First Notice | 5/28/2010 | 5/28/2010 | 5/28/2010 | | DONE |
Jim Storey
|
|
|
This permit finaled on the web by Brandon Byington
|
BLD-Final | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | PASS |
Jim Storey
|
|
|
Inspection requested from web by: Mike Shain Phone #: ###-####
|
DOC - Permit Finaled | 5/28/2010 | 5/28/2010 | 5/28/2010 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 5/25/2010 | 5/26/2010 | 5/26/2010 | A | PASS |
Troy Cobbley
|
|
|
Revised drawings have been provided and approved which show the new fire hydrant being deleted. Life safety passed.
|
FIRE-Final Inspection | 5/17/2010 | 5/18/2010 | 5/19/2010 | A | FAIL |
Troy Cobbley
|
|
|
Could not final permit due to a new fire hydrant being shown not only on sheet ADD on this permit but also on the phase I drawings sheet F-1. The hydrant has not been installed. I spoke to scott arellano and he stated that the hydrant is not required but plans sheets will need to be resubmitted showing the fire hydrant removed for both permits. I let Mike the job superintendant know. The other option is to install the fire hydrant.
|
BLD-Final | 5/17/2010 | 5/18/2010 | 5/18/2010 | P | PART |
Tom Arcoraci
|
|
|
Grading permit ###-#### Inspection requested from web by: Mike Shain Phone #: ###-#### needs plum and fire
|
BLD-Conference | 4/28/2010 | 4/28/2010 | 4/28/2010 | P | PASS |
Tom Arcoraci
|
|
|
demo and grading ok
|
BLD-Aging Inspection | 4/28/2010 | 4/28/2010 | 4/28/2010 | | PART |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 2/22/2010 | 2/22/2010 | 2/22/2010 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 2/22/2010 | 2/22/2010 | 2/22/2010 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Conference | 12/22/2009 | 12/22/2009 | 12/22/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 12/22/2009 | 12/22/2009 | 12/22/2009 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Foundation | 10/22/2009 | 10/22/2009 | 10/22/2009 | P | PART |
Tom Arcoraci
|
|
|
MTI on site for reinforcing and concrete Phone #: ###-#### Internet Inspection Request from: Mike Shain
|
BLD-Foundation | 10/14/2009 | 10/15/2009 | 10/15/2009 | P | PART |
Tom Arcoraci
|
|
|
MTI to also inspect Phone #: ###-#### Internet Inspection Request from: Mike Shain wip ok
|
Plan assigned to (JCM) | 9/18/2009 | 9/18/2009 | 9/21/2009 | | PASS |
John Menard
|
|
|
9/21/2009 11:57:31 JCM - activity updated through activity BLDA022 from case BLD09-01611.
|
Routing - PLAN CHECK | 9/18/2009 | | 9/21/2009 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 9/21/2009 | | PASS |
John Menard
|
|
|
Pulled grading, site work, underground plumbing, basement foundation for the addition and demolition of main floor between grid lines A & Q out of orignal permit BLD09-00980.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2009 | | DONE |
John Menard
|
|
|
|
Inspection Record Card- Bld | | | 9/21/2009 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/21/2009 | | DONE |
Tisha Gallop
|
|
|
called Dave Maloney w/Kreizenbeck Constructors and told him permit is ready and fees
|
Permit Ready to Issue | | | 9/21/2009 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 9/21/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 9/18/2009 | 9/18/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2009 | | DONE |
Tisha Gallop
|
|
|
|