Second Notice | | 3/13/2011 | 3/17/2011 | | DONE |
|
|
|
faxed 3-17-11. Final value received 3/21/11. Value reduced due to elimination of bathroom on plans. No plumbing work needed. Mech value split between the two permits.
|
First Notice | | 2/26/2011 | 3/3/2011 | | DONE |
|
|
|
|
BLD-Conference | 2/15/2011 | 2/15/2011 | 2/16/2011 | A | PASS |
Tony Young
|
|
|
investigate shower rooms?,, built or not.. NOT BUILT,, ok to final out..
|
BLD-Final | 2/14/2011 | 2/14/2011 | 2/16/2011 | P | PART |
Tony Young
|
|
|
Tony//scheduled by Ron Hill Phone #: ###-#### (note: need plumbing permit for shower rooms?),, they elected not to do the shower rooms at this point
|
Permanent Occupancy | | | 2/16/2011 | | DONE |
Barbara Stitt
|
|
|
|
Extend Permit 90/180 days | | 12/22/2010 | 12/22/2010 | | DONE |
|
|
|
extend 90 days per Jason Blais
|
BLD-Aging Inspection | 9/23/2010 | 9/23/2010 | 9/23/2010 | | PEND |
Tony Young
|
|
|
|
Temporary Occupancy | 9/23/2010 | 12/22/2010 | 9/23/2010 | | DONE |
Jason Blais
|
|
|
approved for extension by Jason Blais see scaned documents
|
Temporary Occupancy | 6/23/2010 | 9/21/2010 | 6/23/2010 | | DONE |
Tisha Gallop
|
|
|
pending Bld09-02173 finaled
|
BLD-Final | 6/21/2010 | 6/22/2010 | 6/22/2010 | A | PASS |
Tony Young
|
|
|
Dan Phone #: ###-####
|
FIRE-Final Inspection | 6/21/2010 | 6/21/2010 | 6/22/2010 | P | PASS |
Forrest France
|
|
|
Inspection passed, fire life safety finaled.
|
BLD-Aging Inspection | 6/3/2010 | 6/3/2010 | 6/7/2010 | | PEND |
Tony Young
|
|
|
|
FIRE-Conference | 3/4/2010 | 3/4/2010 | 3/4/2010 | P | DONE |
Forrest France
|
|
|
Regarding project related FIR10-00091 pipe materials.
|
FIRE-Conference | 2/24/2010 | 2/25/2010 | 2/25/2010 | A | DONE |
Forrest France
|
|
|
On site conferecne regarding fire sprinkler protection at the relocated radio test room and conditions per IFC 2006 903.3.1.1.1.
|
BLD-Framing/Rough-in | 2/2/2010 | 2/3/2010 | 2/3/2010 | A | PART |
Tony Young
|
|
|
Dan Phone #: ###-#### columns (2),, fire rating 1 hr,, ok per plan
|
BLD-Framing/Rough-in | 1/26/2010 | 1/26/2010 | 1/26/2010 | P | PASS |
Mike Jordan
|
|
|
Interior steel stud framed walls, 1st. floor ok.
|
Issue PAID IN FULL permit | | | 1/8/2010 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 1/4/2010 | | PASS |
Dan Stuart
|
|
|
|
Additional plans submitted | | | 1/4/2010 | | PASS |
|
|
|
Plans for change of door 001a received 12/22/09 while on vacation (e-mailed). Foor used to receive & deliver product & equipment for business. There are two separate required exits in addition to this product receiving / delivery door.
|
Routing - PLAN CHECK | 12/22/2009 | | 1/4/2010 | | PASS |
Dan Stuart
|
|
|
Plans back from PW review 12/22/09. Resubmitted plan detail for door 001a installation received by e-mail 12/22/09. Inserted into plans 1/04/10 (after vacation). Plans to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/4/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 1/4/2010 | | DONE |
|
|
|
|
Telephone call | | | 1/4/2010 | | DONE |
|
|
|
t/c w chris anderson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 1/4/2010 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/17/2009 | | 12/21/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 12/21/2009 | | 12/21/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Plan assigned to (DRS) | 12/15/2009 | 12/15/2009 | 12/17/2009 | | PASS |
Dan Stuart
|
|
|
12/17/2009 13:45:52 DRS - activity updated through activity BLDA022 from case BLD09-02227.
|
Plan resubmittals received | | | 12/17/2009 | | DONE |
|
|
|
received transmittal letter - 2 sets of A4.01 - taken to dan stuart
|
Routing - Addressing | 12/17/2009 | | 12/17/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 12/15/2009 | 12/15/2009 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/15/2009 | | DONE |
|
|
|
|