DOC - Permit Expired | 2/6/2012 | 2/6/2012 | 2/6/2012 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/3/2012 | 2/3/2012 | 2/6/2012 | | FAIL |
Tony Young
|
|
|
|
BLD-Aging Inspection | 10/18/2011 | 10/18/2011 | 10/25/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/18/2011 | 4/18/2011 | 4/21/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/15/2011 | 2/15/2011 | 2/16/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/14/2010 | 12/14/2010 | 12/15/2010 | | PASS |
Tony Young
|
|
|
|
BLD-Final | 12/7/2009 | 12/8/2009 | 12/8/2009 | A | PART |
Tony Young
|
|
|
Jim Phone #: ###-#### ok to occupy the 1st phase,, the RV and garage shop areas
|
BLD-Energy code compliance | 10/29/2009 | 10/29/2009 | 10/29/2009 | P | PASS |
Tony Young
|
|
|
Jim Band Phone #: ###-####
|
BLD-Framing/Rough-in | 10/23/2009 | 10/26/2009 | 10/26/2009 | A | PART |
Tony Young
|
|
|
jim Phone #: ###-#### shop and garage ok,, house to be built later,, need truss specs,,
|
BLD-Foundation | 9/8/2009 | 9/9/2009 | 9/9/2009 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/8/2009 at 5:17:18 PM. Contact: ###-####.
|
BLD-Footing | 9/4/2009 | 9/8/2009 | 9/8/2009 | A | PASS |
Tony Young
|
|
|
Jim Band ###-####
|
Issue PAID IN FULL permit | | | 9/4/2009 | | DONE |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 8/5/2009 | 8/10/2009 | 9/3/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Inspection Record Card- Bld | | | 9/3/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/3/2009 | | DONE |
|
|
|
|
Telephone call | | | 9/3/2009 | | DONE |
|
|
|
called Jim permit ready and fee given
|
Plan assigned to (CDM) | 8/5/2009 | 8/5/2009 | 9/2/2009 | | PASS |
Carl D Madsen
|
|
|
9/2/2009 15:27:49 CDM - activity updated through activity BLDA022 from case BLD09-01323.
|
Routing - PLAN CHECK | 8/13/2009 | | 9/2/2009 | | PASS |
Carl D Madsen
|
|
|
Additional information required 8-14-09 CDM
E-Mail sent to Builder 8-14-09 CDM
|
Plan resubmittals received | | | 9/2/2009 | | |
Tisha Gallop
|
|
|
received two copies of wall bracing detail, site plans on 8 1/2" x 11", structural calculations and plan sheets 1, 3, 4, 5, 6, 7; taken to Carl Madsen
|
Case Summary (BLD) | | | 9/2/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/2009 | | |
|
|
|
|
1st review completed | | | 8/14/2009 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 8/11/2009 | | 8/13/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 8/11/2009 | | 8/11/2009 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 8/5/2009 | | 8/6/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 8/5/2009 | | | |
|
|
|
|
Routing - PLANNING | 8/6/2009 | | | | |
|
|
|
failed. Called applicant, does not meet front yard setback
|