Permit Information
Permit NumberBLD09-01327
StatusFinaled
Name LARRY HANSEN
Site Address 150 N 8TH ST
Project NameCAPITOL TERRACE BLDG
Customer Number 
ePlanReviewNo
Description
(CAPITOL TERRACE BUILDING - CORE UPGRADES TRIGGERED BY HEIRLOOM DANCE STUDIO - 1ST STORY) The fire sprinklered system is required because this is a high-rise building. To upgrade an interior non-compliant door landing, an interior non-compliant ramp, and the swing of an interior egress door located within the 1st story core area of the Capitol Terrace Building. In addition, outside air serving the "Heirloom Dance Studio" tenant space will be increased. Work is to include extending a door alcove that is part of a 2-hr fire-resistance-rated exit passageway. An interior concrete ramp, a concrete landing at an interior door, 2-hr fire-resistance-rated walls, and a 2-hr fire-resistance-rated ceiling will be constructed. Occupancy of the "Heirloom Dance Studio" tenant space is NOT allowed until the work authorized by this permit is completed. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/25/20102/12/2010 DONE
Third Notice 1/27/20102/12/2010 DONE
faxed, mailed and called
Telephone call  2/12/2010 DONE
DetailsTisha Gallop
called and spoke with Larry, he said this not his fax number any longer and to e-mail it to him.
Third Notice 1/18/20101/13/2010 DONE
DetailsTisha Gallop
faxed
Second Notice 12/4/200912/29/2009 DONE
First Notice11/13/200911/13/200911/25/2009 DONE
DetailsTom Arcoraci
BLD-Final11/12/200911/13/200911/13/2009APASS
DetailsTom Arcoraci
Jeff Carter Phone #: ###-####
DOC - Permit Finaled11/13/200911/13/200911/13/2009PPASS
DetailsTom Arcoraci
FIRE-Final Inspection11/12/200911/12/200911/12/2009PPASS
DetailsForrest France
Correction notice items are finished, fire life safety finaled.
FIRE-Final Inspection11/10/200911/10/200911/10/2009PPART
DetailsForrest France
Discussed final inspection schedule and project related fire sprinkler permit work- final insp. set for 11/12 pm.
FIRE-Final Inspection10/27/200910/28/200910/28/2009AFAIL
DetailsForrest France
Existing fire sprinkler coverage will need modifications due to remodel work, see fire code review notes for details pertaining.
BLD-Final10/26/200910/27/200910/27/2009ANR
DetailsDave Hannah
Jeff Phone #: ###-#### needs other trades to final first
BLD-Wall cover9/14/20099/14/20099/14/2009PPASS
DetailsDave Hannah
Jeff Phone #: ###-#### ok to cover 2hr corrador
Issue PAID IN FULL permit  8/24/2009 DONE
Route to Impact Fee Review8/17/20098/20/20098/20/2009 PASS
DetailsCindy M. Gould
Routing - FIRE8/17/20098/17/20098/20/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  8/20/2009 PASS
Routing - PLAN CHECK8/20/2009 8/20/2009 DONE
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  8/20/2009 DONE
Inspection Record Card- Bld  8/20/2009 DONE
Details
Telephone call  8/20/2009 DONE
Details
t/c w larry at ###-#### - permit ready and fees given
Permit Ready to Issue  8/20/2009 DONE
Details
Plan assigned to (CJW)8/7/2009 8/20/2009 PASS
DetailsCarl Westfall
8/20/2009 09:45:03 CJW - activity updated through activity BLDA022 from case BLD09-01327.
Routing - PLAN CHECK8/7/2009 8/17/2009 PASS
DetailsCarl Westfall
The IBC plan review was started on August 14, 2009 and finished on August 17, 2009. The drawings were approved with "red lines". See the plan review report.
Plans ACCEPTED BY PLAN TECH  8/7/2009 DONE
Recd Pcfee & Taken To Pln CK  8/7/2009 DONE
Pending Assignment by JCB8/7/2009 8/7/2009 DONE
DetailsJason Blais
Application received 8/6/2009