Permit NumberBLD09-02232
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 618 N ALLUMBAUGH ST
Project NameDarigold - Chemical Storage Ro
Customer Number 
ePlanReviewNo
Description
Darigold - Chemical Storage Room Addition - To make the exising 400 square foot, dock on the north side of the building permanent and to construct a 600 square foot, one story chemical storage room on the west side of the dock. The storage room and dock addition are constructed of masonry and steel stud exterior walls and steel roof joists with metal roofing over plywood roof deck. This permit also includes the construction of a secondary containment area around the "courtyard" on the interior of the building surround. All construction per the approved plans and red lined notes. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  8/27/2019 DONE
Case Summary (BLD)  8/27/2019 DONE
Third Notice 2/7/20113/9/2011 DONE
Third Notice 1/12/20111/24/2011 DONE
faxed and e-mailed
Third Notice 11/29/201012/29/2010 DONE
faxed
Second Notice 11/22/201011/24/2010 DONE
First Notice 11/7/201011/12/2010 DONE
Override - Parcel Holds  10/28/2010  
Permanent Occupancy UNPAID FEE  10/28/2010 DONE
DetailsTisha Gallop
BLD-Final10/1/201010/1/201010/1/2010PPASS
DetailsJim Storey
BLD-Aging Inspection9/8/20109/8/20109/8/2010 PASS
DetailsTom Arcoraci
BLD-Wall cover7/6/20107/7/20107/7/2010APASS
DetailsJim Storey
3dr lift 9:30 am
BLD-Other7/6/20107/6/20107/6/2010PPASS
DetailsJim Storey
2nd grout lift. 1:00
BLD-Concrete7/2/20107/6/20107/6/2010APASS
DetailsJim Storey
8:30 grout pour appt. 1st litft ok
BLD-Other6/30/20106/30/20106/30/2010APASS
DetailsJim Storey
rebar ok
Zoning Approval6/28/20106/28/20106/28/2010 DONE
DetailsAndrea Tuning
BLD-Other5/21/20105/21/20105/21/2010PPASS
DetailsJim Storey
handrail c/n made ok
BLD-Final5/3/20105/3/20105/3/2010APART
DetailsJim Storey
temp ok
FIRE-Final Inspection4/26/20104/26/20104/26/2010APASS
DetailsForrest France
Fire life safety final approved.
BLD-Final4/21/20104/23/20104/23/2010APART
DetailsJim Storey
c/n handrail on wall west exit stair.
Zoning Approval Temp4/22/20104/22/20104/22/2010 DONE
DetailsAndrea Tuning
This is a 30 day temporary approval only. The applicant must modify the DR application to reflect the elimination of a man door on teh east elevation, the modification to the loading dock and rail located on the east elevation, install and stripe the 12 parking spaces on the south side of the building, remove the pallettes fromt eh required parkign area and eliminate the rock mulch in the planter located along the south property line.
BLD-Conference4/19/20104/20/20104/21/2010ACANC
DetailsJim Storey
FIRE-Final Inspection4/19/20104/20/20104/20/2010APART
DetailsForrest France
Automatic fire door tested okay per NFPA 80, EM lights and exit signs approved, project related sprinkler permit finaled, door hardware is satisfactory. Final pending project attatched fire alarm permit work- note; ID detector, SD, and horn passed functional test.
FIRE-Conference4/2/20104/2/20104/2/2010PDONE
DetailsForrest France
Regarding fire code review note items including IFC 4004.1.6, fire alarm/sprinkler permits, and door hardware requirements for H occupancies.
BLD-Wall cover3/15/20103/16/20103/16/2010APASS
DetailsJim Storey
first layer of rated wall interior.
BLD-Framing/Rough-in3/11/20103/11/20103/11/2010APASS
DetailsJim Storey
reviewed damper installation listing ok to cover.
BLD-Conference3/10/20103/10/20103/10/2010APART
DetailsJim Storey
wrong listing for damper assembly/ got corect info. in the submital process for insp.
BLD-Framing/Rough-in3/9/20103/9/20103/9/2010PNR
DetailsJim Storey
pending listing instaltion guide for damper in ratted wall.
BLD-Wall cover3/8/20103/8/20103/8/2010ACANC
DetailsJim Storey
first layer of gyp for septration wall. 12:00 am appt.301 1 st layer ok to cover/ talked to contractor to cordenate with mech contractor to provide listing and mech insp with myself to insp. framing.
BLD-Framing/Rough-in3/5/20103/5/20103/5/2010APART
DetailsJim Storey
re-insp.all but roof sheathing at old dock 6 oc screw sch is pending.
BLD-Framing/Rough-in3/2/20103/2/20103/2/2010PFAIL
DetailsJim Storey
roof dyaphram not compley under overbuild/ missing screw pattern roof and sheer walls. reviewed 1 hr top of wall requirments.
BLD-Wall cover2/22/20102/25/20102/25/2010APASS
DetailsJim Storey
9:00 am appointment cmu walls. top out ok.
BLD-Wall cover2/22/20102/24/20102/24/2010ACANC
DetailsJim Storey
9:00 am appointment cmu walls. rained out
BLD-Wall cover2/23/20102/23/20102/23/2010PPASS
DetailsJim Storey
cmu chem bld. 2 nd lift 1:30 appt.
BLD-Wall cover2/22/20102/23/20102/23/2010APASS
DetailsJim Storey
9:00 am appointment cmu walls. first lift cmu and rebar ok si on site.
BLD-Foundation2/16/20102/17/20102/17/2010APASS
DetailsJim Storey
9:00 appt.exterior tank storage wall rebar and containment height ok.
BLD-Concrete2/12/20102/12/20102/12/2010PPASS
DetailsJim Storey
3:00 appt exterior tank pads at chem storage exterior area west of loading dock ok.
BLD-Foundation2/5/20102/5/20102/5/2010PPASS
DetailsJim Storey
chem wall and containment
BLD-Footing2/4/20102/4/20102/4/2010PPASS
DetailsJim Storey
ft ok chem.
BLD-Footing2/4/20102/4/20102/4/2010PPASS
DetailsJim Storey
office restrooms framing ok
Case Summary (BLD)  1/19/2010 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  1/12/2010 DONE
DetailsTisha Gallop
Routing - FIRE1/5/20101/5/20101/8/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
Plan assigned to (JCM)12/16/2009 1/8/2010 PASS
DetailsJohn Menard
1/8/2010 11:43:36 JCM - activity updated through activity BLDA022 from case BLD09-02232.
1st review completed  1/8/2010 FAIL
Failed Planning
Routing - PLANNING1/8/2010 1/8/2010 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK1/8/2010 1/8/2010 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  1/8/2010 DONE
DetailsJohn Menard
Print Occupancy Form  1/8/2010 DONE
Telephone call  1/8/2010 DONE
called Cornel Larson permit ready and fee given Also need ACHD 1-8-10 dld
Permit Ready to Issue  1/8/2010 DONE
Route to Impact Fee Review1/5/20101/8/20101/7/2010 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK12/18/2009 1/5/2010 PASS
DetailsJohn Menard
Routing Off Site - STRUCTURAL12/16/2009 12/29/2009 PASS
DetailsJason Blais
Review attached to case.
Plan resubmittals received  12/23/2009  
DetailsJohn Menard
Rec'd three copies of sheet SP-1- inserted by arch rep and taken back to John M
Routing PW Drainage12/17/2009 12/18/2009 PASS
DetailsBrian Murphy
talked to Cornel no pipes to seepage bed from storage area will be pumped.
Routing - PUBLIC WORKS1/16/2009 12/18/2009 PASS
DetailsBeverly Hall
Routing - Erosion and Sediment12/18/2009 12/18/2009 PASS
DetailsSteven Webb
ESC plan approved under ESC09-02232 as well as permit conditions.
Routing - PLUMBING12/18/2009 12/18/2009 PASS
DetailsBill VanDegrift
no plumbing
Routing - PLANNING12/18/2009 12/18/2009 FAIL
DetailsAndrea Tuning
Fail - The applicant must add three additional parking spaces and provide a copy of a new shared parking agreement that reflects the new parkign layout DRH09-00147 Andrea Tuning
Plan resubmittals received  12/17/2009 DONE
received 4 sets of A-1, A-3 - taken to brian murphy
Routing PW Environmental12/17/2009 12/17/2009 PASS
DetailsWalt Baumgartner
Permitted significant industrial user (SIU) in WestBoise sewer district. Reviewed for ASPP requirements - OK
Routing - Addressing12/16/2009 12/16/2009 PASS
DetailsApril Wing
Plans ACCEPTED BY PLAN TECH  12/16/2009 DONE
Routing - PLANNING Land Div12/16/2009 12/16/2009 PASS
DetailsDave Abo
Pending Assignment by JCM12/16/2009 12/16/2009 BLDA
DetailsJohn Menard
12/16/2009 09:57:15 JCM - activity updated through activity BLDA166 from case BLD09-02232.
Application received 12/16/2009