First Notice | | 2/16/2013 | 2/6/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/6/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 2/4/2013 | 2/5/2013 | 2/5/2013 | A | PASS |
Dave Hannah
|
|
|
Per 410 Fire sprinkler and life safety finished - no card on site to sign- call if questions ###-####
|
FIRE-Final Inspection | 2/4/2013 | 2/4/2013 | 2/4/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety final approved. No signature card on site.
|
Telephone call | | | 2/1/2013 | | |
|
|
|
FIR12-00754 issued 12/28/12 for Delta Fire Spriklers no ispections at this time
|
Telephone call | | | 12/7/2012 | | DONE |
Barbara Stitt
|
|
|
Per Ben, American Sprinkler should be submitting plans next week. 12-7-12 @ 9:40am//BAS
|
FIRE-Conference | 11/19/2012 | 11/20/2012 | 11/20/2012 | A | DONE |
Forrest France
|
|
|
On site conference with tenant rep. regarding overspaced fire sprinkler coverage at one room. The posted fire extinguisher is overdue annual certification. Upon completion of C/N items, fire life safety can be passed.
|
BLD-Aging Inspection | 9/28/2012 | 9/28/2012 | 10/5/2012 | | PEND |
Dave Hannah
|
|
|
needs fire final
|
BLD-Aging Inspection | 4/23/2012 | 4/23/2012 | 5/1/2012 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/1/2012 | 2/1/2012 | 2/1/2012 | | DEFR |
Dave Hannah
|
|
|
sent to fire
|
BLD-Aging Inspection | 9/14/2011 | 9/14/2011 | 9/22/2011 | | DEFR |
Dave Hannah
|
|
|
sent to forest
|
BLD-Aging Inspection | 9/14/2011 | 9/14/2011 | 9/14/2011 | A | FAIL |
Forrest France
|
|
|
Overspaced fire sprinklers at one area.
|
BLD-Aging Inspection | 7/15/2011 | 7/15/2011 | 7/15/2011 | P | PEND |
Forrest France
|
|
|
Pending fire sprinkler work.
|
BLD-Aging Inspection | 7/15/2011 | 7/15/2011 | 7/15/2011 | | DEFR |
Dave Hannah
|
|
|
sent to fire
|
FIRE-Conference | 5/5/2011 | 5/5/2011 | 5/5/2011 | P | DONE |
Forrest France
|
|
|
Conversation with tenant regarding spacing issues at fire sprinkler coverage.
|
BLD-Aging Inspection | 4/28/2011 | 4/28/2011 | 4/30/2011 | | FAIL |
Dave Hannah
|
|
|
needs fire finals
|
FIRE-Final Inspection | 4/28/2011 | 4/29/2011 | 4/28/2011 | A | FAIL |
Forrest France
|
|
|
Fire sprinkler coverage at the VIP room is incorrectly spaced, fire extinguisher is overdue certification and needs posted as discussed.
|
BLD-Final | 2/17/2011 | 2/17/2011 | 2/17/2011 | P | PASS |
Dave Hannah
|
|
|
ken Phone #: ###-#### ok for perm occ
|
BLD-Conference | 2/10/2011 | 2/10/2011 | 2/14/2011 | P | CANC |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/8/2011 | 2/8/2011 | 2/10/2011 | | PART |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 12/7/2010 | 12/7/2010 | 12/8/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 10/4/2010 | 10/4/2010 | 10/11/2010 | | DEFR |
Dave Hannah
|
|
|
|
Temporary Occupancy UNPAID FEE | | | 9/22/2009 | | DONE |
|
|
|
|
BLD-Final | 9/18/2009 | 9/21/2009 | 9/21/2009 | P | PART |
Dave Hannah
|
|
|
ken Phone #: ###-#### ok for temp occ needs to resubmit plans that reflect what was built mainly no vip lounge
|
FIRE-Final Inspection | 9/18/2009 | 9/21/2009 | 9/21/2009 | A | FAIL |
Forrest France
|
|
|
Correction items noted at the previous inspection are not done, project is not in condition for final at this time.
|
FIRE-Final Inspection | 9/16/2009 | 9/16/2009 | 9/16/2009 | A | NR |
Forrest France
|
|
|
Space not ready for final inspection. Inspection correction items include the need for at least one fire extinguisher, and replacement of sticker on main exterior door signage indicating "Doors to be unlocked when building is occupied". Existing sticker is deteriorated.
|
BLD-Framing/Rough-in | 9/9/2009 | 9/10/2009 | 9/11/2009 | A | PART |
Dave Hannah
|
|
|
please call Ken ###-#### ok to cover front area area in back not framed and the owner now does no want to finish this area but leave it as is for now
|
Issue PAID IN FULL permit | | | 9/3/2009 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 9/1/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/1/2009 | | DONE |
|
|
|
|
Telephone call | | | 9/1/2009 | | DONE |
|
|
|
called Ken permit ready and fee given
|
Plan assigned to (TLW) | 8/18/2009 | | 8/31/2009 | | PASS |
Tim L. Woodard
|
|
|
8/31/2009 16:19:13 TLW - activity updated through activity BLDA022 from case BLD09-01405.
|
Routing - PLAN CHECK | 8/28/2009 | | 8/31/2009 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines on plans. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 8/31/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 8/28/2009 | | |
Tisha Gallop
|
|
|
received two copies of sheet A1; taken to Tim Woodard
|
Routing - PLUMBING | 8/28/2009 | | 8/28/2009 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - PLAN CHECK | 8/24/2009 | | 8/26/2009 | | PASS |
Tim L. Woodard
|
|
|
Plans approved with redlines. TLW
|
1st review completed | | | 8/26/2009 | | FAIL |
Tim L. Woodard
|
|
|
Failed Plumbing
|
Routing - FIRE | | | 8/26/2009 | | PASS |
Tim L. Woodard
|
|
|
Field Verify. TLW
|
Plan Reviewer's activity | | | 8/25/2009 | | DONE |
Tim L. Woodard
|
|
|
TI Level Changed to a level II vs. a level I. Due to change in reviewing depts. Mechanical and Plumbing are required to now review Nail Saloons. TLW
|
Routing - MECHANICAL | 8/21/2009 | | 8/24/2009 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/24/2009 | | 8/24/2009 | | FAIL |
Bill VanDegrift
|
|
|
waste and water is undersized. water to pedicure ststions must be protected by an r.p.. isolate from potable water. show locations of waste terminations. show venting for indirect waste.
|
Routing - PUBLIC WORKS | 8/18/2009 | | 8/21/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLAN CHECK | 8/21/2009 | | 8/21/2009 | | PEND |
Tim L. Woodard
|
|
|
routed to Mech. to review. TLW
|
Routing - Addressing | 8/20/2009 | | 8/20/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 8/18/2009 | 8/18/2009 | | FAIL |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/18/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/18/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 8/18/2009 | | 8/18/2009 | | PEND |
Tim L. Woodard
|
|
|
Sent plans to public works for review. TLW
|