Third Notice | | 9/14/2011 | 9/20/2011 | | DONE |
|
|
|
credit given for value pulled under demo permit Bld09-02080
|
Third Notice | | 8/10/2011 | 8/30/2011 | | DONE |
|
|
|
faxed and e-mailed to Curtis Weedop
|
Third Notice | | 7/12/2011 | 7/27/2011 | | DONE |
|
|
|
faxed
|
Third Notice | | 5/31/2011 | 6/28/2011 | | DONE |
|
|
|
faxed
|
First Notice | | 6/5/2011 | 5/26/2011 | | DONE |
|
|
|
changed to third notice to match demo permit
|
Permanent Occupancy | | | 5/26/2011 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 5/18/2011 | 5/18/2011 | 5/18/2011 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|
Zoning Approval | 3/25/2011 | 3/25/2011 | 3/25/2011 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 3/23/2011 | 3/23/2011 | 3/23/2011 | | PASS |
Jim Storey
|
|
|
temp final ok pending p$z pw .
|
Zoning Approval | 1/19/2011 | 1/20/2011 | 1/24/2011 | | PASS |
Andrea Tuning
|
|
|
|
BLD-Final | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble temp final ok pending p$z pw .
|
FIRE-Final Inspection | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety passed with the exception of door hardware at one location first floor to be switched operable under any condition in the direction of egress. Combustible decking at the roof to be removed entirely as agreed to remain in compliance with NFPA 13 requirements as discussed and agreed with general contractors on site.
|
BLD-Final | 1/19/2011 | 1/19/2011 | 1/21/2011 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble pending fire.
|
FIRE-Conference | 12/23/2010 | 12/23/2010 | 12/23/2010 | A | DONE |
Forrest France
|
|
|
Regarding project related FIR permit work.
|
BLD-Wall cover | 11/24/2010 | 11/24/2010 | 11/24/2010 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble ceiling grid ok to cover but needs to fire proof around 1hr wall above ceiling phil will get this work done and schedule an inspection
|
BLD-Wall cover | 11/10/2010 | 11/10/2010 | 11/10/2010 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble. Ceiling grid inspection, 2nd floor only at interior rooms, all other grid existing.
|
CHANGE STATUS TO (ISS) | | | 11/9/2010 | | DONE |
Tisha Gallop
|
|
|
picked up plan mod
|
Plan assigned to (DRS) | 9/10/2010 | 9/10/2010 | 11/8/2010 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 11/5/2010 | | 11/8/2010 | | PASS |
Dan Stuart
|
|
|
Plan mod review complete. Mod of 9/10/10 redfuced scope of interior and exterior work due to budgeting reductions. Plan mod of 10/12/10 for new exterior windows and EIFS system as part of Mold Abatement, modified DRH09-00259.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 11/8/2010 | | |
|
|
|
|
Telephone call | | | 11/8/2010 | | DONE |
|
|
|
11-8-10 called Pat Walsh permit ready and fee given ///dld
|
Routing - PLANNING | 11/5/2010 | | 11/5/2010 | | PASS |
Andrea Tuning
|
|
|
All new exterior modified sheets require approval & initials / date for acceptance.
|
Routing - PLAN CHECK | 9/13/2010 | | 11/5/2010 | | PASS |
Dan Stuart
|
|
|
Plans routing to Planning for review and for modification to DRH09-00259.
|
BLD-Framing/Rough-in | 10/25/2010 | 10/25/2010 | 10/25/2010 | A | PASS |
Jim Storey
|
|
|
hard lid framing ok cooller area ok to instal cooller
|
Additional plans submitted | | | 10/12/2010 | | DONE |
|
|
|
New Sheets A-201A (Window / EFIS Elevations & replacement) & A-201B (Mold Abatement) received. Modification to DRH09-00259 required before plans can be approved for plan modification.
|
Plan resubmittals received | | | 10/12/2010 | | |
Dan Stuart
|
|
|
rec'd modification to existing plan mod to replace windows and eifs - sheets A-201A & A-201B
|
Plan Modification Accepted | | | 9/10/2010 | | |
Dan Stuart
|
|
|
Plan mod rec'd to- Delete two east side canopy covers over existing entrances. Delete new finishes (i.e carpet, paint, ceilings) in all "future" tenant or expansion rooms/spaces. Misc arch., mech, elec, minor changes or subtitutions for cost savings. Sheets - G-001; G-002; G-003; C1.50; C1.51; L-101; AD-101; AD-111; AD-112; AD-131; S-01-07; AD-201; A-101; A-102; A-111; A-112; A-113; A-114; A-121; A-122; A-131; A-201; A-211; A-212; A-213; A-214; A-215; A-216; A-301; A-311; A-312; A-501; A-502; A-503; A-504; A-601; A-602; A-603; A-611; SD-110; S-001; S-111; S-501; S-602; I-100; I-101; I-102; I-103; I-200; I-201; I-202; M-001; MD-002; MD-110; MD-111; MD-112; MD-211; MD-212; MD-311; MD-212; MD-411; MD-611; M-002; M-003; M-110; M-111; M-112; M-211; M-212; M-311; M-312; M-411; M-611; M-612; FPD-111; FPD-112; FP-111; F-112; ED-111; ED-112; ED-131; E-001; E-111; E-112; E-113; E-121; E-122; E-123; E-131; E-132; E-133; E-141; E-142; E-143; E-201; E-211; E-212; E-221; E-301; E-302; Q101; Q251; Q252; Q401; Q402; Q601
|
BLD-Wall cover | 9/7/2010 | 9/7/2010 | 9/7/2010 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble 2nd phase north side ok to cover/ gas storage ok.
|
BLD-Wall cover | 8/19/2010 | 8/19/2010 | 8/19/2010 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble up stairs ok to cover walls all area in main to the south ok to cover walls.
|
BLD-Other | 7/16/2010 | 7/19/2010 | 7/19/2010 | A | PASS |
Jim Storey
|
|
|
work in progress.
|
BLD-Aging Inspection | 7/14/2010 | 7/14/2010 | 7/16/2010 | | PASS |
Jim Storey
|
|
|
work in progress.
|
Issue & PRINT to be Invoiced | | | 4/5/2010 | | DONE |
|
|
|
|
Routing - FIRE | 3/9/2010 | | 3/10/2010 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans
|
Routing - PLAN CHECK | 3/10/2010 | | 3/10/2010 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/10/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/10/2010 | | DONE |
|
|
|
t/c w patrick walsh at ###-#### - permit ready and fees given - also need ACHD receipt
|
Permit Ready to Issue | | | 3/10/2010 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 1/8/2010 | | 3/10/2010 | | PASS |
Dan Stuart
|
|
|
3/10/2010 09:52:46 DRS - activity updated through activity BLDA022 from case BLD10-00044.
|
Routing - PUBLIC WORKS | 3/9/2010 | | 3/9/2010 | | PASS |
Beverly Hall
|
|
|
|
Routing - FIRE | 3/5/2010 | | 3/8/2010 | | |
Scott Arellano
|
|
|
*Plans taken to Planning by project manager*
See architects response #5 to plan review report - (4) Carbon Dioxide (CO2) gas cylinders - (2) active & (2) on stand-by.
|
Routing - PUBLIC WORKS | 3/8/2010 | | 3/8/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLAN CHECK | 2/10/2010 | | 3/5/2010 | | PASS |
Dan Stuart
|
|
|
Reviewed plan and engineering resubmittals of 3/4/10. Plan approved. Re-routing to fire code analyst for review.
|
Routing PW Solid Waste | 3/4/2010 | | 3/4/2010 | | PASS |
Peter J. McCullough
|
|
|
|
Plan resubmittals received | | | 3/4/2010 | | DONE |
|
|
|
received 2 corrections ,and 2 copies of sheets g-003,a-111,a-112,a-113,a-114,a-121,a-122,a-131,a-211,a-215,a-504,a-601,a-602,e-121,e-122,m-110,m-111 inserted by Pat Walsh and taken back to Dan S.
|
Routing PW Sewer Design | 1/11/2010 | | 3/4/2010 | | PASS |
Jon R. Gunnerson
|
|
|
No changes to sewer service.
|
Routing - FIRE | 2/3/2010 | 2/3/2010 | 2/10/2010 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 2/10/2010 | | FAIL |
|
|
|
Failed PW, Plan Check, Fire
|
Route to Impact Fee Review | 2/3/2010 | 2/8/2010 | 2/9/2010 | | PASS |
Cindy M. Gould
|
|
|
Remodle of existing building no impact fees
|
Plan resubmittals requested | | | 2/3/2010 | | DONE |
|
|
|
Copy of plan review resubmittal requirements e-mailed to architect.
|
Telephone call | | | 2/3/2010 | | DONE |
|
|
|
Called Structural Engineer, Chad Gilton, ###-####, to review differences between the submitted engineering design calcs and details and structural plan sheets. Told him I was requesting resubmittals through the architect to bring the two documents to indicate the same requirements.
|
Routing - PLAN CHECK | 1/20/2010 | | 2/3/2010 | | FAIL |
Dan Stuart
|
|
|
Erosion Sediment & Control permit is attacted to Demo permit BLD09-02080. Routing to fire code analyst for review.
|
Routing - Design Review | 1/19/2010 | | 1/20/2010 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH09-00259
|
Routing - PLUMBING | 1/14/2010 | | 1/19/2010 | | PASS |
Bill VanDegrift
|
|
|
provide 4" drain to water softener. update pipesizes at 1st floor restrooms to tempering station to match detail.
|
Routing PW Environmental | | | 1/14/2010 | | PASS |
Walt Baumgartner
|
|
|
Wastewater discharged from laboratory operations must comply with pH standards per City Code 8-14.
|
Routing - PUBLIC WORKS | 1/8/2010 | | 1/14/2010 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jon Gunnerson - ###-####
|
Application received | | 1/7/2010 | 1/8/2010 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCB | 1/8/2010 | | 1/8/2010 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/7/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/7/2010 | | DONE |
Tisha Gallop
|
|
|
|