Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD09-02300
StatusFinaled
Name RM HARRISON & COMPANY
Site Address 2206 N COLE RD
Project NameSt. Stephens Episcopal Church
Customer Number 
ePlanReviewNo
Description
(ST. STEVEN'S EPISCOPAL CHURCH - Sacristy Remodel) Permit is to remodel an existing church. PLAN MODIFICATION 10-21-10 – Modification submitted to install new fire barrier wall, new exit corridor, and new accessible entry to Nave.**TLW** Approval contingent upon adhering to the approved plans on file. Work to include: demo interior non-bearing wall, relocate and enlarge door openings, install new door hardware, frame in mechanical room floor to raise it to the same floor level as the adjoining rooms, modify existing restroom to create a fully accessible unisex restroom, and finishes in compliance with chapter 8 of the 2006 IBC. This building is not fire sprinklered; any alteration to this building that increases occupant load or square footage would require a sprinkler system to be installed. PLAN MODIFICATION 10-21-10 – Modification submitted to install new fire barrier wall, new exit corridor, and new accessible entry to Nave.**TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/22/20112/21/2011 DONE
This permit finaled on the web by robert harrison
Second Notice 2/14/20112/17/2011 DONE
DetailsChristina Prado
Second notice Mailed 2-17-2011
First Notice2/3/20112/3/20112/4/2011 DONE
DetailsTom Arcoraci
BLD-Final2/2/20112/3/20112/3/2011APASS
DetailsTom Arcoraci
Call prior to arrival--Bob Phone #: ###-####
DOC - Permit Finaled2/3/20112/3/20112/3/2011PPASS
DetailsTom Arcoraci
FIRE-Final Inspection2/2/20112/2/20112/2/2011PPASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final2/1/20112/2/20112/2/2011ANR
DetailsTom Arcoraci
robert - please call 1/2 hr prior Phone #: ###-#### needs mech and fie finals
BLD-Framing/Rough-in12/15/201012/16/201012/16/2010APASS
DetailsTom Arcoraci
robert Phone #: ###-####
BLD-Conference11/5/201011/8/201011/8/2010APASS
DetailsTom Arcoraci
robert Phone #: ###-####
BLD-Footing11/5/201011/8/201011/8/2010APASS
DetailsTom Arcoraci
robert Phone #: ###-####
BLD-Aging Inspection10/27/201010/27/201010/27/2010 PASS
DetailsTom Arcoraci
CHANGE STATUS TO (ISS)  10/26/2010 DONE
DetailsBarbara Stitt
(F) Reprint permit  10/26/2010 DONE
DetailsBarbara Stitt
OVERRIDE  10/22/2010  
Telephone call  10/22/2010 DONE
DetailsTisha Gallop
called Liz/Matter Arch. and told her plan mod ready and fees.
Case Summary (BLD)  10/22/2010 DONE
DetailsTisha Gallop
Override - Parcel Holds  10/22/2010  
Permit Ready to Issue  10/22/2010 DONE
DetailsTisha Gallop
Plan assigned to (TLW)9/24/2010 10/21/2010 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK9/24/2010 10/21/2010 PASS
DetailsTim L. Woodard
Modification approved with new resubmittals. TLW
PLANS/APPL TAKEN TO FRONT DESK  10/21/2010 DONE
DetailsTim L. Woodard
Case Summary (BLD)  10/21/2010 DONE
DetailsTim L. Woodard
Plan resubmittals received  10/20/2010  
10-20-10 received 1 transmittal letter,and 2 copies of sheets Code Analysis,a1,a2 taken to Tim Woodard for review.
Plan Modification Accepted  9/23/2010 DONE
DetailsTisha Gallop
Plan modification accepted for Bld09-02300 (St. Stephens Episcopal Church) Modification No. 1 includes ADA upgrades and one-hour exit passageway and construction of a 2 hour fire barrier wall along the south wall of the multi-purpose area and north of existing Nave wall. All work is done inside the building, therefore, no approval from Planning is required. Cody Riddle confirmed by e-mail September 20,2010; submitted on plan sheets A2, A2 and revised certificate of value. Routed to Tim Woodard.
BLD-Aging Inspection7/26/20107/26/20107/26/2010PNR
DetailsTroy Cobbley
Per Bill revised drawings are being submitted and the inspection will hopefully be called in next week.
BLD-Aging Inspection7/26/20107/26/20107/26/2010 FAIL
DetailsTom Arcoraci
see fire inspection
BLD-Aging Inspection5/25/20105/25/20105/25/2010 FAIL
DetailsTom Arcoraci
see fire insp
FIRE-Final Inspection3/25/20103/25/20103/25/2010PFAIL
DetailsTroy Cobbley
The inspection turned into a conference. Plans are going to be resubmitted showing changes in the exiting path. Also the new doors in the new addition need approved single action hardware installed and fire extinguishers need installed as discussed.
BLD-Final3/24/20103/25/20103/25/2010ANR
DetailsTom Arcoraci
Robert-Please call prior to inspection Phone #: ###-####
BLD-Conference3/23/20103/23/20103/23/2010PPASS
DetailsTom Arcoraci
BLD-Aging Inspection3/23/20103/23/20103/23/2010 PASS
DetailsTom Arcoraci
Plan Reviewer's activity  1/29/2010 DONE
DetailsTim L. Woodard
Recieved revised restroom detail. Approved detail and attached to case. TLW
BLD-Framing/Rough-in1/20/20101/21/20101/21/2010PPASS
DetailsTom Arcoraci
Robert-Please call at least 1 hr prior to inspection Phone #: ###-####
Inspection Record Card- Bld  1/12/2010 DONE
Inspection Record Card- Bld  1/12/2010 DONE
Telephone call  1/12/2010 DONE
Details
t/c w bill matter at ###-#### - permit ready and fees given
Permit Ready to Issue  1/12/2010 DONE
Details
Issue PAID IN FULL permit  1/12/2010 DONE
Plan assigned to (TLW)12/30/2009 1/11/2010 PASS
DetailsTim L. Woodard
1/11/2010 14:56:21 TLW - activity updated through activity BLDA022 from case BLD09-02300.
Routing - PLAN CHECK12/31/2009 1/11/2010 PASS
DetailsTim L. Woodard
Approved with notes about when sprinklers are required. TLW
Routing - PLANNING1/11/2010 1/11/2010 PASS
DetailsTim L. Woodard
Verified with Sarah Schaffer that no CZC is required. TLW
Routing - FIRE  1/11/2010 PASS
DetailsTim L. Woodard
Field Verify. TLW
1st review completed  1/11/2010 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  1/11/2010 DONE
DetailsTim L. Woodard
Routing - Erosion and Sediment1/11/2010 1/11/2010 PASS
DetailsTim L. Woodard
Waiver Request approved contigent on adhereing to the attached conditions. TLW
Case Summary (BLD)  1/11/2010 DONE
DetailsTim L. Woodard
Routing - PUBLIC WORKS12/30/2009 12/31/2009 PASS
DetailsBeverly Hall
Routing PW Sewer Rating12/31/2009 12/31/2009 PASS
DetailsConnie Baumgartner
Application received 12/30/200912/30/2009 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  12/30/2009 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  12/30/2009 DONE
DetailsTisha Gallop
Routing - Addressing12/30/2009 12/30/2009 PASS
DetailsApril Wing