Third Notice | | 3/15/2010 | 3/10/2010 | | DONE |
|
|
|
|
Second Notice | | 2/28/2010 | 3/10/2010 | | DONE |
|
|
|
|
First Notice | 2/1/2010 | 2/1/2010 | 2/18/2010 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 2/1/2010 | 2/1/2010 | 2/1/2010 | P | PASS |
Jim Sly
|
|
|
ceiling grid inspection//call when on way please//Tim Phone #: ###-#### FINAL OK C/C issued.
|
DOC - Permit Finaled | 2/1/2010 | 2/1/2010 | 2/1/2010 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 1/28/2010 | 1/29/2010 | 1/29/2010 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 1/7/2010 | 1/8/2010 | 1/8/2010 | A | PASS |
Jim Sly
|
|
|
ceiling grid inspection please-Tim-please call prior to inspection Phone #: ###-####
|
BLD-Framing/Rough-in | 12/7/2009 | 12/8/2009 | 12/8/2009 | A | PASS |
Jim Sly
|
|
|
Tim Phone #: ###-####
|
BLD-Energy code compliance | 12/7/2009 | 12/8/2009 | 12/8/2009 | A | PASS |
Jim Sly
|
|
|
Tim Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/1/2009 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/17/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/17/2009 | | DONE |
|
|
|
|
Telephone call | | | 11/17/2009 | | DONE |
|
|
|
called Connie permit ready and fee given
|
Plan assigned to (CDM) | 11/9/2009 | 11/9/2009 | 11/16/2009 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 11/9/2009 | | 11/16/2009 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | | | 11/16/2009 | | PASS |
Carl D Madsen
|
|
|
Verify in field CDM
|
1st review completed | | | 11/16/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/16/2009 | | DONE |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2009 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/9/2009 | | DONE |
|
|
|
|
Application received | | 11/9/2009 | | | |
|
|
|
|