Third Notice | | 11/14/2009 | 11/16/2009 | | DONE |
|
|
|
|
Second Notice | | 10/31/2009 | 11/4/2009 | | DONE |
|
|
|
|
First Notice | | 10/1/2009 | 10/21/2009 | | DONE |
|
|
|
returned mail and remailed out to applicant/tenant 11/2/09 LEG
|
BLD-Final | 9/21/2009 | 9/21/2009 | 9/21/2009 | P | PASS |
Dave Hannah
|
|
|
ok for perm occ
|
FIRE-Final Inspection | 9/18/2009 | 9/21/2009 | 9/21/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy UNPAID FEE | | | 9/21/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Conference | 9/18/2009 | 9/18/2009 | 9/19/2009 | P | PASS |
Dave Hannah
|
|
|
Gordon Phone #: ###-#### ok to cover small wall
|
Print Occupancy Form | | | 9/16/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/16/2009 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 9/16/2009 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/14/2009 | 9/17/2009 | 9/15/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - FIRE | 9/14/2009 | 9/14/2009 | 9/15/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan assigned to (CJW) | 9/3/2009 | 9/3/2009 | 9/15/2009 | | PASS |
Carl Westfall
|
|
|
9/15/2009 16:25:26 CJW - activity updated through activity BLDA022 from case BLD09-01489.
|
1st review completed | | | 9/15/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 9/15/2009 | | 9/15/2009 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 9/15/2009 | | |
Tisha Gallop
|
|
|
received two copies of sheet A2-1; taken to Carl Westfall
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/11/2009 | | 9/14/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on September 11, 2009 and was finished September 14, 2009. Revised drawings were required. See the plan review report.
|
Routing - Design Review | | | 9/11/2009 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer Meets ordinance requirements.
|
Routing - PLUMBING | 9/9/2009 | | 9/10/2009 | | PASS |
Daryl Spivey
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 9/4/2009 | | 9/9/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Environmental | 9/8/2009 | | 9/8/2009 | | PASS |
Walt Baumgartner
|
|
|
Reviewed - tavern only, no food
|
Routing PW Sewer Rating | 9/8/2009 | | 9/8/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 9/3/2009 | | 9/4/2009 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/3/2009 | | DONE |
|
|
|
|
Application received | | 8/28/2009 | | | |
|
|
|
|