BLD-Final | 4/6/2010 | 4/6/2010 | 4/6/2010 | A | PASS |
Mike Jordan
|
|
|
Please call for onsite access Inspection requested from web by: Scott Zierler Phone #: ###-####
|
DOC - Permit Finaled | 4/6/2010 | 4/6/2010 | 4/6/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy issued.
|
BLD-Wall cover | 2/26/2010 | 3/1/2010 | 3/1/2010 | P | PASS |
Mike Jordan
|
|
|
Please contact Scott at ###-#### for site visit. Thanks Inspection requested from web by: Scott Zierler Phone #: ###-####. 5/8 type x rock for completion of 2hr fire walls at property lines. ok to mud and tape.
|
BLD-Energy code compliance | 2/19/2010 | 2/22/2010 | 2/22/2010 | P | PASS |
Mike Jordan
|
|
|
Please contact Scott at ###-#### to meet on site. Thank you. Inspection requested from web by: Scott Zierler Phone #: ###-####. All previous noted issues have been resolved.
|
BLD-Framing/Rough-in | 2/17/2010 | 2/18/2010 | 2/18/2010 | P | PART |
Mike Jordan
|
|
|
Please contact Scott Zierler with Prestige Homes at ###-#### for access. Inspection requested from web by: Scott Zierler Phone #: ###-####. Provide draft stop at furdown in bathroom nd laundry room. Block microlam. and provide additional smoke detector.
|
Issue PAID IN FULL permit | | | 2/10/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/8/2010 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 2/8/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 1/4/2010 | 1/4/2010 | 2/4/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 1/26/2010 | | 2/4/2010 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 2/4/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/4/2010 | | |
|
|
|
|
Routing - PUBLIC WORKS | 1/26/2010 | | 1/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 1/22/2010 | | 1/22/2010 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING | 1/15/2010 | | 1/21/2010 | | PASS |
Joshua Johnson
|
|
|
|
Application received | | 1/4/2010 | 1/4/2010 | | DONE |
Tisha Gallop
|
|
|
Per CDM route only to Plan Check
|