Second Notice | | 8/22/2010 | 8/26/2010 | | DONE |
|
|
|
|
First Notice | 8/3/2010 | 8/3/2010 | 8/12/2010 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 8/2/2010 | 8/2/2010 | 8/3/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety passed.
|
BLD-Final | 8/2/2010 | 8/3/2010 | 8/3/2010 | A | PASS |
Jim Storey
|
|
|
jerry ###-####
|
DOC - Permit Finaled | 8/3/2010 | 8/3/2010 | 8/3/2010 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 7/13/2010 | 7/13/2010 | 7/16/2010 | | DEFR |
Jim Storey
|
|
|
Mike Phone #: ###-#### need fire life saftey sign off.
|
BLD-Final | 5/12/2010 | 5/13/2010 | 5/13/2010 | A | FAIL |
Jim Storey
|
|
|
Mike Phone #: ###-#### need fire life saftey sign off.
|
FIRE-Conference | 4/12/2010 | 4/12/2010 | 4/12/2010 | A | DONE |
Forrest France
|
|
|
Discussion with contractor regarding items needed for final including completion for project related FIR permit (FDC relocation) etc.
|
BLD-Final | 2/24/2010 | 2/25/2010 | 2/25/2010 | A | PART |
Jim Storey
|
|
|
Nate-9:00 Phone #: ###-####--Please check on electrical and mechanical permits and Fire sign off final ok pending fire and letter from arch. on flush bolts.
|
BLD-Framing/Rough-in | 12/9/2009 | 12/10/2009 | 12/10/2009 | P | PASS |
Jim Storey
|
|
|
Brian Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/25/2009 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 11/23/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/23/2009 | | DONE |
|
|
|
|
Telephone call | | | 11/23/2009 | | DONE |
|
|
|
Called Pete Rockwell permit ready and fee given Also need GC & #
|
Plan assigned to (CDM) | 11/12/2009 | 11/10/2009 | 11/20/2009 | | PASS |
Carl D Madsen
|
|
|
11/20/2009 09:07:16 CDM - activity updated through activity BLDA022 from case BLD09-02027.
|
Routing - PLAN CHECK | 11/12/2009 | | 11/20/2009 | | FAIL |
Carl D Madsen
|
|
|
Additional infoemation is required on dust production, magnetic locks at vestibule doors and sliding doors at the sifting room. 11-18-09 CDM. Plan reciew report sent to Glancey Rockwell Architects on 11-18-09 CDM
|
Routing - PLAN CHECK | 11/20/2009 | | 11/20/2009 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 11/20/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2009 | | |
|
|
|
|
Routing - FIRE | | | 11/17/2009 | | PASS |
|
|
|
Verify in field CDM
|
1st review completed | | | 11/17/2009 | | FAIL |
|
|
|
Sliding doors cannot be part of the egress system 11-17-09 CDM
|
Application received | | 11/10/2009 | 11/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/10/2009 | | DONE |
Tisha Gallop
|
|
|
|