Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD09-01425
StatusFinaled
Name MATHIEU CHOUX
Site Address 200 N CAPITOL BLVD
Project NameADELMAN BLDG - BASEMENT
Customer Number 
ePlanReviewNo
Description
(CATACOMB LOUNGE - BASEMENT) The fire sprinkler system is used to substitute for 1-hr fire-resistance-rated construction of the building. To change a 1,919 square foot basement banquet room into a lounge. Work is to include an elevated floor, a ramp accessible to the disabled, an elevated disk jockey platform, steps, handrails, a bar, tables, and chairs. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/9/20102/19/2010 DONE
Third Notice 1/18/20101/27/2010 DONE
faxed, mailed and called
Telephone call  1/27/2010 DONE
DetailsTisha Gallop
called and spoke with Mathieu, no response from him for months of requests, still need final value and will fax notice to him right now. He said ok.
Third Notice 11/30/200912/29/2009 DONE
faxed, mailed and called
Telephone call  12/29/2009 DONE
DetailsTisha Gallop
Called number for Mathieu(applicant) and Malorie said he's in France and won't be back until the 2nd week in January. I told her ok but for him to do final values as soon as he gets back because we have asked for FV for two months with no response.
Second Notice 11/14/200911/25/2009 DONE
sent by mail
First Notice 11/2/200911/4/2009 DONE
Permanent Occupancy  10/23/2009 DONE
DetailsTisha Gallop
BLD-Final10/16/200910/19/200910/22/2009APASS
DetailsDave Hannah
Matthew ###-####
BLD-Final10/6/200910/7/200910/9/2009PNR
DetailsDave Hannah
mathew Phone #: ###-####
FIRE-Final Inspection10/6/200910/7/200910/7/2009APASS
DetailsForrest France
Fire life safety final okay pending installation of one fire extinguisher, post max occupant load sign, repair one EM light at the back exit corridor. Items to be done prior to structural final approval.
FIRE-Conference9/30/200910/1/200910/1/2009ADONE
DetailsForrest France
On site conference regarding fire code review notes, general requirements, new raised platforms, fire sprinkler coverage, etc.
FIRE-Conference9/30/20099/30/20099/30/2009PDEFR
DetailsForrest France
Scheduled for 10/1 as discussed.
BLD-Conference9/29/20099/29/20099/29/2009PDONE
DetailsDave Hannah
Mathieu Phone #: ###-####
Print Occupancy Form  9/29/2009 DONE
Details
Permit Ready to Issue  9/29/2009 DONE
Telephone call  9/29/2009 DONE
Called Mathieu permit ready and fee given
Issue PAID IN FULL permit  9/29/2009 DONE
PLANS/APPL TAKEN TO FRONT DESK  9/28/2009  
Plan assigned to (CJW)8/24/2009 9/28/2009 PASS
DetailsCarl Westfall
9/28/2009 14:05:36 CJW - activity updated through activity BLDA022 from case BLD09-01425.
Routing - PLAN CHECK9/14/2009 9/28/2009 PASS
DetailsCarl Westfall
Drawings approved with lots of "red lines" after the resubmittal review.
Plan resubmittals received  9/24/2009  
DetailsCarl Westfall
Rec'd two copies of sheet A-1- taken to Carl w
Routing - FIRE9/11/20099/11/20099/14/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  9/14/2009 FAIL
Failed Plan Check
Route to Impact Fee Review9/11/20099/16/20099/11/2009 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Routing - PLAN CHECK8/26/2009 9/11/2009 FAIL
DetailsCarl Westfall
The IBC plan review was started on September 10, 2009 and was finished the next day. Revised drawings were required. See the plan review report.
Plan resubmittals received  9/3/2009  
DetailsCarl Westfall
rec'd addendum to lease agreement- taken to Carl W
Routing PW Environmental8/25/2009 8/26/2009 PASS
DetailsWalt Baumgartner
OK per Terry Alber - no new food equipment.
Routing - PUBLIC WORKS8/24/2009 8/26/2009 PASS
DetailsBeverly Hall
Pending Assignment by JCB8/21/2009 8/24/2009 DONE
DetailsJason Blais
Plan resubmittals received  8/24/2009 DONE
DetailsTisha Gallop
received completed application; taken to JCB.
Intake Approval  8/24/2009 PASS
DetailsJason Blais
Received signed and updated application.
Routing - Addressing8/24/2009 8/24/2009 PASS
DetailsApril Wing
Telephone call  8/21/2009 DONE
DetailsJason Blais
Called applicant concerning signing and completing the rest of the application. He stated he will and drop off on Monday 8/24.
Plan Reviewer's activity  8/21/2009 DONE
DetailsJason Blais
E-mailed applicant the building permit application back which needs a signature and also additional information filled out. Once received will continue to process plans and application.
Intake Approval  8/21/2009 FAIL
DetailsJason Blais
Need signed and completed application. E-mailed applicant.
Application received 8/20/2009