Agreement of Future work | 12/15/2009 | 11/11/2012 | 10/17/2012 | | DONE |
Dan Stuart
|
|
|
#1 - By 11/11/2011 the scope of weork is to be completed - completeing the installation of FSK facing over existing insulation paper face or the owner David Thompson will be required to post a bond based on the remaining areas to be completed.
#2 All work to be completed by 11/11/2012 - Installation of FSK
2/23/12 Bond posted under case BND12-00006 for extra time on Upgrade Agreement.
10/17/12 All upgrade agreement work completed under BLD12-01006. Copy of Notice of Compliance attached to that permit and to this case.
|
Plan Reviewer's activity | | | 11/18/2011 | | DONE |
Jason Blais
|
|
|
Emailed architect for a status report and action to be taken. Two years is up on the agreement. If all work is not completed, a bond was supposed to be posted to add a third year to the agreement.
|
Third Notice | | 11/15/2010 | 5/16/2011 | | DONE |
|
|
|
|
Third Notice | | 5/15/2010 | 5/16/2011 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/29/2011 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 4/22/2010 | 5/10/2010 | | DONE |
|
|
|
|
First Notice | 4/1/2010 | 4/1/2010 | 4/12/2010 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 3/31/2010 | 4/1/2010 | 4/1/2010 | A | PASS |
Jim Sly
|
|
|
bill Phone #: ###-#### C/C issued
|
DOC - Permit Finaled | 4/1/2010 | 4/1/2010 | 4/1/2010 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 11/20/2009 | 11/23/2009 | 11/23/2009 | A | PART |
Jim Sly
|
|
|
Bill phone ###-#### Wall complete except for approx 10 sq inch hole located at area above front awning. Repair and call for inspection. Architect notified.
|
BLD-Final | 11/19/2009 | 11/20/2009 | 11/20/2009 | A | CANC |
Jim Sly
|
|
|
bill Phone #: ###-#### Re-sched.....
|
FIRE-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 11/19/2009 | 11/19/2009 | 11/19/2009 | P | CANC |
Jim Sly
|
|
|
Bill ###-####
|
BLD-Final | 11/18/2009 | 11/18/2009 | 11/18/2009 | P | NR |
Jim Sly
|
|
|
bill Phone #: ###-#### Need fire final
|
BLD-Conference | 10/28/2009 | 10/29/2009 | 10/29/2009 | A | PASS |
Jim Sly
|
|
|
Inspected 2hr wall (inside Bldg) and wrapped columns..........appears OK as per approved plan. Some areas of 2hr wall located above front canopy not continuous. Showed areas of concern to Architect. Need to re-inspect after corrected.
|
BLD-Other | 10/28/2009 | 10/29/2009 | 10/28/2009 | A | CANC |
Jim Sly
|
|
|
bill - fire barrier wall Phone #: ###-####
|
BLD-Framing/Rough-in | 10/27/2009 | 10/28/2009 | 10/28/2009 | A | FAIL |
Jim Sly
|
|
|
Bill Phone #: ###-#### C/N ....Remove enough sheetrock for inspection to verify amount of layers, lapping and attachment at 2hr. wall and columns.
|
Plan assigned to (DRS) | 10/19/2009 | | 10/27/2009 | | PASS |
Dan Stuart
|
|
|
10/27/2009 11:07:10 DRS - activity updated through activity BLDA022 from case BLD09-01840.
|
Routing - PLAN CHECK | 10/22/2009 | | 10/27/2009 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue. Copy of alternate & upgrade document attached to plans and attched to BLD09-01840 for tracking time frame & compliance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2009 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/27/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/27/2009 | | DONE |
|
|
|
|
Telephone call | | | 10/27/2009 | | DONE |
Tisha Gallop
|
|
|
spoke with Bill Matter and told him permit is ready and fees
|
Issue PAID IN FULL permit | | | 10/27/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 10/21/2009 | | 10/22/2009 | | PASS |
Scott Arellano
|
|
|
No fire code review comments attached. A seperate fire sprinkler permit is required for required fire sprinkler system modifications.
|
1st review completed | | | 10/22/2009 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/19/2009 | | 10/21/2009 | | PEND |
Dan Stuart
|
|
|
Pending approval of the proposed Alternate and the Upgrade Agreement. Routing to fire code analyst.
|
Pending Assignment by JCB | 10/19/2009 | | 10/19/2009 | | DONE |
Jason Blais
|
|
|
|
Application received | | 10/16/2009 | 10/16/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/16/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/16/2009 | | DONE |
Tisha Gallop
|
|
|
|