Case Summary (BLD) | | | 8/27/2019 | | DONE |
|
|
|
|
Third Notice | | 6/10/2010 | 6/2/2010 | | DONE |
|
|
|
|
Third Notice | | 5/15/2010 | 5/27/2010 | | DONE |
|
|
|
faxed
|
Second Notice | | 5/6/2010 | 5/10/2010 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 4/26/2010 | 4/26/2010 | 4/26/2010 | | DONE |
Tiffany Lowery
|
|
|
|
First Notice | 4/23/2010 | 4/23/2010 | 4/26/2010 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 4/21/2010 | 4/23/2010 | 4/23/2010 | A | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 4/23/2010 | 4/23/2010 | 4/23/2010 | P | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 4/19/2010 | 4/20/2010 | 4/21/2010 | A | CANC |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 2/19/2010 | 2/19/2010 | 2/19/2010 | | PASS |
Tom Arcoraci
|
|
|
|
(F) Reprint permit | | | 2/2/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/2/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/25/2010 | | 1/27/2010 | | PASS |
John Menard
|
|
|
|
Plan assigned to (JCM) | 1/21/2010 | | 1/27/2010 | | PASS |
John Menard
|
|
|
1/27/2010 09:13:03 JCM - activity updated through activity BLDA022 from case BLD09-01496.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2010 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 1/27/2010 | | DONE |
|
|
|
|
Telephone call | | | 1/27/2010 | | DONE |
|
|
|
called Cornel Larson plan mod ready to pick up and fee given 1-27-10 dld
|
Routing - PUBLIC WORKS | 1/21/2010 | | 1/25/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 1/25/2010 | | 1/25/2010 | | PASS |
Brian Murphy
|
|
|
old seepage bed redone and slightly move see siw fee. Brian Murphy. ###-####
|
Plan Modification Accepted | | | 1/21/2010 | | |
John Menard
|
|
|
Plan modification accepted - During construction, existing problems with drainage in the southern portion of the Darigold site have been identified. The existing seepage bed does not drain in a reasonable amount of time. The grading and drainage plans have been modified to re-consruct the existing seepage bed. This work was not indicated on the original plans. The calculations have been modified to reflect the changes on the plans. 5 copies of sheet C1.1 and 2 drainage calcs -- routed to John Menard
|
CHANGE STATUS TO (ISS) | | | 12/16/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/16/2009 | | DONE |
|
|
|
|
BLD-Footing | 12/4/2009 | 12/4/2009 | 12/4/2009 | A | CANC |
Jim Storey
|
|
|
time test
|
BLD-Footing | 12/4/2009 | 12/4/2009 | 12/4/2009 | A | PASS |
Jim Storey
|
|
|
last of interior ft at east addition shell. 1 hr
|
Plan assigned to (JCM) | 11/18/2009 | 11/18/2009 | 12/4/2009 | | PASS |
John Menard
|
|
|
12/4/2009 13:27:53 JCM - activity updated through activity BLDA022 from case BLD09-01496.
|
Routing - PLAN CHECK | 12/2/2009 | | 12/4/2009 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2009 | | DONE |
John Menard
|
|
|
|
Telephone call | | | 12/4/2009 | | DONE |
|
|
|
left vm for cornel larson at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 12/4/2009 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 11/20/2009 | | 12/2/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 11/20/2009 | | 12/2/2009 | | PASS |
Brian Murphy
|
|
|
|
BLD-Footing | 11/23/2009 | 11/23/2009 | 11/23/2009 | A | PASS |
Jim Storey
|
|
|
interior bearing strip ft rebar ok.
|
Routing - PLAN CHECK | 11/18/2009 | | 11/20/2009 | | |
John Menard
|
|
|
John Menard
|
Plan resubmittals received | | | 11/20/2009 | | |
Brian Murphy
|
|
|
Received 1 copy of plan modification application 2 copies of Phase 2 Storm Water Management Plan, 5 copies of sheets C1.2, C1.1, C1.3 and taken to Brian Murphy per Ron Hill///11-20-09 @ 11:38am BAS
|
Plan Modification Accepted | | | 11/18/2009 | | |
John Menard
|
|
|
Plan modification accepted to modify the drading & drainage plans to accomodate the architectural revisions that create a permanent addition on the northeast corner of the building. This change impacted the location of the seepage bed that was planned to recieve the eastern receiving area runoff. The new structure forced us to combine the runoff from the eastern receiving area with that of the northern dock area. The calculations have been modified to reflect the changes on the plans. 4 copies of sheets C1.1, C1.2, C1.3, C1.4 and 2 drainage calcs and routed to John Menard
|
BLD-Foundation | 11/16/2009 | 11/16/2009 | 11/16/2009 | P | PASS |
Jim Storey
|
|
|
north interior ft and wall rebar ok of shell bld.
|
FIRE-Conference | 11/13/2009 | 11/13/2009 | 11/13/2009 | A | DONE |
Forrest France
|
|
|
On site meeting with general and subcontractors regarding facility program guidelines.
|
BLD-Wall cover | 11/13/2009 | 11/13/2009 | 11/13/2009 | P | PASS |
Jim Storey
|
|
|
1:00 grout pour
|
BLD-Conference | 11/12/2009 | 11/13/2009 | 11/13/2009 | A | PASS |
Jim Storey
|
|
|
10:00 am appointment meeting of trades and inspectors to go over facilitity insp. protacall .
|
BLD-Footing | 11/12/2009 | 11/12/2009 | 11/12/2009 | P | PASS |
Jim Storey
|
|
|
interior ft appointmet 2:30 north and south sides
|
BLD-Conference | 11/10/2009 | 11/10/2009 | 11/10/2009 | A | CANC |
Jim Storey
|
|
|
time test
|
BLD-Foundation | 11/10/2009 | 11/10/2009 | 11/10/2009 | A | PASS |
Jim Storey
|
|
|
east loading dock wall. rebar ok 1 hr sch. for meetting on fri at 10:00 am with facilitys group and contrators to go over job and protacall.
|
BLD-Foundation | 11/5/2009 | 11/6/2009 | 11/6/2009 | A | PASS |
Jim Storey
|
|
|
10:30 or 11:00 appointment for dock wall. southeast wall ok 45min.
|
BLD-Foundation | 11/5/2009 | 11/5/2009 | 11/5/2009 | P | CANC |
Jim Storey
|
|
|
2:00 appointment.
|
BLD-Wall cover | 11/5/2009 | 11/5/2009 | 11/5/2009 | A | PASS |
Jim Storey
|
|
|
1 st course cmu tank and exitway from plant northwest corner of plant. ok
|
BLD-Footing | 11/4/2009 | 11/4/2009 | 11/4/2009 | P | PASS |
Jim Storey
|
|
|
south side to complet exterior of addition ok/ rebar ok
|
BLD-Footing | 11/2/2009 | 11/2/2009 | 11/2/2009 | P | PASS |
Jim Storey
|
|
|
west tank pad ft for rebar insp. 3:30 apointment w/ron ab and weld plats set with rebar double mat ok for cover west tank pad.
|
BLD-Foundation | 10/29/2009 | 10/29/2009 | 10/29/2009 | P | PASS |
Jim Storey
|
|
|
3:00 pm appt. east wall insp. center srction of wall east end of addition rebar ok si onsite/ weld plates set.
|
BLD-Footing | 10/28/2009 | 10/28/2009 | 10/28/2009 | P | PASS |
Jim Storey
|
|
|
2:30 appointment east ft and rebar of main building ok to place concrete/ compaction ok
|
BLD-Wall cover | 10/26/2009 | 10/26/2009 | 10/26/2009 | P | PASS |
Jim Storey
|
|
|
grout placement north dock 5th lift rebar ok
|
BLD-Footing | 10/26/2009 | 10/26/2009 | 10/26/2009 | P | PASS |
Jim Storey
|
|
|
wall northside main addition rebar and weld plates inplace ok
|
BLD-Other | 10/23/2009 | 10/23/2009 | 10/23/2009 | A | PASS |
Jim Storey
|
|
|
north dock 4th lift of cmu wall bond beam rebar ok for 4th lift at north dock area ie over door opening.
|
BLD-Footing | 10/23/2009 | 10/23/2009 | 10/23/2009 | A | PASS |
Jim Storey
|
|
|
ft insp for main building appt:11:30 301 ft for main addition north side rebar inplace and ok to place concrete/ ft at tank pad for building wall north west area ok to place concrete/
|
BLD-Other | 10/21/2009 | 10/22/2009 | 10/22/2009 | A | PASS |
Jim Storey
|
|
|
3rd lift north dock around 11:00 am
|
BLD-Wall cover | 10/20/2009 | 10/21/2009 | 10/21/2009 | A | PASS |
Jim Storey
|
|
|
2nd lift recieving dock north side late insp. rebar ok si to test grout on sch.
|
BLD-Footing | 10/20/2009 | 10/20/2009 | 10/20/2009 | P | PASS |
Jim Storey
|
|
|
northwest 60000 tank rebar as perplan si to be on site at placment.
|
BLD-Wall cover | 10/20/2009 | 10/20/2009 | 10/20/2009 | P | PART |
Jim Storey
|
|
|
cmu first lift receiving dock north side
|
Plan resubmittals received | | | 10/16/2009 | | DONE |
|
|
|
received 1 letterof transmittal 3 review comment response,and 3 copies of sheet S4.1,S4.2 taken to Ron Hill ( this permit was issued 10-2-09 dld
|
BLD-Foundation | 10/15/2009 | 10/15/2009 | 10/15/2009 | P | PASS |
Jim Storey
|
|
|
rebar ok nw area si pending
|
BLD-Footing | 10/14/2009 | 10/14/2009 | 10/14/2009 | P | PART |
Jim Storey
|
|
|
ron Phone #: ###-#### ft for bld. northwest corner of building rebar ok si onsite taking concrete samples.
|
Route to Impact Fee Review | 9/14/2009 | 9/17/2009 | 10/2/2009 | | PASS |
Cindy M. Gould
|
|
|
Footing and Foundation Only NO IMPACT FEES
|
Permit Ready to Issue | | | 10/2/2009 | | DONE |
|
|
|
|
Telephone call | | | 10/2/2009 | | DONE |
|
|
|
Called Mike with Van Auker Construction and told him that permit is ready & fees due///10-2-09 @ 8:30AM BAS
|
Plan resubmittals requested | | | 10/2/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the second structural review requesting revisions. These final revisions will be addressed during the shell and core permit review. JCM
|
Issue PAID IN FULL permit | | | 10/2/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/15/2009 | | 10/1/2009 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 9/23/2009 | | 10/1/2009 | | PASS |
John Menard
|
|
|
Called Action Couriers for pick up - Received comment list from consulting strucltural engineer releasing foundation. Final comments can be addressed under the shell permit. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2009 | | DONE |
John Menard
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2009 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 8/31/2009 | | 10/1/2009 | | PASS |
John Menard
|
|
|
10/1/2009 09:00:00 JCM - activity updated through activity BLDA022 from case BLD09-01496.
|
Plan resubmittals received | | | 9/23/2009 | | DONE |
|
|
|
received 2 responses,3 comment response calcs, 3 copies of C1.4, 0, S1.2,S1.3,S2.1,S2.2,S2.3,S2.4,S3.1,S3.2,S4.1,S4.2,PC1 taken to John M.
|
Plan resubmittals requested | | | 9/21/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Plan resubmittals received | | | 9/21/2009 | | |
John Menard
|
|
|
rec'd 3 copies of PC1.1; given to Ron Hill
|
Routing Off Site - STRUCTURAL | 8/31/2009 | | 9/18/2009 | | FAIL |
John Menard
|
|
|
Received comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - FIRE | 9/14/2009 | 9/14/2009 | 9/15/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 9/15/2009 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/11/2009 | | 9/14/2009 | | PASS |
John Menard
|
|
|
|
Routing PW Environmental | 9/10/2009 | | 9/11/2009 | | PASS |
Walt Baumgartner
|
|
|
Reviewed - located in West Boise Sewer Dist.
|
Routing PW Street Lights | 9/11/2009 | | 9/11/2009 | | PASS |
Hank Alarcon
|
|
|
Rob Bousfield signed for Hank A.
|
Routing - PLANNING | 9/11/2009 | | 9/11/2009 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PUBLIC WORKS | 9/1/2009 | | 9/11/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - Erosion and Sediment | 9/11/2009 | | 9/11/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00554
|
Routing PW Solid Waste | 9/10/2009 | | 9/10/2009 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Sewer Rating | 9/10/2009 | | 9/10/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 9/2/2009 | | 9/10/2009 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 9/9/2009 | | |
|
|
|
Rec'd 5 copies of sheets A1.2; C1.3; C1.4- inserted by arxh rep, taken to Brian M
|
Routing - Addressing | 9/2/2009 | | 9/2/2009 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 8/31/2009 | | 9/1/2009 | | PASS |
Todd Tucker
|
|
|
|
Application received | | 8/31/2009 | 8/31/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/31/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/31/2009 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 8/31/2009 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|