Second Notice | | 3/26/2010 | 3/16/2010 | | DONE |
|
|
|
|
Third Notice | | 3/21/2010 | 3/16/2010 | | DONE |
|
|
|
|
First Notice | | 3/6/2010 | 3/16/2010 | | DONE |
|
|
|
|
BLD-Final | 2/24/2010 | 2/24/2010 | 2/24/2010 | P | PASS |
Tom Arcoraci
|
|
|
Greg Phone #: ###-####
|
FIRE-Final Inspection | 2/24/2010 | 2/24/2010 | 2/24/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy | | | 2/24/2010 | | DONE |
|
|
|
|
FIRE-Conference | 2/17/2010 | 2/18/2010 | 2/18/2010 | A | DONE |
Troy Cobbley
|
|
|
Discussed the locations of several exit signs in relation to sprinkler pendants.
|
BLD-Framing/Rough-in | 1/21/2010 | 1/21/2010 | 1/21/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 1/20/2010 | 1/21/2010 | 1/21/2010 | A | PASS |
Tom Arcoraci
|
|
|
Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 1/13/2010 | 1/14/2010 | 1/14/2010 | A | PASS |
Tom Arcoraci
|
|
|
Greg Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 1/5/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/5/2010 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 12/31/2009 | 12/31/2009 | 1/4/2010 | | PASS |
Carl Westfall
|
|
|
1/4/2010 14:58:50 CJW - activity updated through activity BLDA022 from case BLD09-02109.
|
Routing - PLAN CHECK | 12/31/2009 | | 1/4/2010 | | PASS |
Carl Westfall
|
|
|
Reviewed and approved proposed plan modification.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/4/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/4/2010 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 12/31/2009 | | |
Tisha Gallop
|
|
|
Plan modification accepted for Bld09-02109 (Quality Thermistor) becuase discovered existing sheer wall that part of was to be removed. Made modifications to amount of wall to be removed. Providing engineering calculations and plans; submitted on sheets A2.0, A2.2, plan sheet no page #, and structural calculations; routed to Carl Westfall
|
BLD-Footing | 12/28/2009 | 12/29/2009 | 12/29/2009 | P | PASS |
Tom Arcoraci
|
|
|
Greg Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/22/2009 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 11/27/2009 | | 12/21/2009 | | PASS |
Carl Westfall
|
|
|
12/21/2009 13:47:52 CJW - activity updated through activity BLDA022 from case BLD09-02109.
|
Routing - PLAN CHECK | 12/10/2009 | | 12/21/2009 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/21/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/21/2009 | | DONE |
|
|
|
called Mike permit ready and fee given 12-21-09 dld
|
Permit Ready to Issue | | | 12/21/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/18/2009 | | |
Tisha Gallop
|
|
|
received transmittal and two copies of plan sheets A1.0, A1.1, A2.0, A2.2, A3.0, A5.0, A6.0, E1.0, E2.0, E3.0; taken to Carl Westfall
|
Route to Impact Fee Review | 12/9/2009 | 12/14/2009 | 12/10/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - FIRE | 12/8/2009 | 12/8/2009 | 12/10/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 12/10/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 11/30/2009 | | 12/9/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on December 2, 2009 and finished on December 9, 2009. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 11/27/2009 | | 11/30/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 11/30/2009 | | 11/30/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 11/24/2009 | | 11/27/2009 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 11/27/2009 | | 11/27/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 11/24/2009 | 11/24/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/24/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/24/2009 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 11/24/2009 | | PASS |
Carl D Madsen
|
|
|
|