BLD-Final | 11/25/2009 | 11/27/2009 | 11/27/2009 | A | PASS |
Jim Sly
|
|
|
Shawn Phone #: ###-#### c/c issued
|
DOC - Permit Finaled | 11/27/2009 | 11/21/2009 | 11/27/2009 | P | PASS |
Jim Sly
|
|
|
|
BLD-Footing | 11/3/2009 | 11/4/2009 | 11/4/2009 | A | PART |
Jim Sly
|
|
|
Shawn Phone #: ###-#### Footing depth and width OK No string line pulled. Unable to determine East side setback. Contractor notified.
|
Routing Walk-In (BLD) | 11/3/2009 | 11/3/2009 | 11/3/2009 | P | DONE |
Perry Paine
|
|
|
11/3/2009 16:49:28 PEP - activity updated through activity BLDA022 from case BLD09-01901.
|
Case Summary (BLD) | | | 11/3/2009 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/3/2009 | | DONE |
|
|
|
|
1st review completed | | | 11/3/2009 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/3/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/3/2009 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 10/26/2009 | 10/26/2009 | 10/26/2009 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 10/26/2009 | 10/26/2009 | 10/26/2009 | P | FAIL |
Perry Paine
|
|
|
need engineering for a pole structure.
|
Application received | | 10/26/2009 | | | |
|
|
|
|