Case Summary (BLD) | | | 9/19/2013 | | DONE |
|
|
|
|
First Notice | | 2/20/2010 | 3/2/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 2/9/2010 | 2/10/2010 | 2/10/2010 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. all issues resolved. ok for perm occ.
|
Permanent Occupancy | | | 2/10/2010 | | DONE |
|
|
|
|
BLD-Final | 2/8/2010 | 2/9/2010 | 2/9/2010 | P | FAIL |
Mike Jordan
|
|
|
John Phone #: ###-####. Needs to provide Listed data for Penetrations, Also needs to repair 2hr. wall in canopy, does not seperate completly.
|
FIRE-Final Inspection | 2/8/2010 | 2/9/2010 | 2/9/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The builder will provide the correct sticker at the main exit prior to the building inspection.
|
CHANGE STATUS TO (ISS) | | | 2/8/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/8/2010 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 2/4/2010 | 2/4/2010 | 2/5/2010 | | PASS |
Carl Westfall
|
|
|
2/5/2010 11:39:10 CJW - activity updated through activity BLDA022 from case BLD09-01564.
|
Routing - PLAN CHECK | 2/4/2010 | | 2/5/2010 | | PASS |
Carl Westfall
|
|
|
Approved plan modification. The hybrid 2-hr wall is allowed for this building and this application only because without the fire barrier, this part of the building is only a little over the allowed building area. The approved detail is NOT appropriate or approved for any other application. CJW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/5/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/5/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan Modification Accepted | | | 2/4/2010 | | |
Carl Westfall
|
|
|
Rec'd for new two hour wall details; sheet A1.3- no change in value- taken to Carl W
|
Print Occupancy Form | | | 2/3/2010 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 1/20/2010 | 1/21/2010 | 1/21/2010 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Interior wood framed walls for restroom and demising wall. Also 2hr. fire barrier wall. Noted to contractor that he needs to provide a portion of counter to meet ada requirements as noted on approved plans. Also verified all backing for ada elements in restroom.
|
BLD-Conference | 1/14/2010 | 1/15/2010 | 1/15/2010 | A | DONE |
Mike Jordan
|
|
|
john - please call 1/2 hr prior so he can meet you there Phone #: ###-####. Received additional deatils from architect regarding steel beam and wood truss penetrations. Will discuss wtih structural supervisor. Contractor also wants to change were 2hr. fire barrier wall passes through canopy section. Noted to contractor that architect would have to resubmit details to plan review for approval.
|
BLD-Conference | 1/6/2010 | 1/7/2010 | 1/7/2010 | A | DONE |
Mike Jordan
|
|
|
John please call 30 min before going out Phone #: ###-####. Met with contractor to go over 2hr. fire barrier wall details. Issued c/n for architect to provide details showing UL approved membrane and thru penetrations into 2hr. fire barrier wall, framing details for 2hr. fire barrier wall around wood truss, steel beam, connection to steel and approved UL listing for penetration of wood trusses into 2hr. fire barrier wall.
|
Meeting | | | 1/6/2010 | | |
Tisha Gallop
|
|
|
John Foster rep for JLJ Enterprises in office to change permit into new GC and pay transfer fee. New tenant is Traditional ATA Idaho Martial Arts (previous tenant applied was ATA Idaho Martial Arts) and new applicant is Carrie Jewett, see revised application scanned in documents. Scope of work remains exactly the same as on approved plans.
|
(F) Reprint permit | | | 1/6/2010 | | DONE |
Tisha Gallop
|
|
|
|
Meeting | | | 1/5/2010 | | DONE |
Tisha Gallop
|
|
|
K2 construction in office and submitted letter they are no longer GC of the project anymore. Contact for owner is Gary Weiner and Paul Lamon (Idaho Marial Arts) is no longer going to be the tenant.
|
Meeting | | | 11/17/2009 | | DONE |
Rita DeYoung
|
|
|
Carl W spoke to me regarding changing the contractor on this permit, Carl received a call from the contractor stating they may not be doing the work and they may be changing it from ID Martial Arts to another name. We need a letter from K2 Cont. to ask for the name to be removed and who the new cont. will be.
|
Print Occupancy Form | | | 10/26/2009 | | DONE |
|
|
|
|
Telephone call | | | 10/26/2009 | | DONE |
|
|
|
left vm for jeff likes at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/26/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/26/2009 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/14/2009 | | 10/23/2009 | | PASS |
Carl Westfall
|
|
|
10/23/2009 15:22:17 CJW - activity updated through activity BLDA022 from case BLD09-01564.
|
Routing - PLAN CHECK | 10/7/2009 | | 10/23/2009 | | DONE |
Carl Westfall
|
|
|
Drawings were on hold until called for by Planning.
|
Routing - PLANNING | 10/23/2009 | | 10/23/2009 | | PASS |
Susan Riggs
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/28/2009 | | 10/8/2009 | | PASS |
Carl Westfall
|
|
|
Completed the 2nd IBC plan review. Drawings approved with "red lines".
|
Plan resubmittals received | | | 10/1/2009 | | |
Tisha Gallop
|
|
|
received transmittal, response to comments, and two copies of plan sheets A1.1, A1.2, A3.1; taken to Carl Westfall
|
Routing - FIRE | 9/22/2009 | 9/22/2009 | 9/28/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 9/28/2009 | | FAIL |
|
|
|
Failed Plan Check, Design Review
|
Route to Impact Fee Review | 9/22/2009 | 9/25/2009 | 9/24/2009 | | PASS |
Cindy M. Gould
|
|
|
tenant improvement no fees
|
Routing - PLAN CHECK | 9/15/2009 | | 9/22/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on September 18, 2009 and was finished on September 22, 2009. Revised drawings were required. See the plan review report.
|
Routing - Design Review | 9/15/2009 | | 9/15/2009 | | FAIL |
Sarah Schafer
|
|
|
Sarah Schafer - Assembly type use in retail building
Per the development agreement under CAR04-00057, the use is not allowed within this development. The development agreement will need to be modified to allow the use.
|
Routing - PUBLIC WORKS | 9/14/2009 | | 9/15/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 9/15/2009 | | 9/15/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 9/14/2009 | | 9/14/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 9/11/2009 | | 9/14/2009 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/11/2009 | | DONE |
|
|
|
|
Intake Approval | | | 9/10/2009 | | PASS |
Tim L. Woodard
|
|
|
Applicant had all plan submittal requirements. TLW
|
Application received | | 9/10/2009 | | | |
|
|
|
|