Permit Information
Permit NumberBLD09-02001
StatusFinaled
Name DAVE WALLEN
Site Address 12598 W FAIRVIEW AVE Unit: 103
Project NameClare Zengoe
Customer Number 
ePlanReviewNo
Description
(Clare Zengoe) For tenant improvements to 1,798 sq. ft. tenant space within a 6,758 Building. Work to include the construction of new interior non-bearing partition walls to create new office spaces, exam rooms and lab areas for an eyewear facility. No new lighting will be installed only existing lighting will be repositions to accommodate the new office areas. Two new exam room sinks with associated plumbing will be installed. All work to be done per the approved plans, plan review report and any notations. CDM 1-26-10 FINAL CERT OF VALUE PER GC $25,700.00 ///DLD
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 12/25/20091/28/2010 DONE
BLD-Final12/14/200912/15/200912/15/2009APASS
DetailsJim Sly
Dave Phone #: ###-####
OK for Perm Occ.
Permanent Occupancy UNPAID FEE  12/15/2009 DONE
FIRE-Final Inspection12/11/200912/14/200912/14/2009APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection12/7/200912/8/200912/8/2009AFAIL
DetailsTroy Cobbley
Provide a tagged fire extinguisher as discussed. All other items wil be ok.
BLD-Framing/Rough-in11/17/200911/17/200911/17/2009PPASS
DetailsJim Sly
DAVE Phone #: ###-####
Print Occupancy Form  11/16/2009 DONE
Permit Ready to Issue  11/16/2009 DONE
Telephone call  11/16/2009 DONE
DetailsBarbara Stitt
Called Janice and told her that permit is ready & fees due///11-16-09 @ 11:10am BAS
Issue PAID IN FULL permit  11/16/2009 DONE
DetailsTisha Gallop
Plan assigned to (CDM)11/9/200911/9/200911/14/2009 PASS
DetailsCarl D Madsen
11/14/2009 13:06:25 CDM - activity updated through activity BLDA022 from case BLD09-02001.
Routing - FIRE  11/14/2009 PASS
DetailsCarl D Madsen
Verify in field CDM
1st review completed  11/14/2009 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/14/2009  
Case Summary (BLD)  11/14/2009 DONE
Routing - PLAN CHECK11/9/2009 11/14/2009 PASS
DetailsCarl D Madsen
Routing PW Sewer Rating11/10/2009 11/10/2009 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS11/9/2009 11/10/2009 PASS
DetailsConnie Baumgartner
Plans ACCEPTED BY PLAN TECH  11/9/2009 DONE
ok per Carl Madson for level 1 intake
Routing - Addressing11/9/2009 11/9/2009 PASS
DetailsApril Wing
Application received 11/9/2009