Second Notice | | 2/7/2010 | 2/1/2010 | | DONE |
|
|
|
|
First Notice | | 1/21/2010 | 1/28/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/11/2010 | | DONE |
|
|
|
|
BLD-Final | 1/4/2010 | 1/5/2010 | 1/5/2010 | A | PASS |
Dave Hannah
|
|
|
Evelyn after 9 am if possible Phone #: ###-#### ok for perm occ
|
FIRE-Final Inspection | 12/17/2009 | 12/17/2009 | 12/17/2009 | P | PASS |
Forrest France
|
|
|
Life safety completed acceptable, inspection passed.
|
Zoning Approval | 12/17/2009 | 12/17/2009 | 12/17/2009 | | PASS |
Cody Riddle
|
|
|
Handrails will be verified by building inspector.
|
Issue PAID IN FULL permit | | | 12/10/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/9/2009 | | DONE |
Barbara Stitt
|
|
|
Per Steve Webb an ESC permit and waiver are required but no Responsible Person is required for this project
|
Plan assigned to (DRS) | 9/29/2009 | 9/29/2009 | 12/8/2009 | | PASS |
Dan Stuart
|
|
|
12/8/2009 11:04:50 DRS - activity updated through activity BLDA022 from case BLD09-01623.
|
Routing - PLAN CHECK | 11/30/2009 | | 12/8/2009 | | PASS |
Dan Stuart
|
|
|
Attached engineering design calcs for handrails and installation instructions; attached spec sheets provided; modified permit wording and modified plan review. To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2009 | | PASS |
|
|
|
|
Print Occupancy Form | | | 12/8/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/8/2009 | | DONE |
Tisha Gallop
|
|
|
called Jay Parker and left vm permit is ready, fees, need GC, RCE, RP
|
Permit Ready to Issue | | | 12/8/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 12/7/2009 | | |
Dan Stuart
|
|
|
Rec'd one copy of calcs and two copies of sheet TI-1.0- taken to Dan
|
Routing - PLAN CHECK | 10/7/2009 | | 11/30/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals of 11/25/09 inserted into plans. Two items remain to be addressed that were part of plan review of 10/2/09. Copy of plan review e-mailed to architect Ron Moss.
|
Plan resubmittals requested | | | 11/30/2009 | | DONE |
|
|
|
Copy of plan review e-mailed to ronwmoss@gmail.com with copy to parkerportraits@msn.com.
|
Telephone call | | | 11/30/2009 | | DONE |
|
|
|
Called Ron Moss to see how I could get the plan review to him. Resubmittals required. Reviewed items concerning service sink and handrail connections at exterior ramp with him. He gave me his home e-mail address to send report to him.
|
Plan resubmittals received | | | 11/25/2009 | | |
Tisha Gallop
|
|
|
received two copies of response to comments, copy of Boise City Plan Reivew Report, specs for Tri-Temp Water Dispenser (1 pg.), specs for Swing Clear Full Mortise Template Hinges (1 pg.), letter from Congregation Ahavath Beth Israel addressed to Dan Stuart (2 pgs.), Elkay specs for wall mount water cooler (2 pgs.), plan sheets TI-1.0, TI-1.1; taken to Dan Stuart
|
Route to Impact Fee Review | 10/5/2009 | 10/8/2009 | 10/14/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees.
|
Routing - FIRE | 10/5/2009 | 10/5/2009 | 10/7/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 10/7/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Meeting | | | 10/6/2009 | | DONE |
|
|
|
SUMMARY OF MEETING CONCERNING PARKER PORTRAITS, 2620 Bannock Street, OCCUPANCY USE CHANGE, BLD09-01623.
10/6/09 - Meeting with Ron Moss, Evelyn Grimes, Jenifer Gilliland, Tim Woodard and me to discuss the plan review report and compliance requirements needed to be shown on plans.
1) Sec. 1008.1.1 - All doors or openings without doors shall provide 32" clear width.
2) The ramp construction, landing, handrails, edge protection & accessible route to meet current code.
3) New ramp that replaced original ramp was constructed without app., plans, permits or inspections. As a replacement of an existing ramp, the location should be in compliance with Sec. 1024.3, exit discharge location, requiring a 10 ft. separation from ramp to property line but it does not comply. Plans indicate 3 feet from the ramp to the property line. From the ramp to the existing west wall of the Greek Orthodox Church, based on scale of drawing at 1/8" per foot, scales as being approximately 4.33', a total of 7.33' from edge of ramp to existing building. Evelyn to provide modification request to Jason Blais, Building Official, requesting a modification per sec. 104.10, allowing the ramp to be located as shown on plans with less separation distance to the property than normally required.
3) To provide accessible wheelchair drinking fountain in corridor and a bubbler drinking fountain on the Break Room sink for standing persons for code compliance.
4) Doors 109 & 110 will probably be removed and the opening cased to provide required clear width & latch side clearances.
5) Restroom door #106 will be relocated to open in with the door against the north wall and the 18" latch side clearance from the door to the new lav OR a pocket door installed on the outside of the existing wall to meet door opening clear width and the existing door & frame removed as needed to provide the 32" clear width. If door swing is change to open to the wall, proposed use of surface mounted wall conduit strip molding to move the light switch from behind door. Door hardware on new doors 105 & 106 shall be lever style for accessibility.
5) Site plan with dimensions from building to property line from the surveyor is not required. We will use Evelyn's noted dimensions on site plan for evaluation of concerns for code requirements.
6) Evelyn will provide a signed letter from previous owners that they constructed new interior walls to create office 114 & reception 113.
7) Will provide handrails on stair to raised platform or remove the raised platform except for a 36" shelf, for storage, around the perimeter of the storage area, room 111, located north of the accordion doors OR alter stairs moving them into the platform to provide 11" clear handrail extension for one riser width so new handrails do not affect the existing accordion door location.
8) Breakroom sink is double compartment. One side will be designated as the service sink.
9) Stair landing and rise / run / rails for rear stair to comply with current code.
10) Evelyn to cut and paste dimensioned elevations for accessible water closet, grab bars and sink elevations for code compliance requirements for restroom fixtures onto her plans for use to clarify installation requirements to match her notes. Plan view data provide in enlarged restroom drawing do not show grab bars per code, clearances under accessible new lav or water closet height.
11) All doors required to be changed out to meet door clear width requirements of 32" shall have compliant accessible hardware and clearances when new doors are installed or doors & frames removed as necessary to provide the required clear width.
|
Plan resubmittals requested | | | 10/5/2009 | | DONE |
|
|
|
Sent e-mail copy of plan review to Ron Moss - ron@design4place.com; Evelyn Grime - evelyn@design4place.com and Jay Parker - parkerportraits@msn.com
|
Routing - PLAN CHECK | 10/1/2009 | | 10/5/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Plan review e-mailed to Ron Moss, Evelyn Grime and Jay Parker. Plan routed to fire code analyst for review.
|
Routing - Erosion and Sediment | 10/1/2009 | | 10/1/2009 | | PASS |
Steven Webb
|
|
|
ESC09-00607 plan waiver approved with attached conditions.
|
Routing - PLANNING | 10/1/2009 | | 10/1/2009 | | PASS |
Cody Riddle
|
|
|
|
Routing - PUBLIC WORKS | 9/30/2009 | | 10/1/2009 | | PASS |
Beverly Hall
|
|
|
New service sink & drinking fountains
|
Recd Pcfee & Taken To Pln CK | | | 9/30/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 9/30/2009 | | 9/30/2009 | | PASS |
April Wing
|
|
|
|
Plan resubmittals received | | | 9/30/2009 | | |
Tisha Gallop
|
|
|
received one copy of info on Pre-catalyzed Waterbased Epoxy and one copy of Topographic Survey plan sheet; taken to Dan Stuart
|
Routing PW Drainage | 9/30/2009 | | 9/30/2009 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Rating | 9/30/2009 | | 9/30/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 9/29/2009 | | PASS |
|
|
|
Accepted into the review process for routing.
|
Plans ACCEPTED BY PLAN TECH | | | 9/29/2009 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 9/21/2009 | | FAIL |
|
|
|
Submittals incomplete per checklist
|
Application received | | 9/21/2009 | | | |
|
|
|
|