Third Notice | | 3/15/2010 | 3/18/2010 | | DONE |
|
|
|
|
Second Notice | | 3/5/2010 | 3/10/2010 | | DONE |
|
|
|
|
First Notice | | 2/15/2010 | 2/23/2010 | | DONE |
|
|
|
|
BLD-Final | 2/4/2010 | 2/5/2010 | 2/5/2010 | A | PASS |
Mike Jordan
|
|
|
Jentry please call 30 min before going out Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy UNPAID FEE | | | 2/5/2010 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 2/3/2010 | 2/4/2010 | 2/4/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 1/26/2010 | 1/27/2010 | 1/27/2010 | A | PASS |
Mike Jordan
|
|
|
Jentry please call 1 hr brfore going out. this is a locked gate entry Phone #: ###-####. Interior wood framed walls and lid for restrooms.
|
Issue PAID IN FULL permit | | | 1/14/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/13/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/13/2010 | | |
|
|
|
|
Telephone call | | | 1/13/2010 | | DONE |
|
|
|
called Matt Rhees permit ready and fee given 1-13-10 dld
|
Plan assigned to (TLW) | 1/4/2010 | | 1/12/2010 | | PASS |
Tim L. Woodard
|
|
|
1/12/2010 11:54:13 TLW - activity updated through activity BLDA022 from case BLD10-00014.
|
Routing - FIRE | 1/7/2010 | | 1/12/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 1/12/2010 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 1/12/2010 | | 1/12/2010 | | PASS |
Tim L. Woodard
|
|
|
Plan Review explains drinking fountain provisions. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/12/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/5/2010 | | 1/7/2010 | | PASS |
Tim L. Woodard
|
|
|
approved with explanation on why it was not considered an enclosed parking garage. TLW
|
Routing PW Sewer Rating | 1/5/2010 | | 1/5/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 1/5/2010 | | 1/5/2010 | | PASS |
Walt Baumgartner
|
|
|
Warehouse, no floor drains indicated on plans. Some quantity of racing fuel storage indicated.
|
Routing - PUBLIC WORKS | | | 1/5/2010 | | PASS |
|
|
|
|
Routing - Addressing | 1/4/2010 | | 1/4/2010 | | PASS |
April Wing
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/4/2010 | | DONE |
|
|
|
|
Application received | | 1/4/2010 | | | |
|
|
|
|