BLD-Final | 10/9/2009 | 10/9/2009 | 10/9/2009 | P | PASS |
Mike Jordan
|
|
|
rustin Phone #: ###-####
|
DOC - Permit Finaled | 10/9/2009 | 10/9/2009 | 10/9/2009 | P | PASS |
Mike Jordan
|
|
|
Letter of occ issued.
|
BLD-Energy code compliance | 9/14/2009 | 9/15/2009 | 9/15/2009 | A | PASS |
Mike Jordan
|
|
|
Rustin ###-####
|
BLD-Framing/Rough-in | 9/10/2009 | 9/11/2009 | 9/11/2009 | A | FAIL |
Mike Jordan
|
|
|
Rustin Phone #: ###-####. Complete lateral bracing on A2 and A5 trusses. Get zoning approval for added windows and change in front window. ok to insul.
|
BLD-Footing | 8/20/2009 | 8/20/2009 | 8/20/2009 | P | PASS |
Jim Sly
|
|
|
Jay Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/20/2009 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/7/2009 | 8/12/2009 | 8/18/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (CDM) | 8/7/2009 | 8/7/2009 | 8/18/2009 | | PASS |
Carl D Madsen
|
|
|
8/18/2009 08:50:26 CDM - activity updated through activity BLDA022 from case BLD09-01328.
|
Routing - PLAN CHECK | 8/14/2009 | | 8/18/2009 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 8/18/2009 | | DONE |
|
|
|
|
1st review completed | | | 8/18/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/18/2009 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/18/2009 | | DONE |
|
|
|
|
Telephone call | | | 8/18/2009 | | DONE |
|
|
|
t/c w shelly at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/18/2009 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 8/13/2009 | | 8/14/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Plan resubmittals received | | | 8/13/2009 | | |
Tisha Gallop
|
|
|
received two revised full sets of plans and two reduced size site plans; taken to Cody R.
|
Routing - PLANNING | 8/13/2009 | | 8/13/2009 | | PASS |
Cody Riddle
|
|
|
Okay per revised site plan.
|
Routing - PLANNING | 8/7/2009 | | 8/10/2009 | | FAIL |
Cody Riddle
|
|
|
Routed to Cody Riddle for CUP06-00073 review.
Fail: A 15' rear yard setback is required along the southern property line. Emailed a PDF of changes to applicant this morning. CER
|
Routing - Addressing | 8/7/2009 | | 8/7/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 8/7/2009 | | | |
|
|
|
|
Routing - Addressing | 8/7/2009 | | | | |
April Wing
|
|
|
|