Permit for the construction of a new 2,570 sq. ft., two story (first story 1,503 sq. ft., Second story 1067 sq. ft.) with 4 bedrooms, 2 1/2 bathrooms, 364 sq. ft. of covered patio and a 820 sq. ft. attached garage. THE EAVES ON THE WEST SIDE OF THE STRUCTURE (LEFT SIDE) ARE REQUIRED TO BE OF ONE HOUR CONSTRUCTION ON THE UNDERSIDE WITH NO VENTS ALLOWED. All work to be done per the approved plans, plan review report, any notations and applicable codes. R-1C/DA zoning, CUP98-116 and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/29/20103/30/20103/30/2010APASS
DetailsDave Hannah
9834 access garage--Bruce Wood Phone #: ###-####
DOC - Permit Finaled3/30/20103/30/20103/30/2010PPASS
DetailsDave Hannah
BLD-Aging Inspection3/25/20103/25/20103/25/2010 PASS
DetailsDave Hannah
work in progress
BLD-Framing/Rough-in1/21/20101/22/20101/22/2010APASS
DetailsDave Hannah
bruce Phone #: ###-#### ok to cover eves
BLD-Energy code compliance1/21/20101/22/20101/22/2010APASS
DetailsDave Hannah
bruce Phone #: ###-####
BLD-Energy code compliance1/20/20101/21/20101/21/2010PNR
DetailsDave Hannah
bruce Phone #: ###-#### crew still working on project
BLD-Framing/Rough-in1/20/20101/21/20101/21/2010PPART
DetailsDave Hannah
bruce Phone #: ###-#### hangers ok but still working on eve protection
BLD-Framing/Rough-in1/19/20101/20/20101/20/2010PPART
DetailsDave Hannah
Bruce Phone #: ###-#### ok to insulate correction notice on site with corrections
BLD-Energy code compliance12/15/200912/15/200912/15/2009PPART
DetailsDave Hannah
kevin Phone #: ###-#### foundation insulation ok ok to pour slab
BLD-Footing11/30/200912/1/200912/2/2009PPART
DetailsDave Hannah
kevin Phone #: ###-#### note sw corner of foundation grade is low will need fill for 24 inhs of cover over bottom of ftg
Issue PAID IN FULL permit  11/30/2009 DONE
DetailsTisha Gallop
Route to Impact Fee Review11/13/200911/18/200911/23/2009 PASS
DetailsCindy M. Gould
Plan assigned to (CDM)11/13/200911/13/200911/23/2009 PASS
DetailsCarl D Madsen
11/23/2009 09:17:26 CDM - activity updated through activity BLDA022 from case BLD09-02051.
Routing - PLAN CHECK11/17/2009 11/23/2009 PASS
DetailsCarl D Madsen
Case Summary (BLD)  11/23/2009 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/23/2009  
1st review completed  11/23/2009 DONE
Inspection Record Card- Bld  11/23/2009 DONE
Permit Ready to Issue  11/23/2009 DONE
Telephone call  11/23/2009 DONE
sent e-mail to Steve permit ready and fee given
Routing - PLANNING  11/17/2009 PASS
DetailsColleen T Carroll
Routing - PUBLIC WORKS11/17/2009 11/17/2009 PASS
DetailsConnie Baumgartner
Routing - Addressing11/13/2009 11/16/2009 PASS
DetailsApril Wing
Application received 11/13/200911/13/2009 DONE
DetailsTisha Gallop