Permit Information
Permit NumberBLD09-01337
StatusFinaled
Name HARRY W MORRISON FOUNDATION INC
Site Address 827 E PARK BLVD STE 100 & 120
Project NamePEAK BROADCASTING
Customer Number 
ePlanReviewNo
Description
(PEAK BROADCASTING - Morrison Foundation Building - STE# 100) Permit is to combine the two first floor tenants into a 9,765 square foot whole floor tenant and remove the interior unenclosed stair to isolate the second floor into two tenant spaces (suite 201 / 8,647 square feet and suite 200 / 1,362 square feet). Approval per approved plans on file. Work to include: [construction of interior non-bearing walls to create five offices, one storage room, a receptionist area, and a work room], demo existing unenclosed stairwell and infill with original const., relocating existing lighting, relocate existing ducts and diffusers, new doors and hardware, new accessible sales and service counter, and interior finishes in compliance with chapter 8 of the 2006 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. *TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  2/2/2010 DONE
DetailsBarbara Stitt
Bill goes to Harry Morrison Foundation (Parcel Owner) per HC Company///2-2-10 BAS
Third Notice 1/17/20101/13/2010 DONE
Second Notice 1/9/20101/12/2010 DONE
First Notice 12/3/200912/30/2009 DONE
Print Occupancy Form  11/23/2009 DONE
DetailsTisha Gallop
lost card
Permanent Occupancy  11/23/2009 DONE
DetailsTisha Gallop
BLD-Final11/17/200911/17/200911/18/2009PPASS
DetailsDave Hannah
Please call 1/2 hour upon arrival, thanks. Phone #: ###-#### Internet Inspection Request from: Darren Gossett
FIRE-Final Inspection11/17/200911/17/200911/17/2009APASS
DetailsForrest France
Noted correction items verified for completion, fire life safety final approved.
FIRE-Final Inspection11/16/200911/16/200911/16/2009PNR
DetailsForrest France
Items noted include two fire extinguishers at the 2nd floor common corridor overdue current annual certification, remove dust cover at the smoke detector, replace drop ceiling tiles to maintain thermal response for the pendent sprinklers, clear path of egress where obstructed at the first floor corridors.
FIRE-Final Inspection11/9/200911/10/200911/10/2009ANR
DetailsForrest France
Building life safety final pending project related fire alarm work.
FIRE-Final Inspection11/3/200911/3/200911/3/2009PNR
DetailsForrest France
Pending project related fire alarm permit work final.
BLD-Conference10/15/200910/15/200910/16/2009PPART
DetailsDave Hannah
Please call 1/2 hour upon arrival thanks, Darren Phone #: ###-#### Internet Inspection Request from: Darren Gossett ok to cover ceiling
BLD-Framing/Rough-in9/24/20099/25/20099/25/2009APASS
DetailsDave Hannah
Please call 1/2 hour upon arrival, thanks.
Darren Phone #: ###-#### Internet Inspection Request from: Darren Gossett ok to cover after elec r/i
Issue PAID IN FULL permit  8/31/2009 DONE
DetailsTisha Gallop
Print Occupancy Form  8/19/2009 DONE
Details
Telephone call  8/19/2009 DONE
Details
t/c w matt at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  8/19/2009 DONE
Details
Routing - PLAN CHECK8/11/2009 8/18/2009 PASS
DetailsTim L. Woodard
Plan assigned to (TLW)8/10/2009 8/18/2009 PASS
DetailsTim L. Woodard
8/18/2009 15:51:31 TLW - activity updated through activity BLDA022 from case BLD09-01337.
Routing - FIRE  8/18/2009 PASS
DetailsTim L. Woodard
Field Verify
1st review completed  8/18/2009 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  8/18/2009 DONE
DetailsTim L. Woodard
Case Summary (BLD)  8/18/2009 DONE
DetailsTim L. Woodard
Routing - PUBLIC WORKS8/10/2009 8/11/2009 PASS
DetailsBeverly Hall
Routing PW Sewer Rating8/11/2009 8/11/2009 PASS
DetailsConnie Baumgartner
Recd Pcfee & Taken To Pln CK  8/10/2009 DONE
Routing - Addressing8/10/2009 8/10/2009 PASS
DetailsApril Wing
Plans ACCEPTED BY PLAN TECH  8/10/2009 DONE
ok per Tim W for a level 2 intake
Application received 8/10/2009