BLD-Final | 6/1/2011 | 6/1/2011 | 6/1/2011 | P | DONE |
Tony Young
|
|
|
|
DOC - Permit Finaled | 6/1/2011 | 6/1/2011 | 6/1/2011 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Final | 5/6/2011 | 5/9/2011 | 5/9/2011 | A | PASS |
Tony Young
|
|
|
Keith Phone #: ###-####
|
FIRE-Final Inspection | 5/5/2011 | 5/6/2011 | 5/6/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 4/29/2011 | 5/2/2011 | 5/4/2011 | P | NR |
Tony Young
|
|
|
Keith Phone #: ###-####,, will need fire/lifesafety,, electrical
|
BLD-Final | 4/29/2011 | 5/2/2011 | 5/2/2011 | A | NR |
Tony Young
|
|
|
Keith; Phone #: ###-####
|
FIRE-Final Inspection | 4/29/2011 | 5/2/2011 | 5/2/2011 | A | FAIL |
Troy Cobbley
|
|
|
Provide the additional fire extinguisher as discussed and provide the single action hardware on the new doors as discussed.
|
BLD-Final | 4/28/2011 | 4/29/2011 | 4/29/2011 | A | PART |
Tony Young
|
|
|
keith Phone #: ###-####,, walk through only,, need fire and life safety
|
BLD-Foundation | 4/22/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Tony Young
|
|
|
keith Phone #: ###-####,, rear main door area ok
|
BLD-Foundation | 4/8/2011 | 4/8/2011 | 4/15/2011 | P | PASS |
Tony Young
|
|
|
keith Phone #: ###-####
|
BLD-Footing | 4/12/2011 | 4/14/2011 | 4/14/2011 | A | PASS |
Tony Young
|
|
|
keith Phone #: ###-####,, ok to pour remainder of the footing under the existing storage building
|
BLD-Footing | 4/13/2011 | 4/13/2011 | 4/14/2011 | P | PASS |
Tony Young
|
|
|
keith Phone #: ###-####
|
BLD-Footing | 4/7/2011 | 4/8/2011 | 4/8/2011 | A | PART |
Tony Young
|
|
|
keith Phone #: ###-####,, north and west ftg ok
|
BLD-Conference | 4/6/2011 | 4/6/2011 | 4/7/2011 | P | PART |
Tony Young
|
|
|
keith Phone #: ###-####,, ok to use existing for small part on south side,, tie into with rebar
|
BLD-Footing | 4/5/2011 | 4/6/2011 | 4/6/2011 | A | PART |
Tony Young
|
|
|
keith Phone #: ###-####,, work in progress
|
BLD-Aging Inspection | 2/28/2011 | 2/28/2011 | 3/3/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/27/2010 | 12/27/2010 | 1/4/2011 | | PASS |
Tony Young
|
|
|
|
BLD-Wall cover | 10/25/2010 | 10/26/2010 | 10/26/2010 | A | PASS |
Tony Young
|
|
|
fire wall framing//Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 10/22/2010 | 10/25/2010 | 10/25/2010 | A | PART |
Tony Young
|
|
|
fire wall framing//Keith Phone #: ###-####,, 1st layer ok
|
BLD-Conference | 10/20/2010 | 10/20/2010 | 10/20/2010 | P | PART |
Tony Young
|
|
|
keith Phone #: ###-####,, general ?s,, firewall,, foundation,, etc..
|
Telephone call | | | 10/20/2010 | | DONE |
|
|
|
Call from inspector Tony Young. South wall indicates on plans as being masonry has a portion that is frame with waht appears to be stucco on the outside and Oriented Stand Board on the inside. Need to added 5/8" fire code drywall to both sides of wall to provide the required 1-hour protection. Parapets were not required under the UBC at the time indicated for construction of kennels (< 20' height / one story. All opening and or penetrations are to be sealed with minimum 1-hour construction. No openings or penetrations in this wall. To be solid wood blocked between roof joists in line with top of wall.
|
BLD-Aging Inspection | 10/6/2010 | 10/6/2010 | 10/6/2010 | | PEND |
Tony Young
|
|
|
|
BLD - Request for Extension | 8/6/2010 | 8/6/2010 | 8/6/2010 | P | PASS |
Tony Young
|
|
|
or ###-#### Lance PLease call to discuss this Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/22/2010 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 11/13/2009 | 11/13/2009 | 12/17/2009 | | PASS |
Dan Stuart
|
|
|
12/17/2009 10:07:00 DRS - activity updated through activity BLDA022 from case BLD09-02034.
|
Routing - Erosion and Sediment | 12/16/2009 | | 12/17/2009 | | PASS |
Steven Webb
|
|
|
RP provided. Added to list by Tisha. ESC plan waiver approved according to the attached permit conditions. ESC09-00725
|
Routing - PLAN CHECK | 12/17/2009 | | 12/17/2009 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2009 | | PASS |
|
|
|
|
Print Occupancy Form | | | 12/17/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/17/2009 | | DONE |
|
|
|
left vm for richard at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 12/17/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/14/2009 | | 12/16/2009 | | PEND |
Dan Stuart
|
|
|
Re-routing to Steve Webb. ESC
|
Telephone call | | | 12/14/2009 | | DONE |
|
|
|
Called Richard George to see what action had been taken toward establishing an RP for this project. Contractor Lance Worley wa going to check this out but had not provided any data to Mr. George. Mr. George will follow up and let me know the status. ESC approval is all that remains in order to issue the permit.
|
1st review completed | | | 12/14/2009 | | FAIL |
|
|
|
Failed Erosion & Soil Control
|
Routing - FIRE | 12/7/2009 | | 12/14/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - Erosion and Sediment | 12/4/2009 | | 12/7/2009 | | FAIL |
Steven Webb
|
|
|
Responsible person listed on the ESC application is not certified by Boise City.
|
Routing PW Drainage | 12/4/2009 | | 12/4/2009 | | PASS |
Brian Murphy
|
|
|
BLD LESS THAN 500 FT SQUARE. . ADDITION IS ON TOP OF CONCREATE PAD LESS THAN 1000 SQUARE FEET
|
Routing - Addressing | 12/3/2009 | | 12/4/2009 | | PASS |
April Wing
|
|
|
April created routing slip and taking plans to PW.
|
Routing PW Sewer Rating | 12/4/2009 | | 12/4/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 12/4/2009 | | 12/4/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLAN CHECK | 11/13/2009 | | 12/3/2009 | | PASS |
Dan Stuart
|
|
|
No resubmittals required. Routing to planning.
|
Routing - PLANNING | 12/3/2009 | | 12/3/2009 | | PASS |
David Moser
|
|
|
|
Application received | | 11/12/2009 | | | |
|
|
|
|