| Second Notice | | 10/7/2010 | 10/4/2010 | | DONE |
|
|
|
|
| First Notice | | 9/17/2010 | 9/27/2010 | | DONE |
|
|
|
|
| PubWorks Occupancy Approval | 9/7/2010 | 9/7/2010 | 9/7/2010 | | DONE |
Tiffany Lowery
|
|
|
|
| Permanent Occupancy | | | 9/7/2010 | | DONE |
|
|
|
|
| BLD-Final | 8/31/2010 | 9/1/2010 | 9/1/2010 | A | PASS |
Tom Arcoraci
|
|
|
Travis Phone #: ###-####
|
| FIRE-Final Inspection | 8/31/2010 | 8/31/2010 | 9/1/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
| BLD-Final | 8/26/2010 | 8/26/2010 | 8/26/2010 | P | PART |
Tom Arcoraci
|
|
|
travis Phone #: ###-#### ok after fire sign off
|
| FIRE-Final Inspection | 8/26/2010 | 8/26/2010 | 8/26/2010 | P | FAIL |
Troy Cobbley
|
|
|
An outside supply duct has been added to the unit. This new duct is connected to the hvac unit before the duct detector which would delute any smoke from within the compartment. This new ducting needs to be connected to the hvac unit after the duct smoke detector. No testing was performed.
|
| FIRE-Final Inspection | 8/24/2010 | 8/24/2010 | 8/25/2010 | P | FAIL |
Troy Cobbley
|
|
|
The west hvac unit tested ok. The east hvac unit would not go into heat mode like it did the day before so that it could be tested.
|
| BLD-Final | 8/24/2010 | 8/24/2010 | 8/24/2010 | P | NR |
Tom Arcoraci
|
|
|
Kent Phone #: ###-####
|
| FIRE-Final Inspection | 8/20/2010 | 8/23/2010 | 8/23/2010 | A | FAIL |
Troy Cobbley
|
|
|
The east side duct smoke detector did not shut down the hvac unit immediately when tested. The west side hvac unit would not turn on for the testing.
|
| BLD-Final | 8/20/2010 | 8/23/2010 | 8/23/2010 | A | NR |
Tom Arcoraci
|
|
|
travis Phone #: ###-####
|
| BLD-Final | 7/23/2010 | 7/26/2010 | 7/26/2010 | P | PART |
Tom Arcoraci
|
|
|
James Phone #: ###-#### needs fire sign off
|
| FIRE-Final Inspection | 7/23/2010 | 7/26/2010 | 7/26/2010 | A | FAIL |
Troy Cobbley
|
|
|
Upon review of the city approved plans there are two duct smoke detectors shown on the Mechanical sheets and they are installed as well. These two detectors will be required to be tested with the required remote annunciators or have engineer approval to delete since the drawings show the units at only 1700 cfm. All other items are ok.
|
| FIRE-Final Inspection | 7/22/2010 | 7/22/2010 | 7/22/2010 | P | FAIL |
Troy Cobbley
|
|
|
Provide city approved plans, provide address and fire extinguisher as discussed.
|
| BLD-Final | 7/21/2010 | 7/22/2010 | 7/22/2010 | A | NR |
Tom Arcoraci
|
|
|
call 30 min prior to meet//Travis Shelton Phone #: ###-####
|
| Zoning Approval | 7/22/2010 | 7/22/2010 | 7/22/2010 | | DONE |
Cody Riddle
|
|
|
|
| Print Occupancy Form | | | 7/22/2010 | | |
|
|
|
|
| BLD-Aging Inspection | 6/22/2010 | 6/22/2010 | 6/22/2010 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Framing/Rough-in | 4/21/2010 | 4/22/2010 | 4/22/2010 | P | PART |
Tom Arcoraci
|
|
|
shane Phone #: ###-#### check truss buckets for girder at next inspection
|
| BLD-Foundation | 3/18/2010 | 3/19/2010 | 3/19/2010 | A | PASS |
Tom Arcoraci
|
|
|
Re-enforcing-rebar inspection Phone #: ###-#### strata on site
|
| BLD-Footing | 3/18/2010 | 3/18/2010 | 3/18/2010 | P | PASS |
Tom Arcoraci
|
|
|
Re-enforcing-rebar inspection Phone #: ###-#### strata on site
|
| Plan assigned to (JCM) | 11/12/2009 | | 1/20/2010 | | PASS |
John Menard
|
|
|
1/20/2010 08:49:31 JCM - activity updated through activity BLDA022 from case BLD09-02032.
|
| Routing - PLANNING Land Div | 1/20/2010 | | 1/20/2010 | | PASS |
Dave Abo
|
|
|
Parcels have been combined into one. New Tax Parcel Number is R5128000175.
|
| Routing - PLAN CHECK | 1/20/2010 | | 1/20/2010 | | PASS |
John Menard
|
|
|
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2010 | | DONE |
John Menard
|
|
|
|
| Print Occupancy Form | | | 1/20/2010 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 1/20/2010 | | DONE |
|
|
|
|
| Issue PAID IN FULL permit | | | 1/20/2010 | | DONE |
|
|
|
|
| Plan resubmittals received | | | 1/11/2010 | | |
John Menard
|
|
|
rec'd notice of buildable parcel for combining lots/parcel; taken to John M
|
| Routing PW Environmental | 12/18/2009 | | 12/18/2009 | | PASS |
Walt Baumgartner
|
|
|
Approved - resubmittal sheets show secondary containment around sodium hypochlorite tank
|
| Plan resubmittals received | | | 12/18/2009 | | DONE |
|
|
|
received transmittal letter and 2 sheets of P-102 - taken to john menard
|
| Routing - PUBLIC WORKS | 12/18/2009 | | 12/18/2009 | | PASS |
Beverly Hall
|
|
|
|
| Routing PW Drainage | 12/10/2009 | | 12/17/2009 | | PASS |
Brian Murphy
|
|
|
|
| Plan resubmittals received | | | 12/16/2009 | | |
Tisha Gallop
|
|
|
received transmittal, response letter, plan check corrections, ES Report about Skylights, two copies of sheets A1, A1.1, C-102; inserted by arch. rep. and taken back to Brian Murphy
|
| Plan resubmittals received | | | 12/15/2009 | | |
Tisha Gallop
|
|
|
received one copy of response letter and structural calculations, three copies of plan sheets C-502, A4; inserted by eng. rep.and taken back to Public Works.
|
| Routing - PLAN CHECK | 12/2/2009 | | 12/10/2009 | | |
John Menard
|
|
|
|
| Plan resubmittals received | | | 12/9/2009 | | |
Tisha Gallop
|
|
|
received two copies of transmittal, O & M Manual, Drainage calcs, plan sheets C-101, C-102, C-501; inserted by eng. rep. and taken back to John Menard
|
| Routing - FIRE | 11/25/2009 | 11/25/2009 | 12/2/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
| 1st review completed | | | 12/2/2009 | | FAIL |
|
|
|
Failed Public Works, Structural, Plumbing, Planning, Plan Check
|
| Route to Impact Fee Review | 11/25/2009 | 12/1/2009 | 11/27/2009 | | PASS |
Cindy M. Gould
|
|
|
|
| Plan resubmittals requested | | | 11/25/2009 | | DONE |
John Menard
|
|
|
E-mailed architect a copy of the plan review requesting revisions. JCM
|
| Routing - PLAN CHECK | 11/24/2009 | | 11/25/2009 | | FAIL |
John Menard
|
|
|
|
| Routing - PLANNING | 11/23/2009 | | 11/24/2009 | | PASS |
Joshua Johnson
|
|
|
|
| Routing - PLUMBING | 11/23/2009 | | 11/23/2009 | | PASS |
Bill VanDegrift
|
|
|
no plumbing
|
| Routing Off Site - STRUCTURAL | 11/12/2009 | | 11/23/2009 | | FAIL |
John Menard
|
|
|
called Action Couriers for pick up - Received comment list from consulting structural engineer requesting revisions. JCM
|
| Routing - Erosion and Sediment | | | 11/23/2009 | | PASS |
Steven Webb
|
|
|
ESC plan is approved along with the permit attached conditions. Certified RP required prior to start of work. Inform Boise City with the name of RP at ###-####. ESC09-00724
|
| Plan resubmittals requested | | | 11/23/2009 | | DONE |
John Menard
|
|
|
E-mailed the engineer a copy of the structural comments requesting revisions. JCM
|
| Routing - PUBLIC WORKS | 11/12/2009 | | 11/20/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
| Routing PW Drainage | 11/16/2009 | | 11/20/2009 | | FAIL |
Brian Murphy
|
|
|
O and M incomplete. BRIAN MURPHY ###-####
|
| Routing - Addressing | 11/16/2009 | | 11/16/2009 | | PASS |
April Wing
|
|
|
|
| Routing - PLANNING Land Div | 11/12/2009 | | 11/12/2009 | | FAIL |
Dave Abo
|
|
|
Applicant owns two parcels. Marty Santoya stated that the existing building would be torn down and a new structure would be buillt to replace it. The new building is one foot from the property line. Prior to issuing building permit, the two parcels must be combined. Called Nathaniel Runyan, JUB on 11/12/09
|
| Plans ACCEPTED BY PLAN TECH | | | 11/12/2009 | | DONE |
|
|
|
Ok per John M for new construction
|
| Pending Assignment by JCM | 11/12/2009 | | 11/12/2009 | | BLDA |
John Menard
|
|
|
11/12/2009 11:57:43 JCM - activity updated through activity BLDA166 from case BLD09-02032.
|
| Application received | | 11/12/2009 | | | |
|
|
|
|
| Routing - PUBLIC WORKS | 12/10/2009 | | | | FAIL |
Beverly Hall
|
|
|
See Environmental notes.
|
| Routing PW Environmental | 12/17/2009 | | | | FAIL |
Walt Baumgartner
|
|
|
Must resubmit plan showing wall around hypochloride tank. Called JUB 12/17/09.
|
| Routing - PLAN CHECK | 12/18/2009 | | | | |
John Menard
|
|
|
|