Case Summary (BLD) | | | 8/27/2019 | | DONE |
|
|
|
|
Third Notice | | 2/7/2011 | 3/8/2011 | | DONE |
|
|
|
|
Third Notice | | 1/12/2011 | 1/24/2011 | | DONE |
|
|
|
faxed and e-mailed
|
Third Notice | | 11/29/2010 | 12/29/2010 | | DONE |
|
|
|
faxed
|
Second Notice | | 11/22/2010 | 11/24/2010 | | DONE |
|
|
|
|
First Notice | | 11/7/2010 | 11/12/2010 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 10/28/2010 | | |
|
|
|
|
Permanent Occupancy | | | 10/28/2010 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 10/1/2010 | 10/1/2010 | 10/1/2010 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/17/2010 | 8/17/2010 | 8/17/2010 | | PART |
Tom Arcoraci
|
|
|
|
BLD-Conference | 6/17/2010 | 6/17/2010 | 6/17/2010 | P | PASS |
Jim Storey
|
|
|
reviewed out standing signoffs w/ron ti had no action to be able to find out ele activty.
|
BLD-Conference | 5/10/2010 | 5/11/2010 | 5/12/2010 | A | PART |
Jim Storey
|
|
|
ele division had site walk through. bob and jack called and said they are still trying to get ul to respond back to there inquirys.
|
BLD-Conference | 5/7/2010 | 5/10/2010 | 5/10/2010 | A | PART |
Jim Storey
|
|
|
follow up w/doug and jack jack called ul as ask to do and has been refered to joe buttler he has not returned the call. Jack is trying to provide the direction that dairygold was not able to achive when they tried to get ul per the friday confrance jack and I where involved to resolve the equment listing isues.
|
BLD-Conference | 5/7/2010 | 5/7/2010 | 5/7/2010 | P | FAIL |
Jim Storey
|
|
|
jack is contacting ul for specfic equment listing requriments for specfic machinary as to clearify white book std.
|
BLD-Conference | 5/7/2010 | 5/7/2010 | 5/7/2010 | A | PART |
Jim Storey
|
|
|
reviewed ele requriments for c/n isued.
|
BLD-Final | 5/3/2010 | 5/3/2010 | 5/3/2010 | A | PART |
Jim Storey
|
|
|
temp ok
|
FIRE-Final Inspection | 4/26/2010 | 4/27/2010 | 4/27/2010 | A | PASS |
Forrest France
|
|
|
Fire life safety final inspection passed.
|
BLD-Final | 4/21/2010 | 4/23/2010 | 4/23/2010 | A | PART |
Jim Storey
|
|
|
fire stop wall penatrations/ missing smoke seal/ encloce foam above ceilling/ door closer
|
BLD-Conference | 4/19/2010 | 4/20/2010 | 4/21/2010 | A | CANC |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 4/14/2010 | 4/19/2010 | 4/19/2010 | P | PART |
Forrest France
|
|
|
EM lighting and exit signs tested satisfactory, reviewed project related FIR permits and discussed items necessary for final.
|
FIRE-Conference | 4/6/2010 | 4/6/2010 | 4/7/2010 | P | DONE |
Forrest France
|
|
|
Discussion with electrical contractor regarding fire alarm permit work for sprinkler monitoring and equipment at the new chemical storage room.
|
BLD-Final | 3/9/2010 | 3/9/2010 | 3/9/2010 | P | PART |
Jim Storey
|
|
|
offices and restrooms ok for use.
|
BLD-Framing/Rough-in | 2/10/2010 | 2/10/2010 | 2/10/2010 | P | PART |
Jim Storey
|
|
|
framing of control rm 1 hr lid behind restroom gyp ok on top of assembly as well as ledger attchment. will reinsp. for gyp on bottom side.
|
BLD-Conference | 2/3/2010 | 2/4/2010 | 2/4/2010 | P | PASS |
Jim Storey
|
|
|
bathroom and office framing insp.
|
BLD-Wall cover | 1/25/2010 | 1/25/2010 | 1/25/2010 | A | PASS |
Jim Storey
|
|
|
cmu 1 st lift at restaroom/ storage area.
|
BLD-Framing/Rough-in | 1/21/2010 | 1/21/2010 | 1/21/2010 | A | PASS |
Jim Storey
|
|
|
added for time
|
BLD-Framing/Rough-in | 1/20/2010 | 1/21/2010 | 1/21/2010 | A | PASS |
Jim Storey
|
|
|
exterior ceillings framing and insulation ok to cover.4 locations.
|
Issue PAID IN FULL permit | | | 11/13/2009 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 11/12/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/12/2009 | | DONE |
|
|
|
|
Telephone call | | | 11/12/2009 | | DONE |
Barbara Stitt
|
|
|
Called Mike with Van Auker Construction and told him that permit is ready & fees due///11-12-09 @ 4:07pm BAS
|
Routing - PLAN CHECK | 11/2/2009 | | 11/10/2009 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2009 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 10/6/2009 | | 11/10/2009 | | PASS |
John Menard
|
|
|
11/10/2009 14:00:47 JCM - activity updated through activity BLDA022 from case BLD09-01727.
|
Plan resubmittals received | | | 11/9/2009 | | |
John Menard
|
|
|
Rec'd response letter, and two copies of sheets- 0; A-.01; A-1.2; A-3; A-5; A-6; A-6.2; A-8; M2.1; E2.2; E2.4- Insterted by arch rep- taken back to John M
|
Plan resubmittals requested | | | 11/5/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - FIRE | 10/29/2009 | 10/29/2009 | 11/2/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 11/2/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 10/29/2009 | 11/3/2009 | 10/30/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Plan resubmittals requested | | | 10/29/2009 | | DONE |
John Menard
|
|
|
Emailed the architect a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 10/13/2009 | | 10/29/2009 | | FAIL |
John Menard
|
|
|
|
Routing - Design Review | 10/12/2009 | | 10/13/2009 | | PASS |
Andrea Tuning
|
|
|
This building permit is for interior tenant improvements only. The site plan, landscape plan and elevations were previously approved with the shell and core permit. Andrea Tuning - DRH09-00147
|
Routing - PLUMBING | 10/8/2009 | | 10/12/2009 | | PASS |
Bill VanDegrift
|
|
|
verify cross connection control. per plans and 2003 upc
|
Routing - PUBLIC WORKS | 10/6/2009 | | 10/8/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Environmental | 10/7/2009 | | 10/8/2009 | | PASS |
Walt Baumgartner
|
|
|
West Boise Sewer Dist. Reviewed. Facility operates under Indirect Discharge Permit, subject to pretreatment regulations.
|
Routing PW Solid Waste | 10/7/2009 | | 10/7/2009 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - Addressing | 10/7/2009 | | 10/7/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 10/5/2009 | | 10/6/2009 | | DONE |
Jason Blais
|
|
|
|
Application received | | 10/5/2009 | 10/5/2009 | | DONE |
|
|
|
|
Intake Approval | | | 10/5/2009 | | PASS |
|
|
|
Approved to take into the review system.
|
Plans ACCEPTED BY PLAN TECH | | | 10/5/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/5/2009 | | DONE |
Tisha Gallop
|
|
|
|