Third Notice | | 3/15/2010 | 3/10/2010 | | DONE |
|
|
|
|
Second Notice | | 2/28/2010 | 3/10/2010 | | DONE |
|
|
|
|
First Notice | | 1/31/2010 | 2/18/2010 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 1/21/2010 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 1/19/2010 | 1/20/2010 | 1/20/2010 | P | PASS |
Dave Hannah
|
|
|
Tim please call 30 min before going out Phone #: ###-#### ok for perm occ
|
FIRE-Final Inspection | 1/12/2010 | 1/13/2010 | 1/13/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 1/11/2010 | 1/11/2010 | 1/11/2010 | P | FAIL |
Forrest France
|
|
|
Correction items include post suite address, provide lock status indicator at the main entry/exit door, post fire extinguisher on the wall at location as discussed, project related fire sprinkler permit final pending work at electrical room.
|
BLD-Framing/Rough-in | 1/6/2010 | 1/7/2010 | 1/7/2010 | P | PASS |
Dave Hannah
|
|
|
Ceiling grid inspection please-Tim Phone #: ###-####
|
BLD-Framing/Rough-in | 12/2/2009 | 12/3/2009 | 12/3/2009 | A | PASS |
Dave Hannah
|
|
|
Tim-Please call prior to inspection-also an energy code inspection please Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/25/2009 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 11/9/2009 | 11/9/2009 | 11/24/2009 | | PASS |
Carl D Madsen
|
|
|
11/24/2009 16:45:18 CDM - activity updated through activity BLDA022 from case BLD09-02008.
|
Routing - PLAN CHECK | 11/9/2009 | | 11/24/2009 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | | | 11/24/2009 | | PASS |
|
|
|
Verify in field CDM
|
1st review completed | | | 11/24/2009 | | DONE |
|
|
|
|
Routing PW Sewer Rating | 11/24/2009 | | 11/24/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 11/24/2009 | | 11/24/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 11/24/2009 | | 11/24/2009 | | PASS |
April Wing
|
|
|
|
Case Summary (BLD) | | | 11/24/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2009 | | |
|
|
|
|
Print Occupancy Form | | | 11/24/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2009 | | |
|
|
|
|
Telephone call | | | 11/24/2009 | | DONE |
|
|
|
Called left message for Connie permit ready and fee given
|
Application received | | 11/9/2009 | | | |
|
|
|
|