Third Notice | | 10/11/2010 | 10/27/2010 | | DONE |
|
|
|
|
Telephone call | | | 10/27/2010 | | DONE |
Tisha Gallop
|
|
|
spoke with Arthur Macumera w/Gymboree Corp (owner of Crazy 8) he said Greenwood Const. is out of business and final total project value is $55,114; he said Precision Permits put the initial value on and they were way over.
|
Third Notice | | 8/27/2010 | 9/27/2010 | | DONE |
|
|
|
mailed
|
Third Notice | | 8/7/2010 | 8/13/2010 | | DONE |
|
|
|
faxed (error), mailed
|
Second Notice | | 7/26/2010 | 8/2/2010 | | DONE |
|
|
|
|
First Notice | | 6/19/2010 | 7/16/2010 | | DONE |
|
|
|
|
Telephone call | | | 6/9/2010 | | DONE |
Tisha Gallop
|
|
|
Per phone call with Mike Jordan to clarify mechanical work only replace the existing diffuesers with new, and no plumbing work done.
|
Permanent Occupancy | | | 6/9/2010 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 6/8/2010 | 6/8/2010 | 6/8/2010 | A | PASS |
Mike Jordan
|
|
|
Ok for perm occ. Noted that existing flex was used, only new diffusers were added. No mech. work that required permit.
|
BLD-Other | 6/7/2010 | 6/8/2010 | 6/8/2010 | A | PASS |
Mike Jordan
|
|
|
cyril - glass Phone #: ###-####
|
BLD-Final | 6/2/2010 | 6/3/2010 | 6/3/2010 | P | PART |
Mike Jordan
|
|
|
cyril Phone #: ###-####. Still needs to install storefront glass and provide paperwork for millwork. everything else ok.
|
FIRE-Final Inspection | 6/2/2010 | 6/3/2010 | 6/3/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Fire alarm passed.
|
BLD-Final | 6/1/2010 | 6/2/2010 | 6/2/2010 | P | NR |
Mike Jordan
|
|
|
Cyril Phone #: ###-####. Needs fire/life/safety.
|
BLD-Other | 5/21/2010 | 5/24/2010 | 5/24/2010 | A | PART |
Mike Jordan
|
|
|
cyril - ceiling grid Phone #: ###-####. Needs to provide wires on diffusers. Will check on final. Pending elec. rough in inspection.
|
BLD-Other | 5/20/2010 | 5/21/2010 | 5/21/2010 | A | CANC |
Mike Jordan
|
|
|
request first thing in AM//grid and above grid inspection//Cyril Webb Phone #: ###-####
|
(F) Reprint permit | | | 5/12/2010 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/29/2010 | 4/29/2010 | 4/29/2010 | P | PASS |
Dave Hannah
|
|
|
cyril Phone #: ###-#### ok to cover after elec r/i
|
Issue PAID IN FULL permit | | | 4/16/2010 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 1/14/2010 | | DONE |
|
|
|
|
Telephone call | | | 1/14/2010 | | DONE |
|
|
|
t/c w lyn davies at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 1/14/2010 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 11/13/2009 | | 1/13/2010 | | PASS |
Tim L. Woodard
|
|
|
1/13/2010 16:24:02 TLW - activity updated through activity BLDA022 from case BLD09-02049.
|
Routing - PLAN CHECK | 1/13/2010 | | 1/13/2010 | | PASS |
Tim L. Woodard
|
|
|
Plans approved with resubmittals.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/13/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 1/6/2010 | | |
Tisha Gallop
|
|
|
received resubmittals by mail; received response comments from Finn Daniles Archtiects, response comments from Dunham (Engineer), response comments from CSHQA, Burn Barrier info, three copies of Interior Lighting Compliance, structural calcs, and plan sheets A0.0, A0.1, A2.1, A2.2, A3.1, A4.1, A5.1, A5.2, A5.3, A5.4, E2.0, M1.0, M2.0, S1.0; taken to Tim Woodard
|
Routing - FIRE | | | 11/24/2009 | | PASS |
Tim L. Woodard
|
|
|
Field Verify. TLW
|
1st review completed | | | 11/24/2009 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 11/13/2009 | | 11/24/2009 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report. TLW
|
Application received | | 11/13/2009 | 11/13/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/13/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/13/2009 | | DONE |
Tisha Gallop
|
|
|
|