Permanent Occupancy | | | 10/1/2009 | | DONE |
|
|
|
|
BLD-Final | 9/22/2009 | 9/23/2009 | 9/23/2009 | P | PASS |
Tom Arcoraci
|
|
|
BRINDY Phone #: ###-####
|
FIRE-Final Inspection | 9/22/2009 | 9/23/2009 | 9/23/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Correct hardware was being installed on the warehouse as I left
|
BLD-Final | 9/9/2009 | 9/10/2009 | 9/10/2009 | P | NR |
Jim Sly
|
|
|
brindi or rob Phone #: ###-#### Need Fire final
|
FIRE-Final Inspection | 9/9/2009 | 9/10/2009 | 9/10/2009 | A | FAIL |
Troy Cobbley
|
|
|
Provide single action hardware on the warehouse door.
|
Issue PAID IN FULL permit | | | 9/9/2009 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 8/28/2009 | | 9/4/2009 | | PASS |
Tim L. Woodard
|
|
|
9/4/2009 12:19:09 TLW - activity updated through activity BLDA022 from case BLD09-01482.
|
Routing - PLAN CHECK | 8/28/2009 | | 9/4/2009 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 9/4/2009 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 9/4/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 9/4/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 9/4/2009 | | DONE |
|
|
|
|
Telephone call | | | 9/4/2009 | | DONE |
|
|
|
left vm for brindi blessing at ###-#### - permit ready and fees paid
|
Permit Ready to Issue | | | 9/4/2009 | | DONE |
|
|
|
|
Intake Approval | | | 9/1/2009 | | PASS |
Tim L. Woodard
|
|
|
Plans accepted. TLW
|
Application received | | 8/28/2009 | 8/28/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/28/2009 | | DONE |
Tisha Gallop
|
|
|
|