Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD09-02257
StatusFinaled
Name PATTERSON COMPANY
Site Address 4417 N STRATHMORE PL
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit for the construction of a new 3,176 sq. ft. two story single family dwelling with 3 bedrooms, 2 full bathrooms, 2 half bathrooms, approximately 416 sq. ft. of covered patio and a 878 sq. ft. attached garage. All work to be done per the approved plans, attached engineering and any notations. Special inspection is required for the epoxy anchors for the steel columns in the garage. A letter from the applicant's geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at 384-3946 R-1B zoning and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled3/8/20113/8/20113/8/2011APASS
DetailsTony Young
BLD-Aging Inspection3/4/20113/4/20113/8/2011 PASS
DetailsTony Young
BLD-Final8/23/20108/23/20108/23/2010PPASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Grading Inspection8/3/20108/3/20108/3/2010ADONE
DetailsTerry Records
Final grading and drainage approved.
BLD-Energy code compliance6/7/20106/7/20106/7/2010PPASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Framing/Rough-in6/1/20106/1/20106/1/2010PPART
DetailsTony Young
Scott Phone #: ###-####,, corrections, trusses, straps,, , ok to insulate
BLD-Wall cover5/24/20105/24/20105/24/2010PPASS
DetailsTony Young
Scott Phone #: ###-####,, shear on exterior ok
BLD-Conference5/5/20105/5/20105/5/2010PPART
DetailsTony Young
Scott Phone #: ###-####,, shear conf
BLD-Foundation4/6/20104/7/20104/8/2010PPART
DetailsTony Young
Phone #: ###-####,, work in progress,, ok to pour when ready
BLD-Footing4/6/20104/6/20104/6/2010PPART
DetailsTony Young
Phone #: ###-####,, work in progress,, ok
PubWorks Subgrade Approval3/29/20103/29/20103/29/2010 DONE
DetailsTerry Records
HOUSE FOOTING SUBGRADE APPROVED BY THE GEOTECHNICAL ENGINEER
BLD-Foundation3/17/20103/19/20103/19/2010APART
DetailsTony Young
adam Phone #: ###-####,, work in progress on retaining wall (wall),, ok
BLD-Footing3/17/20103/18/20103/18/2010APART
DetailsTony Young
adam Phone #: ###-####,, retaining wall work in progress,, ok
PubWorks Subgrade Approval3/17/20103/17/20103/17/2010 DONE
DetailsTerry Records
Retaining wall subgrade approved by the geotechnical engineer
Issue PAID IN FULL permit  3/8/2010 DONE
Route to Impact Fee Review12/18/200912/23/20091/4/2010 PASS
DetailsCindy M. Gould
Plan assigned to (CDM)12/18/200912/18/20091/4/2010 DONE
DetailsCarl D Madsen
Routing - Erosion and Sediment12/22/2009 1/4/2010 PASS
DetailsSteven Webb
ESC plan was approved along with the permit conditions on 12/22/09. ESC09-00803
Routing - PLAN CHECK12/24/2009 1/4/2010 PASS
DetailsCarl D Madsen
Case Summary (BLD)  1/4/2010 DONE
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  1/4/2010  
Inspection Record Card- Bld  1/4/2010 DONE
Telephone call  1/4/2010 DONE
called left message for Scott permit ready and fee given 1-4-10 ///dld
Permit Ready to Issue  1/4/2010 DONE
Routing - FIRE12/22/2009 12/24/2009 PASS
DetailsScott Arellano
No fire sprinkler requirement.
Routing PW Grading-Hillside12/21/2009 12/22/2009 PASS
DetailsTerry Records
Approved as category 3
Routing - PUBLIC WORKS  12/22/2009 PASS
DetailsConnie Baumgartner
Routing - PLANNING12/22/2009 12/22/2009 PASS
DetailsColleen T Carroll
Approved as redlined, eave on north side of garage shall be reduce to 2 feet.
Routing - Addressing12/18/2009 12/21/2009 PASS
DetailsApril Wing
Application received 12/18/200912/18/2009 DONE
DetailsTisha Gallop
Per Terry R. ok to submit for building for building dept. also