough-in | 8/28/2009 | 8/31/2009 | 8/31/2009 | P | PASS |
Dave Hannah
|
|
|
Tim Opp-Please call at least 30 mins prior to inspection Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/7/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/5/2009 | | DONE |
|
|
|
|
Telephone call | | | 8/5/2009 | | DONE |
|
|
|
Called Sage Construction and spoke with Debbie-informaed her that permit is ready and fees due///8-5-09 @ 8:40am BAS
|
Routing - PLAN CHECK | | | 8/4/2009 | | PASS |
Tim L. Woodard
|
|
|
Approved with comments. TLW
|
Plan assigned to (TLW) | 7/30/2009 | | 8/4/2009 | | PASS |
Tim L. Woodard
|
|
|
8/4/2009 13:53:34 TLW - activity updated through activity BLDA022 from case BLD09-01289.
|
Routing - PUBLIC WORKS | | | 8/4/2009 | | PASS |
Connie Baumgartner
|
|
|
Bev Hall Signed plans 8-3-09. TLW
|
Routing - FIRE | | | 8/4/2009 | | PASS |
Tim L. Woodard
|
|
|
Field Verify Compliance. TLW
|
1st review completed | | | 8/4/2009 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/4/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 8/4/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 8/4/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 8/4/2009 | | DONE |
|
|
|
|
Routing - Addressing | 7/30/2009 | | 7/31/2009 | | PASS |
April Wing
|
|
|
|
Routing PW Sewer Rating | 7/31/2009 | | 7/31/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/30/2009 | | DONE |
|
|
|
ok to take in as a level 1 per Tim W.
|
Application received | | 7/30/2009 | | | |
|
|
|
|