Letter of compliance/Occupancy | | | 1/18/2011 | | DONE |
Christina Prado
|
|
|
|
First Notice | 6/17/2010 | 6/17/2010 | 8/2/2010 | | DONE |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 6/16/2010 | 6/16/2010 | 6/17/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed per the scope of work.
|
BLD-Final | 6/16/2010 | 6/17/2010 | 6/17/2010 | A | PASS |
Dave Hannah
|
|
|
Darrell Phone #: ###-####
|
DOC - Permit Finaled | 6/17/2010 | 6/17/2010 | 6/17/2010 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 4/29/2010 | 5/3/2010 | 5/3/2010 | A | PART |
Dave Hannah
|
|
|
kelly \\ceiling Phone #: ###-#### ok to cover ceiling
|
FIRE-Final Inspection | 3/9/2010 | 3/9/2010 | 3/9/2010 | P | FAIL |
Forrest France
|
|
|
Need to provide EM lighting per plan at two locations, post signage at door to the sprinkler antifreeze manifold riser per review note # 16, project attatched fire sprinkler permit final pending missing ceiling tile and escutcheons at some areas. Remainder of fire life safety items okayed.
|
Issue & PRINT to be Invoiced | | | 12/29/2009 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 12/15/2009 | 12/15/2009 | 12/24/2009 | | PASS |
Carl D Madsen
|
|
|
12/24/2009 10:36:53 CDM - activity updated through activity BLDA022 from case BLD09-02218.
|
Routing - PLAN CHECK | 12/15/2009 | | 12/24/2009 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | | | 12/24/2009 | | PASS |
Carl D Madsen
|
|
|
Verify in field cdm
|
1st review completed | | | 12/24/2009 | | DONE |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 12/24/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/24/2009 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/24/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/24/2009 | | |
|
|
|
|
Telephone call | | | 12/24/2009 | | DONE |
|
|
|
called Josh permit ready and fee given 12-24-09 dld
|
Case Summary (BLD) | | | 12/15/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/15/2009 | | DONE |
|
|
|
|
Application received | | 12/15/2009 | | | |
|
|
|
|