Plan Reviewer's activity | | | 6/21/2010 | | DONE |
|
|
|
Drawings took to Records with BLD09-01944.
|
Third Notice | | 3/29/2010 | 3/16/2010 | | DONE |
|
|
|
|
Third Notice | | 3/9/2010 | 3/15/2010 | | DONE |
|
|
|
faxed and called
|
Telephone call | | | 3/15/2010 | | DONE |
Tisha Gallop
|
|
|
spoke to John Lodman and he said will fill out FV and get it back to me.
|
First Notice | 2/19/2010 | 2/19/2010 | 2/23/2010 | | DONE |
Dave Hannah
|
|
|
faxed//changed next notice to third to match Bld09-01977 which is connected to this project.//leg
|
BLD-Final | 2/19/2010 | 2/19/2010 | 2/19/2010 | P | PASS |
Dave Hannah
|
|
|
Matt@P&Z approved by telecon as no exterior changes were made. No mechanical work completed under this permit. call with any questions. thank you. Inspection requested from web by: John Lodman Phone #: ###-#### This T I will need to be finished under a new bld
|
DOC - Permit Finaled | 2/19/2010 | 2/19/2010 | 2/19/2010 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 2/18/2010 | 2/19/2010 | 2/19/2010 | A | PASS |
Forrest France
|
|
|
Fire life safety for the vanilla shell approved.
|
FIRE-Final Inspection | 2/18/2010 | 2/18/2010 | 2/18/2010 | A | PASS |
Forrest France
|
|
|
C/N items completed.
|
FIRE-Final Inspection | 2/5/2010 | 2/8/2010 | 2/8/2010 | A | FAIL |
Forrest France
|
|
|
Noted two existing uprights blocked by adjacent plumbing drain pipe at the front east side of the tenant space. Remainder of vanilla permit work is satisfactory, final pending corrections for fire sprinkler coverage.
|
Plan assigned to (CJW) | 11/4/2009 | | 12/11/2009 | | PASS |
Carl Westfall
|
|
|
12/11/2009 09:22:59 CJW - activity updated through activity BLDA022 from case BLD09-01977.
|
Routing - PLAN CHECK | 12/10/2009 | | 12/11/2009 | | DONE |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2009 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/11/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/11/2009 | | DONE |
|
|
|
LM for John at ###-#### permit ready fees given
|
Permit Ready to Issue | | | 12/11/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/11/2009 | | DONE |
|
|
|
|
Routing - FIRE | 12/8/2009 | | 12/10/2009 | | PASS |
Scott Arellano
|
|
|
Went back to Fire since this project is on the same drawings as another project.
|
Routing - PLAN CHECK | 11/25/2009 | | 12/8/2009 | | PASS |
Carl Westfall
|
|
|
Drawings approved.
|
Route to Impact Fee Review | 11/23/2009 | 11/27/2009 | 11/30/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - FIRE | 11/23/2009 | 11/23/2009 | 11/25/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 11/25/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 11/16/2009 | | 11/23/2009 | | FAIL |
Carl Westfall
|
|
|
Plan review report could not be finished until the excessive length of the common path of egress travel is resolved.
|
Routing - Design Review | 11/9/2009 | | 11/16/2009 | | PASS |
Matthew A Halitsky
|
|
|
Matt Halitsky - DRH09-00260
|
Routing - PUBLIC WORKS | 11/4/2009 | | 11/9/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 11/6/2009 | | 11/6/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 11/5/2009 | | 11/5/2009 | | PASS |
April Wing
|
|
|
|
Intake Approval | | | 11/4/2009 | | PASS |
Jason Blais
|
|
|
|
Pending Assignment by JCB | 11/4/2009 | | 11/4/2009 | | DONE |
Jason Blais
|
|
|
|
Application received | | 11/4/2009 | | | |
|
|
|
|