Third Notice | | 7/7/2010 | 7/8/2010 | | DONE |
|
|
|
Final values done in combo with Bld10-00106
|
Permanent Occupancy | | | 6/8/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 6/4/2010 | 6/7/2010 | 6/7/2010 | A | PASS |
Jim Storey
|
|
|
Scott Beseman-please check drinking fountain for final-if ok please let Barb at permits know to send perm occ Thanks Phone #: ###-#### final ok
|
Telephone call | | | 6/7/2010 | | DONE |
|
|
|
Received phone call from Jim Storey, Structural Building Inspector, stating the accessible drinking fountains were installed and approved.
|
Second Notice | | 5/20/2010 | 6/4/2010 | | DONE |
|
|
|
|
First Notice | | 4/11/2010 | 5/10/2010 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/11/2010 | 3/12/2010 | 3/12/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety passed inspection.
|
BLD-Final | 3/11/2010 | 3/12/2010 | 3/12/2010 | P | PART |
Jim Storey
|
|
|
Scott Phone #: ###-#### tco ok
|
Temporary Occupancy | 3/12/2010 | 6/10/2010 | 3/12/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (DRS) | 1/26/2010 | | 3/12/2010 | | PASS |
Dan Stuart
|
|
|
3/12/2010 06:46:11 DRS - activity updated through activity BLDA022 from case BLD10-00105.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/11/2010 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 3/11/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/11/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/11/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 3/9/2010 | | 3/9/2010 | | PASS |
Cody Riddle
|
|
|
CUP10-00008 10 DAY APPEAL
Okay to issue permit at 5:00 on 3/11/10. CER
|
Routing - PLAN CHECK | 2/24/2010 | | 3/9/2010 | | PASS |
Dan Stuart
|
|
|
Approved with comments & conditions attached to and red-lined on plans. Issuance pending the 10 day appeal period for CUP10-0008 at 5pm on 3/11/10.
|
Plan resubmittals received | | | 3/4/2010 | | |
Tisha Gallop
|
|
|
received response, letter to Jason Blais, revised cert of value, and two copies of plan sheets A0.0, A1.0, A2.0; taken to Dan Stuart
|
Received Certificate of Value | | | 3/4/2010 | | DONE |
Tisha Gallop
|
|
|
received revised cert of value with resubmittals; new project value is $2,000; ele $1,000; mech $1,000; plm $1,000 (this is same as original cert of value submitted with application but valuation was typed in wrong at initial $21,000.)
|
Routing - FIRE | 2/19/2010 | 2/19/2010 | 2/24/2010 | | PASS |
Tim Frost
|
|
|
|
1st review completed | | | 2/24/2010 | | FAIL |
|
|
|
Failed Planning and Plan Check
|
Route to Impact Fee Review | 2/19/2010 | 2/24/2010 | 2/23/2010 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Plan resubmittals requested | | | 2/19/2010 | | DONE |
|
|
|
Copy of plan review e-mailed to architect. Resubmittals required.
|
Routing - PLAN CHECK | 1/29/2010 | | 2/19/2010 | | FAIL |
Dan Stuart
|
|
|
Do not issue until CUP is approved and 10 day appeal period is over.
Resubmittals required. Copy of plan review e-mailed to architect. Plans routed to fire code analyst for review.
|
Routing - PUBLIC WORKS | 1/26/2010 | | 1/29/2010 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLANNING | 1/29/2010 | | 1/29/2010 | | FAIL |
Cody Riddle
|
|
|
Cody Riddle - CUP???
1/29/10-A temporary zoning certificate was previously issued. It required a conditional use permit application be submitted by January 26, 2010. That application has yet to be submitted as required.
|
Routing - Addressing | 1/29/2010 | | 1/29/2010 | | PASS |
April Wing
|
|
|
|
Routing PW Sewer Rating | 1/28/2010 | | 1/28/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 1/28/2010 | | 1/28/2010 | | PASS |
Walt Baumgartner
|
|
|
catering warming/serving kitchen area. No food prep or cooking.
|
Intake Approval | | | 1/26/2010 | | PASS |
Carl D Madsen
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/26/2010 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/26/2010 | | DONE |
|
|
|
|
Pending Assignment by JCB | 1/26/2010 | | 1/26/2010 | | DONE |
Jason Blais
|
|
|
|
Application received | | 1/20/2010 | 1/20/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/20/2010 | | FAIL |
|
|
|
|