Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD09-01336
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 519 N ALLUMBAUGH ST
Project NameDarigold
Customer Number 
ePlanReviewNo
Description
Darigold - Pre-treatment tank and equipment building - To construct a 1,176 square foot CMU block equipment building (unocupied) and install a 7,776 square foot pre-treatment tank, located on the West side of Allumbaugh Street across from the existing production plant. All work per the approved plans, Engineering, and attached plan review report. DRH09-00148 **SRZ**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  8/27/2019 DONE
Third Notice 10/11/201010/5/2010 DONE
Third Notice 8/30/20109/27/2010 DONE
faxed
Third Notice 8/3/20108/16/2010 DONE
faxed
Second Notice 7/25/20107/29/2010 DONE
First Notice6/30/20106/30/20107/15/2010 DONE
DetailsJim Storey
BLD-Aging Inspection6/23/20106/23/20107/1/2010 PASS
DetailsJim Storey
BLD-Final6/30/20106/30/20106/30/2010APASS
DetailsJim Storey
DOC - Permit Finaled6/30/20106/30/20106/30/2010PPASS
DetailsJim Storey
Zoning Approval6/18/20106/18/20106/18/2010 PASS
DetailsAndrea Tuning
BLD-Final4/23/20104/23/20104/23/2010APART
DetailsJim Storey
tempok for final pending zoning sign off.
FIRE-Final Inspection4/19/20104/20/20104/20/2010APASS
DetailsForrest France
Life safety inspection passed.
FIRE-Conference3/29/20103/29/20103/29/2010ADONE
DetailsForrest France
Ref. activity notes 3/26
FIRE-Final Inspection3/25/20103/26/20103/26/2010APASS
DetailsForrest France
Life safety inspection completed satisfactory. Noted some site work incomplete. Existing hydrant locations approved per M. Sentenno- see plan review comments.
FIRE-Final Inspection3/25/20103/25/20103/26/2010PDONE
DetailsForrest France
FPP insp. request #: ###-####
BLD-Final3/24/20103/25/20103/25/2010APART
DetailsJim Storey
Ron Phone #: ###-#### bld final ok pending landscapping.
BLD-Aging Inspection2/18/20102/18/20102/18/2010 PASS
DetailsTom Arcoraci
BLD-Aging Inspection12/8/200912/8/200912/8/2009 PASS
DetailsTom Arcoraci
CHANGE STATUS TO (ISS)  11/3/2009 DONE
DetailsTisha Gallop
plan mod approved
Routing - PUBLIC WORKS10/16/2009 10/23/2009 PASS
DetailsBeverly Hall
Routing - PUBLIC WORKS10/22/2009 10/23/2009 PASS
DetailsBeverly Hall
Routing - PLAN CHECK10/23/2009 10/23/2009 PASS
DetailsSam Zahorka
Routed to Brian Murphy with Public works.
Routing PW Drainage10/22/2009 10/22/2009 PASS
DetailsBrian Murphy
Plan resubmittals received  10/21/2009 DONE
received 5 copies of sheet C1.1 taken to Sam Z .
Plan Modification Accepted  10/15/2009 DONE
Plan mod rec'd to match actual construction; new tank does not drain runoff to the landscape but actually collects runoff which reduces the site drainage reuirements. The path about the tank is held closer to the buildings and the design has been modified to sheet flow all runoff away from the tank and buildings which allows runoff to be collected in a "collection swale" which routes the runoff to an infiltration swale
CHANGE STATUS TO (REV)  10/15/2009 DONE
BLD-Framing/Rough-in10/5/200910/5/200910/5/2009PPASS
DetailsJim Storey
Ron Phone #: ###-#### roof framiming ok ofr exterior cover/ pending trade ri and insulation insp.
BLD-Other9/30/20099/30/20099/30/2009PPASS
DetailsJim Storey
CMU inspection please around 1:30 if possible Phone #: ###-#### topped out with cmu/ rebar ok si on site.
BLD-Footing9/28/20099/29/20099/29/2009APART
DetailsJim Storey
ron - re-bar Phone #: ###-#### topped out n and south walls as well as center wall.ok pending si report rebar ok.
BLD-Concrete9/25/20099/25/20099/25/2009PPART
DetailsJim Storey
Ron Phone #: ###-#### first lift of cmu blk placment in progess rebar in the process of being placed all is progressing ok si to be on site monday for insp. of grout and remainder of rebar.
BLD-Foundation9/17/20099/17/20099/17/2009PPASS
DetailsJim Storey
Ian Phone #: ###-#### pending si report insp. was eraler in the day.
BLD-Conference9/17/20099/17/20099/17/2009APASS
DetailsJim Storey
ring rebar lap ok and placment ok form work in progress/ reviewed w/derill the supper as to si procegers.
BLD-Foundation9/16/20099/16/20099/16/2009PPASS
DetailsJim Storey
ron//want right after lunch if possible Phone #: ###-#### rebar ok and lap to cmu ok wall ok
BLD-Footing9/15/20099/15/20099/15/2009PPASS
DetailsJim Storey
ron - right after lunch if possible Phone #: ###-####
BLD-Footing9/14/20099/15/20099/15/2009APASS
DetailsJim Storey
Ian-late am if possible please Phone #: ###-#### si on site pending report soil report done ft for building ok/ rat slab for tank ok
Inspection Record Card- Bld  9/11/2009 DONE
Permit Ready to Issue  9/11/2009 DONE
Issue PAID IN FULL permit  9/11/2009 DONE
Routing - PLAN CHECK9/3/2009 9/10/2009 PASS
DetailsSam Zahorka
Routing - PLANNING Land Div9/9/2009 9/10/2009 PASS
DetailsTodd Tucker
ROS09-00015 has been signed by the Planning Director and is at the county to be recorded.
Routing - PLANNING9/10/2009 9/10/2009 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK9/10/2009 9/10/2009 PASS
DetailsAndrea Tuning
PLANS/APPL TAKEN TO FRONT DESK  9/10/2009 DONE
DetailsSam Zahorka
Plan assigned to (SRZ)8/10/2009 9/10/2009 PASS
DetailsSam Zahorka
9/10/2009 16:08:44 SRZ - activity updated through activity BLDA022 from case BLD09-01336.
Routing - PLANNING9/2/2009 9/3/2009 FAIL
DetailsAndrea Tuning
The parcel configuration does not match what was submitted with the DR application. Andrea Tuning- DRH09-00148
Routing - PLANNING Land Div9/3/2009 9/3/2009 FAIL
DetailsTodd Tucker
Building Permit cannont be issued until the Record of Survey Application for a Property Line Adjustment has been completed and all required documents have been recorded.
Routing PW Drainage9/2/2009 9/2/2009 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS9/2/2009 9/2/2009 PASS
DetailsBeverly Hall
Routing - FIRE8/26/20098/26/20099/1/2009 PASS
DetailsScott Arellano
Plans approved with red line comments. Existing hydrant locations approved by Fire Code Official.
1st review completed  9/1/2009 FAIL
Failed Public Works, Planning,.
Route to Impact Fee Review8/26/20098/31/20098/26/2009 PASS
DetailsCindy M. Gould
Demo permit listed with this BLD was on a different lot no credit given
Routing - PLAN CHECK8/18/2009 8/26/2009 PASS
DetailsSam Zahorka
Plan resubmittals received  8/25/2009  
DetailsSam Zahorka
Rec'd two copies of sheets C1.1 and C1.2- inserted by arch rep- taken to Sam
Routing Off Site - STRUCTURAL8/24/2009 8/24/2009 PASS
DetailsSam Zahorka
Plan Reviewer's activity  8/20/2009 DONE
DetailsSam Zahorka
Recieved structural resubmittals but no foundation drawings, structural calculations, or foundation calculations for the steel tank. Waiting for these items before routing back to the outsourced structural reviewer per telephone conversation with the architect Mr. Larson.
Telephone call  8/20/2009 DONE
DetailsSam Zahorka
Recieved structural resubmittals but no foundation drawings, structural calculations, or foundation calculations for the steel tank. Waiting for these items before routing back to the outsourced structural reviewer per telephone conversation with the architect Mr. Larson.
Routing PW Drainage8/13/2009 8/18/2009 FAIL
DetailsBrian Murphy
Need to update O and M. Need swale sand depth. Brian Murphy ###-####
Plan resubmittals received  8/18/2009  
DetailsTisha Gallop
Received three copies of transmittal, response comments, structural calcs and sheet S-1.1; inserted by arch. rep. and plans taken back to erosion
Routing - PLANNING8/18/2009 8/18/2009 FAIL
DetailsAndrea Tuning
The parcel configuration does not match what was submitted with the DR application. Andrea Tuning- DRH09-00148
Routing - PUBLIC WORKS8/12/2009 8/18/2009 FAIL
DetailsBeverly Hall
Failed by BM
Routing - Erosion and Sediment8/18/2009 8/18/2009 PASS
DetailsSteven Webb
ESC09-00501 plan approved with attched conditions.
Routing Off Site - STRUCTURAL8/11/2009 8/13/2009 FAIL
DetailsSam Zahorka
Recieved outsourced Structural Reviewers comments/corrections and emailed to the Registered Design Proffessional.
Routing PW Environmental8/12/2009 8/13/2009 PASS
DetailsWalt Baumgartner
WBSD project. Reviewed for new prefab digester tank and equipment control building. Overall facility subject to Pretreatment Program permit conditions.
Routing PW Sewer Rating8/12/2009 8/13/2009 PASS
DetailsConnie Baumgartner
Plan Reviewer's activity  8/13/2009 DONE
DetailsSam Zahorka
Emailed Structural Reviewers corrections to the registered design proffessional.
Routing - Addressing8/12/2009 8/12/2009 PASS
DetailsApril Wing
Routing - PLANNING Land Div8/11/2009 8/12/2009 FAIL
DetailsTodd Tucker
Building Permit cannont be issued until the Record of Survey Application for a Property Line Adjustment has been completed and all required documents have been recorded.
Plans ACCEPTED BY PLAN TECH  8/11/2009 DONE
Plan routing begun/NEW & ADDTN  8/11/2009  
Pending Assignment by JCM8/10/2009 8/10/2009 BLDA
DetailsJohn Menard
8/10/2009 10:38:30 JCM - activity updated through activity BLDA160 from case BLD09-01336.
Application received 8/10/2009   
Routing - PLAN CHECK9/1/2009   PEND
DetailsSam Zahorka
Pending Public Works and Planning to pass.
Routing PW Drainage10/15/2009    
DetailsBrian Murphy
Routing - PUBLIC WORKS GRADING10/23/2009    
DetailsBrian Murphy