CHANGE STATUS TO (FNL) | | | 7/17/2010 | | DONE |
|
|
|
|
BLD-Final | 7/9/2010 | 7/9/2010 | 7/9/2010 | P | PASS |
Jim Storey
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 7/9/2010 | 7/9/2010 | 7/9/2010 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 7/6/2010 | 7/7/2010 | 7/7/2010 | P | NR |
Mike Jordan
|
|
|
Brett Phone #: ###-####. Needs electrical final.
|
BLD-Energy code compliance | 6/3/2010 | 6/4/2010 | 6/4/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 6/4/2010 | 6/4/2010 | 6/4/2010 | P | PASS |
Mike Jordan
|
|
|
Framing issues were repaired.
|
BLD-Framing/Rough-in | 6/2/2010 | 6/3/2010 | 6/3/2010 | P | FAIL |
Mike Jordan
|
|
|
Complete all lateral bracing, provide strap on top plate from 2x6 to 2x4 wall transition in garage. ok to insulate. correction notice posted.
|
BLD-Foundation | 5/20/2010 | 5/20/2010 | 5/20/2010 | P | PASS |
Mike Jordan
|
|
|
donny Phone #: ###-####
|
BLD-Foundation | 5/19/2010 | 5/19/2010 | 5/20/2010 | P | CANC |
Mike Jordan
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 5/20/2010 | 5/20/2010 | 5/20/2010 | A | PASS |
Mike Jordan
|
|
|
Ryan Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/21/2010 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 4/20/2010 | | DONE |
Tisha Gallop
|
|
|
|
CHANGE STATUS TO (RDY) | | | 4/20/2010 | | DONE |
Tisha Gallop
|
|
|
change permit back to RDY status, will not pick up permit until 4/21
|
OVERRIDE | | | 2/17/2010 | | |
|
|
|
|
Telephone call | | | 2/17/2010 | | DONE |
Barbara Stitt
|
|
|
Called and told Tanya and told her that plans were ready and fees due @ 8:23am on 2-17-10 BAS
|
Permit Ready to Issue | | | 2/17/2010 | | DONE |
Barbara Stitt
|
|
|
|
Route to Impact Fee Review | 12/15/2009 | 12/18/2009 | 2/12/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (PEP) | 2/11/2010 | 2/11/2010 | 2/11/2010 | | PASS |
Perry Paine
|
|
|
2/11/2010 15:37:35 PEP - activity updated through activity BLDA022 from case BLD09-02229.
|
Plan assigned to (CDM) | 12/15/2009 | 12/15/2009 | 2/11/2010 | | DEFR |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/8/2010 | | 2/11/2010 | | PEND |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/11/2010 | | 2/11/2010 | | PASS |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 2/11/2010 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/11/2010 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PUBLIC WORKS | 2/5/2010 | | 2/8/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Plan resubmittals received | | | 2/5/2010 | | DONE |
|
|
|
2 new sets of plans taken to Susan Riggs
|
Routing - PLANNING | 2/5/2010 | | 2/5/2010 | | PASS |
Susan Riggs
|
|
|
|
1st review completed | | | 12/17/2009 | | FAIL |
|
|
|
|
Routing - PLANNING | 12/16/2009 | | 12/17/2009 | | FAIL |
Colleen T Carroll
|
|
|
routed to Susan Riggs per CUP09-00129
fail for lack of design
|
Routing - PLAN CHECK | 12/17/2009 | | 12/17/2009 | | FAIL |
Carl D Madsen
|
|
|
Full review could not be completed because of Planning issues.
|
Routing - Addressing | 12/15/2009 | | 12/16/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 12/15/2009 | 12/15/2009 | | DONE |
Tisha Gallop
|
|
|
|