BLD-Final | 6/30/2010 | 7/2/2010 | 7/2/2010 | A | PASS |
Mike Jordan
|
|
|
Please call for on-site access. Thanks! Inspection requested from web by: Scott Zierler Phone #: ###-####
|
DOC - Permit Finaled | 7/2/2010 | 7/2/2010 | 7/2/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy was issued.
|
BLD-Aging Inspection | 6/16/2010 | 6/16/2010 | 6/21/2010 | | PASS |
Mike Jordan
|
|
|
Work is in progress.
|
BLD-Energy code compliance | 4/15/2010 | 4/15/2010 | 4/15/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/14/2010 | 4/15/2010 | 4/15/2010 | A | NR |
Mike Jordan
|
|
|
Insulation inspection Inspection requested from web by: Scott Zierler Phone #: ###-####
|
BLD-Framing/Rough-in | 4/14/2010 | 4/15/2010 | 4/15/2010 | A | PASS |
Mike Jordan
|
|
|
Reinspect Inspection requested from web by: Scott Zierler Phone #: ###-####
|
BLD-Energy code compliance | 4/13/2010 | 4/14/2010 | 4/14/2010 | A | NR |
Mike Jordan
|
|
|
Inspection requested from web by: Scott Zierler Phone #: ###-####
|
BLD-Framing/Rough-in | 4/13/2010 | 4/14/2010 | 4/14/2010 | A | PART |
Mike Jordan
|
|
|
please call for on onsite visit Inspection requested from web by: Scott Zierler Phone #: ###-####. ok to insulate. Needs to provide stud shoe at plumbing penetration.
|
BLD-Energy code compliance | 4/13/2010 | 4/15/2010 | 4/13/2010 | A | CANC |
Mike Jordan
|
|
|
Inspection requested from web by: Scott Zierler Phone #: ###-#### Inspection cancelled from web by: Scott Zierler
|
BLD-Framing/Rough-in | 4/13/2010 | 4/15/2010 | 4/13/2010 | A | CANC |
Mike Jordan
|
|
|
please call for onsite access Inspection requested from web by: Scott Zierler Phone #: ###-#### Inspection cancelled from web by: Scott Zierler
|
Issue PAID IN FULL permit | | | 2/10/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/8/2010 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 2/8/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 1/4/2010 | 1/4/2010 | 2/5/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 1/26/2010 | | 2/5/2010 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 2/5/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2010 | | |
|
|
|
|
Routing - PUBLIC WORKS | 1/26/2010 | | 1/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 1/22/2010 | | 1/22/2010 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING | 1/15/2010 | | 1/21/2010 | | PASS |
Joshua Johnson
|
|
|
|
Application received | | 1/4/2010 | 1/4/2010 | | DONE |
Tisha Gallop
|
|
|
Per CDM route only to Plan Check
|